You are on page 1of 9

RISK ASSESSMENT AND ANALYSIS

SEVERITY / CONSEQUENCE (Impact/Hazard Effect) (Where an event has more than one ' Loss Type ', choose the ' Consequence' with the highest rating)
Loss Type Additional "Loss Types" may exist for an
event: Identify & rate accordingly (1) Insignificant (2) Minor (3) Moderate (4) Major (5) Catastrophic
Single Fatality or Loss of Quality of Life / Irreversible impact
(S/H) Harm to People (Safety/Health) First Aid Case/Exposure to Minor Health Risk Medical Treatment Case/Exposure to Major Health Risk Loss Time Injury / Reversible Impact on Health on Health Multiple Fatalities / Impact on health Ultimately Fatal

Material Environment harm (RST) Serious environmental harm


(EI) Environmental Impact Minimal environment harm incident with workplace Material Environment harm (RST) incident (RMT) Major environmental incident (RLT) Major environmental harm – Incident Irreversible

(BI/MD) Business Interruption / Material / Fire No disruption to operation / 1000 SR to Less than 10k SR Brief Disruption to Operation / 10k SR to Less Than 100k SR Partial Shutdown/100k SR to Less than 1M SR Partial Loss of Operation/1M SR to Less than10M SR Substantial or Total Loss of Operation / 10M SR and more
Damage & Other Consequential Losses

LIKELIHOOD Examples (Consider Near-Hits as well as actual events) RISK RATING / PROFILE
The unwanted event has occurred frequently : Occurs in order of (1) or more per year & is likely to
(5) ALMOST CERTAIN reoccur within 1 year 5 (L) 10 (M) 15 (H) 20 (Ex) 25 (Ex)
The unwanted event has occurred infrequently : Occurs in order of less than once per year & is
(4) LIKELY likely to reoccur within 5 yrs. 4 (L) 8 (M) 12 (H) 16 (Ex) 20 (Ex)

(3) POSSIBLE The unwanted event has occurred in the business at some time: or could happen within 10 years. 3 (L) 6 (L) 9 (M) 12 (H) 15 (H)

(2) UNLIKELY The unwanted event has occurred in the business at some time: or could happen within 20 years. 2 (L) 4 (L) 6 (L) 8 (M) 10 (M)
The unwanted event has never known to occur in the business or it is highly unlikely to occur
(1) RARE within 20 years. 1 (L) 2 (L) 3 (L) 4 (L) 5 (L)

Stop operation and review controls - Eliminate, Proactively manage & implement specific Actively manage & monitor – Additional Risk acceptable – Monitor & manage as
Project Name : DD-2021-170 – Bujairi Public Realm Wayfinding (Darriyah Riyadh) GUIDELINES FOR RISK MATRIX avoid risk & implement high priority action plans controls/action plans-Review after 7 days controls is advised & review after 30 days appropriate with frequent review

Contract No. : RISK RATING 16 To 25 12 To 15 8 To 10 1 To 6


RA Number: 01:‫رقم تقييم المخاطر‬ RISK LEVEL (Ex) - Extreme (H) - High (M) - Medium (L) - Low
RA TEAM (NAMES) DESIGNATION SIGNATURES WORKPLACE / TASK / ACTIVITY / PROCESS NAME: DEPARMENT / AREA: Civil

1. R.S.REDDY Safety Engineer DATE:20/12/2023 :


2. Mr. DEBASISH MONDAL Site Manager NEXT REVIEW DATE: 20/12/2024:
EXCAVATION WORK/ Foundation Installation
3. Mr. MANOJ KUMAR MISHRA Operation Manager APPROVED BY MANAGER / SUPERVISOR: MANOJ KUMAR MISHRA
4. SIGNATURE:
RISK
HAZARD IDENTIFICATION CONTROL ASSESSMENT RISK REDUCTION ACTION PLAN

Consequence

Consequence
Risk Issue

Risk Ranking
Likelihood

Likelihood
(Possible Incident) (What can go wrong) (Improve Existing Controls/ Implement Follow up By Whom (Name) & By

Ranking
Workplace/ Activity/ Process/ Hazards Existing Controls Controls
Item

Equipment/ materials (Accident/ Ill health to person, fire or new controls) When (Date) Implemented (Yes
/ No)
property loss)

• Permit to Work shall be obtained as a pre- • Permit Receiver shall be trained and
requisite to perform work authorized by the Manager to receive a
• Work shall not be started until duly approved Permit to Work
• Accident resulting serious injury or death to Permit to Work is available at site and that Safety ●Permit Receiver shall be responsible to
Toolbox meeting was conducted 3 2 6 oversee for the safety of all workers under 1 2 2 Supervisor/Engineers/Workers YES
worker
his Permit to Work
• Work shall not proceed without the presence of
approved Permit to Work with the Permit Receiver
• Unathorized work to be performed within overseeing the activity
a defined location and boundary ● A safe work practice shall be implemented to • All workers attending the toolbox meeting
reduce the possibilities of accident / incident shall sign on the attendance sheet attached
to the specific Permit to Work
●Permit Receiver and Permit Issuer shall visit
• Significant property and appurtenances together at the site to ensure that workplace 3 2 1 2 Supervisor/Engineers/Workers YES
damage hazards are adequately identified and mitigating
measure shall be established

● Permit to Work shall be displayed at the ● All workers shall attend the toolbox
worksite meeting on a daily basis conducted by the
● Permit Receiver shall not leave the area for the Supervising Engineer, Foreman and Permit
• Loss of production whole duration of work
2 2 4 Receiver 0 Supervisor/Engineers/Workers YES
1 Obtain Permit to Work
• Uncontrolled personnel entering a
restricted location
●Permit Receiver shall account all workers under
his Permit to Work before the start of work
• Significant cost due to damages

● Manager, Supervisor, Foreman and all workers ●


shall adhere to all requirements set forth in the ●
Permit to Work, Risk Assessment, Method
• Unidentified hazards with unplanned Statement, Job Safety Procedure and other
• Governmental violation relevant safety practices and standards 0 0
safety mitigating measures

1 of Rev. 2 (08 - April - 2019) Project Business Unit


● Site Manager, Supervising Engineer, Foreman ●
shall designate a Permit Receiver competent ●
enough to take responsibility in securing the
• Inadequate coordination and area control Permit to Work
• Environmental complaint 0 0
protocol

• Obtain a valid wok permit • Ensure that Tool Box Talk is conducted
• Ensure that all workers undergo safety induction daily by the Supervisor and Foreman
that discuss safety policies and standards of • Safety trainings must be conducted
• Lack of safety awareness and knowledge • Engage in accident resulting injury to company and Saudi Electricity Company periodically as work requires
for the job personnel due to lack of safety awareness • Conduct Tool box talk and discuss safe work
procedure, RA, and JSP prior to the start of work. 3 2 6 1 2 2 Supervisor/Engineers/Workers YES

• Ensure that all workers are provided with • Close supervision is required. Supervisor
required mandatory PPEs such as: Helmet (ANSI and foreman must be present at site.
Z89.1, CE EN397), Safety Glass, Safety Shoes, Cover • Ensure presence of safety personnel
• Working without wearing appropriate • Hand injury all, Safety Gloves, Dust Mask • Conduct trainings for PPE as per activity.
• Use hand gloves for hand protection 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
Personal Protective Equipment (PPE) • Arm injury

• Only up to 20 kg is allowable for each worker to • Ensure that all personnel are trained in
lift. proper manual handling
• Physical injury from slip / trip / fall • Ensure that access has no obstruction
• Improper manual handling • Back injury • If the load is heavier, buddy system is advised 0 0
• Arm injury

• All operators must be trained and certified by a • Only operators that are certified and
third party trained can operate the equipment at the
• All equipment must be inspected and certified by site
• Failure of equipment may lead to accident or a 3rd party • All drivers and operators shall undergo
• Equipment and operator without 3rd party Defensive Driving Safety Training
incident
certificate • Daily tool box talk must be conducted
3 2 6 1 2 2 Supervisor/Engineers/Workers YES
before any work commences

• Daily equipment inspection must be carried out • Equipment Operator shall be oriented on
by the operator how to use and fill out the checklist properly
• All operators must be trained in conducting • Equipment inspection checklist shall be
• Physical / fatal injury inspection of equipment using the checklist provided and conducted in a daily basis
• All equipment must be inspected regularly using 2 3 6 1 2 2 Supervisor/Engineers/Workers YES
• Damage of property
checklists by the operator
• Lack of knowledge in conducting inspection
using checklist
• The equipment to be used shall be in good • Supervising Engineer and Safety Officer
condition shall ensure that inspection was carried out
Mobilization / Inspection of heavy • The equipment must be suitable to perform the thoroughly
2 equipment (excavator and dump • Physical injury from slip, trips and fall task 0 0
trucks) at site

• Establish equipment access and shall be free • Site management plan shall be prepared,
• Vehicular accident from any obstruction approved and implemented to avoid
• Accident resulting Injury to personnel • Designate parking area property damage and personnel accident
0 0

• Struck by moving equipment and vehicle • Designate location for unloading of materials ●
• Designate spotter and flagman to guide all ●
• Property damage of adjacent structure or equipment and personnel movement
0 0
appurtenances

• All heavy equipment and its driver/operator shall • All heavy equipment operator and driver
hold a valid third party certification authorizing shall be oriented with the proper use on how
them on the specified equipment to operate to fill out the daily inspection checklist
• Select and mobilize only good condition • Lease equipment and operator must be
equipment from establish company
• Incompetent equipment operator or driver • Equipment certification and registration must be • All operator and driver must sign the
• Property damage, fatality or injuries during secured and available drivers’ pledge
2 3 6 1 2 2 Supervisor/Engineers/Workers YES
the operation of the equipment. • Operator and driver must have certification and
license

2 of Rev. 2 (08 - April - 2019) Project Business Unit


• All heavy equipment shall be inspected by the • Pre-selection of equipment and operator
authorized operator on a daily basis to ensure that should establish
equipment is in good working condition before
using to the site
• Heavy equipment shall not be used if found any
defects or damage that might affect its safe
• Dilapidated equipment / Damage or • Property damage, fatality or injuries during operation
• Repair of heavy equipment shall not be done on 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
defective condition of equipment the operation of the equipment.
the site. It must be brought to the designated work
shop and only certified mechanic shall make repair
of the equipment

• Implementation of Log-in and Log-out from the • Recording and registry for all equipment,
security post. operator and driver shall be made.
• Unauthorized entry of the equipment to • Equipment / vehicle insurance
• Property damage, fatality or injuries during
the site. 0 0
the operation of the equipment.

• Locate underground services referring to the site • Report accordingly any noticed
• Damage to property map / drawing. underground utility
• Use suitable detectors to check and locate any 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
underground utilities.

• Supervisor and Foreman shall closely monitor to ●


• Damage to underground utlities prior to ensure accurate reading is obtained ●
Checking and verification of any
3 excavation due to failure to perform pre- • Disruption to production 0 0
underground utilities
checks.

• Worker who will perform the verification shall be ●


knowledgeable and trained in using and ●
• Accident resulting in injury to worker interpreting the instrument 0 0

• Operator must be competent, trained, and • Flagman training must be conducted


experienced of the task and must be 3rd party • Acquire as-built drawings of underground
certified holder existing facilities prior to any task to be done
• Trained and competent flagman must be • Close supervision is required
assigned for all heavy equipment operation • Supervisor and foreman must be present in
• Impact by a sudden operation of equipment • Heavy equipment shall not be allowed at any the site.
may cause serious injuries or property damage time without the presence of dedicated flagman • Conduct safety toolbox meeting and
• Toolbox meeting must discuss the safe use of discuss the work procedures prior to start of
equipment to be conducted by Foreman work.
• Struck by excavator moving / operating • Only trained competent operators shall be • Supervising Engineer and Safety Officer
assigned to operate any heavy equipment during 4 2 8 shall attend and ensure that toolbox meeting 1 2 2 Supervisor/Engineers/Workers YES
equipment
mechanical excavation works was conducted and discussed according to
the risk assessment of the activity

• All underground utilities must be identified, • At all stages of the excavation, a competent
marked with a visible warning or relocated, fixed person must supervise the work and all
and secure workers must be given clear instructions on
• Area to be excavated must be scanned for working safely in the excavation.
underground services and utilities • Ensure proper and adequate supervision by
• Conduct test pit. Manual excavation is highly supervisor/ foreman.
required to prevent any damages to any existing • Site safety officer must ensure that all
underground utilities due to machine excavation excavations are provided with necessary
• Permit To Excavate must be issued before work safety requirements as per SEC safety
commences standard.
• Spotter must be assigned to guide the heavy • Close supervision is required
equipment operator specially if underground • Supervisor and foreman must be present in
utility is found the site
• Impact and damage to existing plant / • Hand digging only in the vicinity of underground • Training for excavation works must be
• Presence of plant / underground services services 3 2 6 conducted 1 2 2 Supervisor/Engineers/Workers YES
underground facilities
• Properly monitor when hand digging the vicinity • Tool Box Talk shall be provided to the
of underground services workers prior to the start of work
• Electrical cables adjacent to excavation shall be
isolated by electrician using permit to isolate

3 of Rev. 2 (08 - April - 2019) Project Business Unit


• All underground utilities must be identified, ● • Ensure proper housekeeping to avoid
marked with a visible warning or relocated, fixed unnecessary materials
and secure ●
• Area to be excavated must be scanned for
underground services and utilities
• Conduct test pit. Manual excavation is highly
required to prevent any damages to any existing
underground utilities due to machine excavation
• Permit To Excavate must be issued before work
commences
• Spotter must be assigned to guide the heavy
equipment operator specially if underground
utility is found
• Hand digging only in the vicinity of underground
services
• Properly monitor when hand digging the vicinity
of underground services
• Falling of workers / equipment / tools into • Electrical cables adjacent to excavation shall be
• Unprotected edges of excavation excavation resulting to personnel injury, isolated by electrician using permit to isolate 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
fatality, property damage • Fall prevention barriers (barricades) with signs
shall be erected around excavation at least 1
meter away
• Concrete Jersey barrier installed at a safe
distance from excavation, preventing vehicles from
falling into the excavation. Standard barricading
for UG shall be complied accordingly.
• Wear appropriate PPE – hard hats, safety glasses,
safety mask, safety gloves and safety shoes

• Check the condition of excavation at all times for • Report any signs of cave-in to supervisor.
possibility of collapse or cave in • Excavation training must be conducted
• Excavation walls that are deeper than 1.5 meter prior to start of activity
must be sloped / benched or shored depending on • Hazard awareness and best practices
Perform excavation using heavy the type of materials being excavated relevant to excavation must be conducted.
4 equipment such as skid loader, • Erosion control measures must be considered • Provide hole watcher to monitor the entry
backhoe, Excavator when using dewatering operations & exit of entrant
• Provide temporary sum pit and sub pump to • Practice good housekeeping while working
remove water inside excavation in and around excavations and trenches
• Unstable soil condition (due to type, • If equipment is being used above the trench,
• Cave-in (sudden collapse of soil) 0 0
vibration, and water) then no operatives should be in the trench when
the machine is in use • Stability of
soil must be ensured

• All excavated materials must be a minimum of 1 • Provide Gas Test equipment and conduct
meter away from the edges of excavation or gas test by competent persons if suspected
totally removed from the site. to have a buildup of unknown gas
• Excavation must be properly barricaded • Contact the site area
physically, and DANGER DEEP EXCAVATION signs in advance and agree that access to the
must be provided specific area is acceptable
• Heavy equipment parking must be a minimum of • Follow safe work practices
• Buildup of harmful gases in the excavation • Health hazards (asphyxiation / collapse due 3 meters away from the edges of excavation • Conduct confined space training for the
• Excavations > 4 ft. deep (1.20 m) that may 3 2 6 involved personnel 1 2 2 Supervisor/Engineers/Workers YES
for 1.2 meters confined space to inhalation of hazardous gases)
develop hazardous atmospheres shall be
considered a confined space

4 of Rev. 2 (08 - April - 2019) Project Business Unit


• Use safe access while entering and exiting • Hoses / cables shall be positioned in such a
excavations and trenches way that it will not create obstruction on the
• Each excavation must be provided with proper access and work areas
access and egress • Warning signs and safety barricades shall
• Ladders must be secured when workers are be used whenever a slip, trip or fall hazard
required to work inside the excavation for manual has been identified but cannot be corrected
excavation or removed immediately
• Avoid taking short cuts or jumping in and out of
excavation
• Aisles, stairs, and passageways shall be kept clear
• Materials must not be carried in a manner that
will provide obstruction in the way ahead
• Materials shall be stored in designated areas
• Materials and tools shall be stored away from
exposed edges
• Ensure proper access and egress in the
• Personal injury due to slip and trip hazards excavation
• Poor access and egress from the obstruction of materials on access / • Provide proper illumination or blinker lights
3 2 6 1 2 2 Supervisor/Engineers/Workers YES
egress along the excavation in order to be identified
during night time.
• No tools and equipment shall be stored close to
the edge of excavation.

• Modify work schedules and arrange frequent • Establish a complete heat illness
rest periods with water breaks in shaded area prevention program
• Provide adequate cool water to workers close to • Provide heat stress training, and its
the work area. prevention
• Ensure workers drink at least a pint of
water every hour
• Workers must be advised to drink plenty of
fluids
• Workers must be advised to drink water
more often and even before they feel thirsty
• Working under direct sunlight • Heat exhaustion/ stress 3 2 6 • Workers must avoid beverages that contain 1 2 2 Supervisor/Engineers/Workers YES
alcohol or caffeine.
• Workers must wear light-weight, light-
colored, and loose-fitting clothes

• Use an approved dusk mask (such as 3M, etc.) • Water sprinkling shall be carried out to
• Dust control must be thoroughly done around avoid dust emissions, where necessary
• Exposure to dust the excavation area • Supervisor and foreman must ensure
• Respiratory illness 0 adequate monitoring of activities 0

• Provide trained flagman equipped with green • All heavy equipment operator including
and red flags to control the moving equipment rentals shall attend Defensive Driving
• Serious accident and even death to personnel • There shall be no working personnel inside the Training for the driver
• Struck by moving equipment (such as excavation while excavation and loading of soils is
dump truck, etc.) ongoing 2 3 6 1 2 2 Supervisor/Engineers/Workers YES
• Conduct tool box talk prior start to work.

• Establish safe distance from equipment to the • Equipment must have back-up alarms
edge of excavation
• Concrete Jersey barrier shall be maintained and
• Falling of heavy equipment into the installed at a safe distance from excavation,
• Significant property damage preventing vehicles from falling into the excavation 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
excavation

• Provide adequate shoring with approve shoring • Supervisor and foreman must ensure
Loading of excavated soils to a materials on an excavated area adequate monitoring of activities
5 • Soil cave in and collapse • Physical injury / property damage • Provide complete physical barricades with 2 3 6 1 2 2 Supervisor/Engineers/Workers YES
dump truck
flagman standing outside the barricades

5 of Rev. 2 (08 - April - 2019) Project Business Unit


• All drivers must be trained and have a driving • Proper training must be provided to the
license operator / driver
• Filled dump trucks shall be covered with screen
or equivalent materials to prevent spoils from
spilling on the road while transporting to dump
• Incompetent driver • Disruption to activity and productivity site 2 3 6 1 2 2 Supervisor/Engineers/Workers YES
• Foreman shall ensure that cover is installed
properly

• Use an approved dusk mask (such as 3M, etc.) • Water sprinkling shall be carried out to
• Dust control must be thoroughly done around avoid dust emissions, where necessary
• Respiratory illness the excavation area
• Exposure to dust 0 0

• Provide trained flagman equipped with green


• Struck by moving equipment (such as and red flags to control the movement of
• Vehicular accident resulting to injury or ill equipment.
dump truck, etc)
health to worker or bystander • Suitable traffic management plan shall be
established such as segregation of pedestrian lanes 2 3 6 0 Supervisor/Engineers/Workers YES
from vehicle access ways.

• Slowly dump the soil to minimize the airborne of • Check surrounding for any equipment or
dust materials that might be covered during
• Exposure to Dust • Ill health to worker due to inhalation of dust 3 2 6 dumping of excavated soil 1 2 2 Supervisor/Engineers/Workers YES

• Driver shall follow instruction from the foreman • Driver shall be trained and follow defensive
Shifting and offloading of excavated • Reckless driving driving technique
6 • Significant damage to property 0 0
soils into the designated area
• Filled dump trucks shall be covered with screen • Driver shall follow designated route going
or equivalent materials to prevent spoils from to the dumping area
spilling on the road while transporting to dump
• Vehicular accident resulting to injury or ill site
• Busy traversed road • Foreman shall ensure that cover is installed
2 3 6 1 2 2 Supervisor/Engineers/Workers YES
health to worker or bystander
properly.

• Designated offloading (dump site) shall be • Designated dumping area shall be away
established with suitable demarcation and signs from residential area
posted.
• Populated area • Ill health to worker due to inhalation of dust 2 3 6 1 2 2 Supervisor/Engineers/Workers YES

• Conduct and maintain daily housekeeping ●


• Foreman must designate 1 or 2 persons to ●
• Unwanted materials laid inside and outside maintain good housekeeping.
the excavation area
• Physical injuries from slip, trips and fall 2 0 0

• Maintain daily proper housekeeping ●


• Additional person for housekeeping must be ●
provided if necessary.
• Ladder and hand tools that block in the • Provide designated trash disposal area so
• Physical injuries from slip, trips and fall 0 0
walkway anybody can perform housekeeping

• Manual handling can lead to musculoskeletal • Facilitate training for manual handling.
• Manual handling disorder • Observe proper posture during manual lifting,
pushing, pulling, etc. 2 3 6 0 Supervisor/Engineers/Workers YES
Housekeeping, Clearing the area
with all used materials, tools and
7 equipment and brought to the
designated storage and disposal • Provide storage box for cables • • Daily inventory of the equipment •
area Labeling of storage box (good items, scrap / Training / awareness regarding the
• Materials lying on the ground • Property damage 3 2 6 1 2 2 Supervisor/Engineers/Workers YES
damage items, by capacity, etc.) segregation of waste
• Immediate disposal or sending the damage one
•toRemove
the storeallkeeper
unwanted / protruding materials / • Good housekeeping at the site
object at the site • Daily toolbox meeting
• Protruding object / materials at the site • Accident resulting injury to worker 0 0

• Provision of standby fire extinguisher • Records and registry for fire extinguisher
• Periodical inspection and / or color coding for • Records /
fire extinguisher registry for the quantity of waste disposed
• Provision of waste skip in the strategic location
• Uncollected / scattered rubbish • Fire at the site with marking 2 3 6 1 2 2 Supervisor/Engineers/Workers YES
• Provision of color coded waste bins at the site

6 of Rev. 2 (08 - April - 2019) Project Business Unit


• Permit Receiver shall ensure that housekeeping
• Significant property and appurtenances in done before, during and after the work
damage • Electrical equipment shall be properly secured,
• Unsecured electrical equipment, energized distribution board closed and padlocked
equipment 2 2 4 0 Supervisor/Engineers/Workers YES

• All waste materials generated from the work • Supervising Engineer and Foreman shall
shall be disposed properly and shall not be left adhere to the proper housekeeping and
• Undisposed waste materials • Governmental violation unattended at the worksite 2 3 6 storage of materials at the designated 1 2 2 Supervisor/Engineers/Workers YES
location
• Permit Receiver shall account all worker under ●
his Permit to Work and ensure all have signed out ●
• Accident resulting serious injury or death to on the attendance sheet and clear of the area
• Unaccounted workers 2 3 6 0 Supervisor/Engineers/Workers YES
8 Closing of Permit to Work worker

• Site Manager shall be responsible on the ●


effective implementation of the Permit to Work ●
• Inadequate communication • Loss of production 2 2 4 0 Supervisor/Engineers/Workers YES

• All materials used at the site such as chemicals, ●


flammable and combustible materials shall be ●
• Poor storage of chemical, flammable and stored at the designated storage at the end of
• Environmental complaint 0 0
combustible materials and etc. each day

• Permit Issuer shall visit the work location to • Mobile equipment shall properly parked on
verify good housekeeping was conducted before a designated equipment laydown
• Unattended unsafe condition • Significant cost due to damages closing the Permit to Work 2 2 4 1 2 2 Supervisor/Engineers/Workers YES

● 0 ● 0

● ●

0 0

● ●

0 0
● ●

7 of Rev. 2 (08 - April - 2019) Project Business Unit


RA Prepared by : RA Accepted by : RA Approved by SEC / Safety Rep: RA Aprroved by SEC-HV&EHVPD:
Name & Sign Name & Sign Name & Sign Name & Sign
Desgination Desgination Desgination Desgination
Date Date Date Date

You might also like