SEVERITY / CONSEQUENCE (Impact/Hazard Effect) (Where an event has more than one ' Loss Type ', choose the ' Consequence' with the highest rating)
Loss Type Additional "Loss Types" may exist for an
event: Identify & rate accordingly (1) Insignificant (2) Minor (3) Moderate (4) Major (5) Catastrophic
Single Fatality or Loss of Quality of Life / Irreversible impact
(S/H) Harm to People (Safety/Health) First Aid Case/Exposure to Minor Health Risk Medical Treatment Case/Exposure to Major Health Risk Loss Time Injury / Reversible Impact on Health on Health Multiple Fatalities / Impact on health Ultimately Fatal
(BI/MD) Business Interruption / Material / Fire No disruption to operation / 1000 SR to Less than 10k SR Brief Disruption to Operation / 10k SR to Less Than 100k SR Partial Shutdown/100k SR to Less than 1M SR Partial Loss of Operation/1M SR to Less than10M SR Substantial or Total Loss of Operation / 10M SR and more
Damage & Other Consequential Losses
LIKELIHOOD Examples (Consider Near-Hits as well as actual events) RISK RATING / PROFILE
The unwanted event has occurred frequently : Occurs in order of (1) or more per year & is likely to
(5) ALMOST CERTAIN reoccur within 1 year 5 (L) 10 (M) 15 (H) 20 (Ex) 25 (Ex)
The unwanted event has occurred infrequently : Occurs in order of less than once per year & is
(4) LIKELY likely to reoccur within 5 yrs. 4 (L) 8 (M) 12 (H) 16 (Ex) 20 (Ex)
(3) POSSIBLE The unwanted event has occurred in the business at some time: or could happen within 10 years. 3 (L) 6 (L) 9 (M) 12 (H) 15 (H)
(2) UNLIKELY The unwanted event has occurred in the business at some time: or could happen within 20 years. 2 (L) 4 (L) 6 (L) 8 (M) 10 (M)
The unwanted event has never known to occur in the business or it is highly unlikely to occur
(1) RARE within 20 years. 1 (L) 2 (L) 3 (L) 4 (L) 5 (L)
Stop operation and review controls - Eliminate, Proactively manage & implement specific Actively manage & monitor – Additional Risk acceptable – Monitor & manage as
Project Name : GUIDELINES FOR RISK MATRIX avoid risk & implement high priority action plans controls/action plans-Review after 7 days controls is advised & review after 30 days appropriate with frequent review
1. DATE: اتاريخ:
2. NEXT REVIEW DATE / تاريخ مراجعة القادم:
TEMPORARY PERIMETER FENCING
3. APPROVED BY MANAGER / SUPERVISOR:اعتمد من قبل
4. SIGNATURE:التوقيع
RISK
HAZARD IDENTIFICATION/تحديد المخاطر CONTROL/وسائل التحكم ASSESSMENT RISK REDUCTION ACTION PLAN/ خطة العمل لتقييم المخاطر
تقييم المخاطر
Consequence
Consequence
Risk Issue
Risk Ranking
Likelihood
Likelihood
الرقم المتسلسل
(Possible Incident) (What can go wrong) (Improve Existing Controls/ Implement Follow up By Whom (Name) & By
Ranking
Workplace/ Activity/ Process/ Controls
Hazards Existing Controls
Item #
Implemented (Yes
Equipment/ materials
االخطار (Accident/ Ill health to person, fire or وسائل التحكم المتوفرة new controls) When (Date) / No)/هل تم التنفيذ
المواد/ المعدات/موقع العمل ظمهمة العمل property loss) التحكم والسيطرة االضافية التاريخ/المهمة المعنية بالتنفيذ ال/ نعم
/ المخاطر المحتملة/
• Permit to Work shall be obtained as a pre- • Permit Receiver shall be trained and
requisite to perform work authorized by the Manager to receive a
• Work shall not be started until duly approved Permit to Work
• Accident resulting serious injury or death to Permit to Work is available at site and that Safety ●Permit Receiver shall be responsible to
Toolbox meeting was conducted 0 oversee for the safety of all workers under 0
worker
his Permit to Work
• Work shall not proceed without the presence of
approved Permit to Work with the Permit Receiver
• Unathorized work to be performed within overseeing the activity
a defined location and boundary ● A safe work practice shall be implemented to • All workers attending the toolbox meeting
reduce the possibilities of accident / incident shall sign on the attendance sheet attached
to the specific Permit to Work
●Permit Receiver and Permit Issuer shall visit
• Significant property and appurtenances together at the site to ensure that workplace
damage hazards are adequately identified and mitigating
measure shall be established
● Permit to Work shall be displayed at the ● All workers shall attend the toolbox
worksite meeting on a daily basis conducted by the
● Permit Receiver shall not leave the area for the Supervising Engineer, Foreman and Permit
• Loss of production whole duration of work 0 Receiver 0
1 Obtain Permit to Work
• Uncontrolled personnel entering a
restricted location
●Permit Receiver shall account all workers under
his Permit to Work before the start of work
• Significant cost due to damages
● Heavy Equipment to be used at the site must ● Isolate the area and provide signboards.
have a valid third party inspection certification ●Use mobile equipment if available
• Severe accident result in physical injury or such as TUV
• Construction equipment malfunctioning, • Monthly equipment inspection and color coding.
death
• Fire extinguisher required on the unit (20 lbs. 0 0
capacity).
● Daily inspection of equipment by operator/driver ● Conduct a spot inspection to all tools and
using checklist specific to their equipment shall be equipment prior to commence the work.
• Environmental pollution due to leaking of strictly implemented.
• Fuel/oil leaks/ground contamination 0 0
fuel/oil
● Driver and operator shall be oriented to the site • No flagman no movement of the
condition equipment policy
• Accident resulting injuries to the operator or • Provide trained flagman with reflective vest
driver once struck the structure along with Red and Green flags. 0 0
• Fastened of seat belt
• Access must be properly compacted and even • Foreman / supervisor must ensure the
• Workers are advised / instruct to move away competency of the operator / driver
• Significant property damage to adjacent from the equipment.
• Positioning of equipment 0 0
structure
• Remind the operator and driver to follow the • Daily toolbox meeting must be conducted
signal of the flagman by the Supervisor or Foreman discussing the
• Injuries to other personnel involved to the
0 risk assessment 0
activity
• Housekeeping shall be done before, during and • Designate a dedicated personnel who is
• Poor housekeeping in the workplace / after the job familiar with the site management plan to
• Accident resulting injury to personnel • Designated access shall be free from any guide all personnel and equipment in loading
Unorganized materials and access
obstruction 0 and unloading of materials and equipment 0
• Designate location for unloading of personnel • Site management plan shall be prepared
and materials be stored only on a designated indicating all the location of personnel and
storage area equipment access, parking areas, offices,
materials storage area, disposal area,
• Area congestion • Vehicular accident 0 hazardous waste disposal and storage area, 0
rest shelter, evacuation area and etc.
• Struck by moving equipment and vehicle • Establish equipment access and shall be free ●
• Accident resulting Injury to personnel from any obstruction 0 ● 0
• Workers shall use appropriate and good • Ensure monthly inspection for all hand
condition hand tools tools
• Defective hand tool shall not be use and must be • Certified first aider must be available
taken out of the project • Provision of first aid kit
• Use appropriate hand gloves
• Personal injury (laceration, etc.) due to • Avoid damaged tools and machine
• Defective, damaged and improvised tools • Supervisor and foreman must ensure the tools 0 0
contact with sharp edge, tools and materials
and materials are free from damage
• No modification of tools and machine
• Boring hole shall be done using heavy equipment • Defective equipment shall only be repaired
• Boring equipment shall only be operated by by authorized technician and shall be
• Serious accident to personnel resulting into competent and third party certified operator subjected for re-inspection after repair
• Using damage or defective equipment
multiple injury or death • Provide spotter when equipment is in use 0 0
• Boring hole equipment shall have 3rd party • There shall be single and dedicated signal
Boring hole for the temporary • Struck by moving and operating boring inspection or at least mechanical inspection and man to guide the operator where to position
4 certified to be in good condition 0 the boring tool 0
fencing post equipment • Property damage
• All workers shall wear prescribe PPE with • Only authorized and competent workers
reflective vest shall be allowed at the working area
• Conduct daily toolbox meeting to discuss
• Inadequate communication between hazard of boring equipment and how to work with
• Temporary to permanent disability 0 0
workers / Unfamiliar worker it safely
• Proper manual lifting shall be observed • Tandem manual lifting shall be done by tall
• Temporary to permanent physical injury • Use mobile lifting equipment If manual lifting is and strong workers
• Ill health not possible 0 0
• Manual heavy lifting of post
• When the post is too heavy for a single person, it • Proper communication and movement
5 Erection of fencing post manually shall be lifted by two to three person to position coordination shall be observed
• Back injury or sprain on the hole 0 0
• Eye burning sensation or temporary blindness • Welder shall be competent to perform the work • Welder must be a third party trained and
• If welding machine is positioned more than 15 certified to perform the welding works safely
meters, it shall be provided by a dedicated fire and efficiently
extinguisher 0 0
• Materials and equipment shall be inspected prior • Assisting worker shall have basic
each use and ensure that all parts, components, knowledge in welding and fire safety to avoid
• Manual handling of fencing materials • Property damage functionality are in good conditionnt 0 and prevent possible accide 0
• Workers shall hold firmly the sheet to avoid from • Use plate holder if manual holding is
• Pinch point • Property damage falling 0 impossible 0
• Manual handling can lead to musculoskeletal • Facilitate training for manual handling.
• Manual handling disorder • Observe proper posture during manual lifting,
pushing, pulling, etc. 0 0
• All waste materials generated from the work • Supervising Engineer and Foreman shall
shall be disposed properly and shall not be left adhere to the proper housekeeping and
• Undisposed waste materials • Governmental violation unattended at the worksite 0 storage of materials at the designated 0
location
• Permit Receiver shall account all worker under ●
his Permit to Work and ensure all have signed out ●
• Accident resulting serious injury or death to on the attendance sheet and clear of the area
• Unaccounted workers 0 0
9 Closing of Permit to Work worker
• Permit Issuer shall visit the work location to • Mobile equipment shall properly parked on
verify good housekeeping was conducted before a designated equipment laydown
• Unattended unsafe condition • Significant cost due to damages closing the Permit to Work 0 0
● 0 ● 0
●
● ●
●
0 0
●
● ●
●
0 0
● ●