You are on page 1of 10

RISK ASSESSMENT AND ANALYSIS/‫قييم توـحليل لاـمخاطر‬

‫تــ‬

SEVERITY / CONSEQUENCE (Impact/Hazard Effect) (Where an event has more than one ' Loss Type ', choose the ' Consequence' with the highest rating)
Loss Type Additional "Loss Types" may exist for an event:
Identify & rate accordingly (1) Insignificant (2) Minor (3) Moderate (4) Major (5) Catastrophic
Single Fatality or Loss of Quality of Life / Irreversible impact
(S/H) Harm to People (Safety/Health) First Aid Case/Exposure to Minor Health Risk Medical Treatment Case/Exposure to Major Health Risk Loss Time Injury / Reversible Impact on Health on Health Multiple Fatalities / Impact on health Ultimately Fatal

Material Environment harm (RST) Serious environmental harm


(EI) Environmental Impact Minimal environment harm incident with workplace Material Environment harm (RST) incident (RMT) Major environmental incident (RLT) Major environmental harm – Incident Irreversible

(BI/MD) Business Interruption / Material / Fire Damage & No disruption to operation / 1000 SR to Less than 10k SR Brief Disruption to Operation / 10k SR to Less Than 100k SR Partial Shutdown/100k SR to Less than 1M SR Partial Loss of Operation/1M SR to Less than10M SR Substantial or Total Loss of Operation / 10M SR and more
Other Consequential Losses

LIKELIHOOD Examples (Consider Near-Hits as well as actual events) RISK RATING / PROFILE
The unwanted event has occurred infrequently : Occurs in order of less than once per year & is
(4) LIKELY likely to reoccur within 5 yrs. 4 (L) 8 (M) 12 (H) 14 (Ex) 16 (Ex)

(3) POSSIBLE The unwanted event has occurred in the business at some time: or could happen within 10 years. 3 (L) 6 (L) 6 (M) 12 (H) 13 (H)

(2) UNLIKELY The unwanted event has occurred in the business at some time: or could happen within 20 years. 2 (L) 4 (L) 4 (L) 8 (M) 10 (M)
The unwanted event has never known to occur in the business or it is highly unlikely to occur
(1) RARE within 20 years. 1 (L) 2 (L) 2 (L) 4 (L) 5 (L)

Stop operation and review controls - Eliminate, Proactively manage & implement specific Actively manage & monitor – Additional Risk acceptable – Monitor & manage as
Project Name : R12-T07B19-BDOM Contract ( Civil and mechanical works for water tanks at TRSDC ) GUIDELINES FOR RISK MATRIX avoid risk & implement high priority action plans controls/action plans-Review after 7 days controls is advised & review after 30 days appropriate with frequent review

Contract No. : 225211000 RISK RATING 16 To 25 12 To 15 8 To 10 1 To 6


- RISK LEVEL (Ex) - Extreme (H) - High (M) - Medium (L) - Low
RA TEAM (NAMES):‫ريق لاـتقييم‬
‫اسمءاـ فــ‬ DESIGNATION SIGNATURES WORKPLACE / TASK / ACTIVITY / PROCESS NAME:‫ لاـمعـدة‬/‫ لاـعملية‬/ ‫ لاـمهمة‬/ ‫لاـموقعـ‬

1. CIVIL SITE MANAGER


DEPARMENT / AREA:‫ لاـمنطقة‬/‫ اـالدارة‬:
2. CIVIL ENGINEER
EXCAVATION , BACKFILLING AND COMPACTION WORK USING HEAVY EQUIPMENT
3. CIVIL ENGINEER
4.
RISK
HAZARD IDENTIFICATION/ ‫حديد لاـمخاطر‬
‫تــ‬ CONTROL/‫وـسائـل لاـتحكم‬ ASSESSMENT RISK REDUCTION ACTION PLAN/ ‫تقييم لاـمخاطر‬
‫خـطـة لاـعمل ل ـ‬
‫تقييم المخاطر‬

Consequence

Consequence

Risk Ranking
Risk Issue
‫الرقم المتسلسل‬

Likelihood

Likelihood
Ranking
Workplace/ Activity/ Process/ (Possible Incident) (What can go wrong) (Improve Existing Controls/ Implement Controls
Item #

Hazards (Accident/ Ill health to person, fire or Existing Controls Follow up By Whom (Name) Implemented (Yes
Equipment/ materials
‫االخطار‬ ‫وسائل التحكم المتوفرة‬ new controls) ‫المهمة المعنية بالتنفيذ‬ / No)/‫تــ لاـتنفيذ‬
‫هل م‬
‫ المواد‬/ ‫المعدات‬/‫موقع العمل ظمهمة العمل‬ property loss) ‫التحكم والسيطرة االضافية‬ ‫الـ‬/‫نـعم‬
/‫ لاـمخاطر لاـمحتملة‬/
• Permit to Work shall be obtained as a pre-requisite to • Permit Receiver shall be trained and
perform work authorized by the Manager to receive a
• Work shall not be started until duly approved Permit Permit to Work
to Work is available at site and that Safety Toolbox ●Permit Receiver shall be responsible to
meeting was conducted
• TSTI/TBT oversee for the safety of all workers under
• Work shall not proceed without the presence of his Permit to Work
4 2 8 2 1 2 Engr. Ibbo Yes
• All crew shall be given safety induction, approved Permit to Work with the Permit Receiver
before mobilizing to site. overseeing the activity

• Lack of communication ● A safe work practice shall be implemented to • All workers attending the toolbox meeting
• Wrong information or details are written in reduce the possibilities of accident / incident shall sign on the attendance sheet attached
the Permit to Work. ●Permit Receiver and Permit Issuer shall visit to the specific Permit to Work
• Other activities may not be cover with the • TSTI/TBT. together at the site to ensure that workplace
Permit to Work. • A safe work practice shall be identified to hazards are adequately identified and mitigating
reduce the possibilities of accident/incident. measure shall be established
• Ensure that all required supporting
documents shall be available as per Permit to
Work requirements.
• All the required related documents as
3 2 6 3 1 3 Engr. Ibbo Yes
Briefing and Introduction to identified to be attached in Permit to Work
1
perform an activity shall be reviewed and evaluated by issuer and
receiver to ensure that all hazard and risk is
identified and complete.
● Permit to Work shall be displayed at the ● All workers shall attend the toolbox
• Does not aware of the risks involved worksite meeting on a daily basis conducted by the
• Unidentified or incomplete hazards and risk ● Permit Receiver shall not leave the area for the Supervising Engineer, Foreman and Permit
• Loss of production whole duration of work
2 2 4 Receiver
2 1 2 Engr. Ibbo Yes
information.

- ● Proper PPE to be checked and monitored


for workers which are involved in the activity
 As a minimum PPE Use; Hard Hat, Safety
Boots, Safety Gloves, Safety Glasses, Cover all,
Dust mask, Reflective vests & Earplug
•Lack of PPE 3 2 6 2 2 4 Engr. Ibbo Yes
• If workers are used for compaction, proper
foot protection to be provided.

• Obtain a valid wok permit • Ensure that Tool Box Talk is conducted
• Ensure that all workers undergo safety induction daily by the Supervisor and Foreman
that discuss safety policies • Safety trainings must be conducted
• Lack of safety awareness and knowledge • Engage in accident resulting injury to • Conduct Tool box talk and discuss safe work periodically as work requires
for the job personnel due to lack of safety awareness procedure, RA, and JSP prior to the start of work.
3 2 6 2 2 4 Engr. Ibbo Yes

• Ensure that all workers are provided with • Close supervision is required. Supervisor
required mandatory PPEs such as: Helmet (ANSI and foreman must be present at site.
Z89.1, CE EN397), Safety Glass, Safety Shoes, Cover • Ensure presence of safety personnel
• Working without wearing appropriate • Hand injury all, Safety Gloves, Dust Mask • Conduct trainings for PPE as per activity.
Personal Protective Equipment (PPE) • Arm injury • Use hand gloves for hand protection 3 2 6 2 2 4 Engr. Ibbo Yes

• Only up to 20 kg is allowable for each worker to • Ensure that all personnel are trained in
lift. proper manual handling
• Physical injury from slip / trip / fall • Ensure that access has no obstruction
• Improper manual handling • Back injury • If the load is heavier, buddy system is advised 3 2 6 2 2 4 Engr. Ibbo Yes
• Arm injury

• All operators must be trained and certified by a • Only operators that are certified and
third party trained can operate the equipment at the
• All equipment must be inspected and certified by site
• Failure of equipment may lead to accident or a 3rd party • All drivers and operators shall undergo
• Equipment and operator without 3rd party incident Defensive Driving Safety Training
certificate 3 2 6 • Daily tool box talk must be conducted 3 1 3 Engr. Ibbo Yes
before any work commences

• Daily equipment inspection must be carried out • Equipment Operator shall be oriented on
by the operator how to use and fill out the checklist properly
• All operators must be trained in conducting • Equipment inspection checklist shall be
• Physical / fatal injury inspection of equipment using the checklist provided and conducted in a daily basis
• All equipment must be inspected regularly using 3 2 6 2 1 2 Engr. Ibbo Yes
• Damage of property
checklists by the operator
• Lack of knowledge in conducting inspection
using checklist
• The equipment to be used shall be in good • Supervising Engineer and Safety Officer
condition shall ensure that inspection was carried out
• The equipment must be suitable to perform the 2 thoroughly
Mobilization / Inspection of heavy • Physical injury from slip, trips and fall task
2 4 3 1 3 Engr. Ibbo Yes
2 equipment (excavator and dump
trucks) at site
• Establish equipment access and shall be free • Site management plan shall be prepared,
• Vehicular accident from any obstruction approved and implemented to avoid
• Accident resulting Injury to personnel • Designate parking area property damage and personnel accident
2 2 4 2 1 2 Engr. Ibbo Yes

• Struck by moving equipment and vehicle • Designate location for unloading of materials ●
• Designate spotter and flagman to guide all ●
• Property damage of adjacent structure or equipment and personnel movement
appurtenances
3 2 6 0 Engr. Ibbo Yes

• All heavy equipment and its driver/operator shall • All heavy equipment operator and driver
hold a valid third party certification authorizing shall be oriented with the proper use on how
them on the specified equipment to operate to fill out the daily inspection checklist
• Select and mobilize only good condition • Lease equipment and operator must be
equipment from establish company
• Incompetent equipment operator or driver • Equipment certification and registration must be • All operator and driver must sign the
• Property damage, fatality or injuries during ured and available drivers’ pledge
4 2 8 2 2 4 Engr. Ibbo Yes
the operation of the equipment. • Operator and driver must have certification and
license
• All heavy equipment shall be inspected by the • Pre-selection of equipment and operator
authorized operator on a daily basis to ensure that should establish
equipment is in good working condition before
using to the site
• Heavy equipment shall not be used if found any
defects or damage that might affect its safe
operation
• Repair of heavy equipment shall not be done on
• Dilapidated equipment / Damage or • Property damage, fatality or injuries during the site. It must be brought to the designated work 4
defective condition of equipment the operation of the equipment.
2 8 2 1 2 Engr. Ibbo Yes
shop and only certified mechanic shall make repair
of the equipment

• Implementation of Log-in and Log-out from the • Recording and registry for all equipment,
urity post. operator and driver shall be made.
• Unauthorized entry of the equipment to • Equipment / vehicle insurance
• Property damage, fatality or injuries during 8 4 Engr. Ibbo Yes
the site. the operation of the equipment.
4 2 2 2

• Locate underground services referring to the site • Report accordingly any noticed
• Damage to property map / drawing. underground utility
• Use suitable detectors to check and locate any 2 3 6 2 1 2 Engr. Ibbo Yes
underground utilities.

• Supervisor and Foreman shall closely monitor to ●


• Damage to underground utlities prior to ensure accurate reading is obtained ●
Checking and verification of any
3 excavation due to failure to perform pre- • Disruption to production 2 2 4 0 Engr. Ibbo Yes
underground utilities
checks.

• Worker who will perform the verification shall be ●


knowledgeable and trained in using and ●
• Accident resulting in injury to worker interpreting the instrument 3 2 6 0 Engr. Ibbo Yes

• Operator must be competent, trained, and • Flagman training must be conducted


experienced of the task and must be 3rd party • Acquire as-built drawings of underground
certified holder existing facilities prior to any task to be done
• Trained and competent flagman must be • Close supervision is required
assigned for all heavy equipment operation • Supervisor and foreman must be present in
• Impact by a sudden operation of equipment • Heavy equipment shall not be allowed at any the site.
may cause serious injuries or property damage time without the presence of dedicated flagman • Conduct safety toolbox meeting and
• Toolbox meeting must discuss the safe use of discuss the work procedures prior to start of
equipment to be conducted by Foreman work.
• Struck by excavator moving / operating • Only trained competent operators shall be • Supervising Engineer and Safety Officer
assigned to operate any heavy equipment during 4 2 8 shall attend and ensure that toolbox meeting 2 2 4 Engr. Ibbo Yes
equipment
mechanical excavation works was conducted and discussed according to
the risk assessment of the activity

• All underground utilities must be identified, • At all stages of the excavation, a competent
marked with a visible warning or relocated, fixed person must supervise the work and all
and ure workers must be given clear instructions on
• Area to be excavated must be scanned for working safely in the excavation.
underground services and utilities • Ensure proper and adequate supervision by
• Conduct test pit. Manual excavation is highly supervisor/ foreman.
required to prevent any damages to any existing • Site safety officer must ensure that all
underground utilities due to machine excavation excavations are provided with necessary
• Permit To Excavate must be issued before work safety requirements.
commences • Close supervision is required
• Spotter must be assigned to guide the heavy • Supervisor and foreman must be present in
equipment operator specially if underground the site
utility is found • Training for excavation works must be
• Impact and damage to existing plant / • Hand digging only in the vicinity of underground conducted
• Presence of plant / underground services services 3 2 6 • Tool Box Talk shall be provided to the 2 1 2 Engr. Ibbo Yes
underground facilities
• Properly monitor when hand digging the vicinity workers prior to the start of work
of underground services
• Electrical cables adjacent to excavation shall be
isolated by electrician using permit to isolate
• All underground utilities must be identified, ● • Ensure proper housekeeping to avoid
marked with a visible warning or relocated, fixed unnecessary materials
and ure ●
• Area to be excavated must be scanned for
underground services and utilities
• Conduct test pit. Manual excavation is highly
required to prevent any damages to any existing
underground utilities due to machine excavation
• Permit To Excavate must be issued before work
commences
• Spotter must be assigned to guide the heavy
equipment operator specially if underground
utility is found
• Hand digging only in the vicinity of underground
services
• Properly monitor when hand digging the vicinity
of underground services
• Falling of workers / equipment / tools into • Electrical cables adjacent to excavation shall be
• Unprotected edges of excavation excavation resulting to personnel injury, isolated by electrician using permit to isolate 4 2 8 2 2 4 Engr. Ibbo Yes
fatality, property damage • Fall prevention barriers (barricades) with signs
shall be erected around excavation at least 1
meter away
• Concrete Jersey barrier installed at a safe
distance from excavation, preventing vehicles from
falling into the excavation. Standard barricading
for UG shall be complied accordingly.
• Wear appropriate PPE – hard hats, safety glasses,
safety mask, safety gloves and safety shoes

• Check the condition of excavation at all times for • Report any signs of cave-in to supervisor.
possibility of collapse or cave in • Excavation training must be conducted
• Excavation walls that are deeper than 1.5 meter prior to start of activity
must be sloped / benched or shored depending on • Hazard awareness and best practices
Perform excavation using heavy the type of materials being excavated relevant to excavation must be conducted.
4 equipment such as skid loader, • Erosion control measures must be considered • Provide hole watcher to monitor the entry
backhoe, when using dewatering operations & exit of entrant
• Provide temporary sum pit and sub pump to • Practice good housekeeping while working
remove water inside excavation in and around excavations and trenches
• Unstable soil condition (due to type, • If equipment is being used above the trench,
• Cave-in (sudden collapse of soil) 3 2 6 3 1 3
vibration, and water) then no operatives should be in the trench when
the machine is in use • Stability of
soil must be ensured

• All excavated materials must be a minimum of 1 • Provide Gas Test equipment and conduct
meter away from the edges of excavation or totally gas test by competent persons if suspected
removed from the site. to have a buildup of unknown gas
• Excavation must be properly barricaded • Contact the site area
physically, and DANGER DEEP EXCAVATION signs in advance and agree that access to the
must be provided specific area is acceptable
• Heavy equipment parking must be a minimum of • Follow safe work practices
• Buildup of harmful gases in the excavation • Health hazards (asphyxiation / collapse due 3 meters away from the edges of excavation • Conduct confined space training for the
• Excavations > 4 ft. deep (1.20 m) that may 4 2 8 involved personnel 2 2 4 Engr. Ibbo Yes
for 1.2 meters confined space to inhalation of hazardous gases)
develop hazardous atmospheres shall be
considered a confined space
• Use safe access while entering and exiting • Hoses / cables shall be positioned in such a
excavations and trenches way that it will not create obstruction on the
• Each excavation must be provided with proper access and work areas
access and egress • Warning signs and safety barricades shall
• Ladders must be ured when workers are required be used whenever a slip, trip or fall hazard
to work inside the excavation for manual has been identified but cannot be corrected
excavation or removed immediately
• Avoid taking short cuts or jumping in and out of
excavation
• Aisles, stairs, and passageways shall be kept clear
• Materials must not be carried in a manner that
will provide obstruction in the way ahead
• Materials shall be stored in designated areas
• Materials and tools shall be stored away from
exposed edges
• Ensure proper access and egress in the
• Personal injury due to slip and trip hazards excavation
• Poor access and egress from the obstruction of materials on access / • Provide proper illumination or blinker lights
3 2 6 2 1 2 Engr. Ibbo Yes
egress along the excavation in order to be identified
during night time.
• No tools and equipment shall be stored close to
the edge of excavation.

• Modify work schedules and arrange frequent • Establish a complete heat illness
rest periods with water breaks in shaded area prevention program
• Provide adequate cool water to workers close to • Provide heat stress training, and its
the work area. prevention
• Ensure workers drink at least a pint of
water every hour
• Workers must be advised to drink plenty of
fluids
• Workers must be advised to drink water
more often and even before they feel thirsty
• Working under direct sunlight • Heat exhaustion/ stress 4 2 8 • Workers must avoid beverages that contain 2 2 4 Engr. Ibbo Yes
alcohol or caffeine.
• Workers must wear light-weight, light-
colored, and loose-fitting clothes

• Use an approved dusk mask (such as 3M, etc.) • Water sprinkling shall be carried out to
• Dust control must be thoroughly done around avoid dust emissions, where necessary
• Exposure to dust the excavation area • Supervisor and foreman must ensure
• Respiratory illness 3 2 6 adequate monitoring of activities 2 1 2 Engr. Ibbo Yes

• Provide trained flagman equipped with green • All heavy equipment operator including
and red flags to control the moving equipment rentals shall attend Defensive Driving
• Serious accident and even death to personnel • There shall be no working personnel inside the Training for the driver
• Struck by moving equipment (such as excavation while excavation and loading of soils is
dump truck, etc.) ongoing 4 2 8 2 2 4 Engr. Ibbo Yes
• Conduct tool box talk prior start to work.

• Establish safe distance from equipment to the • Equipment must have back-up alarms
edge of excavation
• Concrete Jersey barrier shall be maintained and
• Falling of heavy equipment into the installed at a safe distance from excavation,
• Significant property damage preventing vehicles from falling into the excavation 3 2 6 2 2 4 Engr. Ibbo Yes
excavation

• Provide adequate shoring with approve shoring • Supervisor and foreman must ensure
Loading of excavated soils to a materials on an excavated area adequate monitoring of activities
5 • Soil cave in and collapse • Physical injury / property damage • Provide complete physical barricades with 3 2 6 3 2 6 Engr. Ibbo Yes
dump truck
flagman standing outside the barricades

• All drivers must be trained and have a driving • Proper training must be provided to the
license operator / driver
• Filled dump trucks shall be covered with screen
or equivalent materials to prevent spoils from
spilling on the road while transporting to dump
• Incompetent driver • Disruption to activity and productivity site 3 2 6 2 1 2 Engr. Ibbo Yes
• Foreman shall ensure that cover is installed
properly
• Use an approved dusk mask (such as 3M, etc.) • Water sprinkling shall be carried out to
• Dust control must be thoroughly done around avoid dust emissions, where necessary
• Respiratory illness the excavation area
• Exposure to dust 2 2 4 3 2 6 Engr. Ibbo Yes

• Provide trained flagman equipped with green


• Struck by moving equipment (such as and red flags to control the movement of
• Vehicular accident resulting to injury or ill equipment.
dump truck, etc)
health to worker or bystander • Suitable traffic management plan shall be
established such as segregation of pedestrian lanes 2 2 4 0 Engr. Ibbo Yes
from vehicle access ways.

• Slowly dump the soil to minimize the airborne of • Check surrounding for any equipment or
dust materials that might be covered during
• Exposure to Dust • Ill health to worker due to inhalation of dust 3 2 6 dumping of excavated soil 2 1 2 Engr. Ibbo Yes

• Driver shall follow instruction from the foreman • Driver shall be trained and follow defensive
driving technique
• Reckless driving • Significant damage to property 3 2 6 2 2 4 Engr. Ibbo Yes
Shifting and offloading of excavated
6
soils into the designated area
• Filled dump trucks shall be covered with screen • Driver shall follow designated route going
or equivalent materials to prevent spoils from to the dumping area
spilling on the road while transporting to dump
• Vehicular accident resulting to injury or ill site
• Busy traversed road • Foreman shall ensure that cover is installed
3 2 6 3 1 3 Engr. Ibbo Yes
health to worker or bystander
properly.

• Designated offloading (dump site) shall be • Designated dumping area shall be away
established with suitable demarcation and signs from residential area
posted.
• Populated area • Ill health to worker due to inhalation of dust 3 2 6 2 1 2 Engr. Ibbo Yes

• All workers / personnel and visitors must attend • Re-orientation for all workers / personnel
the required safety induction before allowing to and visitors after 1 year and returning from
work on the site vacation.
• All workers / personnel and visitors must sign the
• Slip and trip that can cause sprain and strain attendance records and acceptance for new
employee on the job orientation 3 2 6 3 1 3 Engr. Ibbo Yes

• Workers shall be issuedwith appropriate PPE’s • Periodical replacements of PPE’s and


• Unfamiliar to the construction site such as safety shoes (BS 1970 or ANSI Z 41.1), comply with its recommended lifetime.
safety helmet (BS EN 397 or ANSI Z 89.1), safety • Observed proper storing and disposal of
glasses (BS 2092 or ANSI Z 87.1), ear plugs (ANSI used PPE’s.
• Getting injured from protruding object S3.19), protective clothing or equivalent for all, 2 2 4 2 1 2 Engr. Ibbo Yes
etc.

• Provision of pedestrian access, signage and


building / structure identification
• Struck-by, hit into or injured by moving • Awareness / training for all operator and driver 3 2 6 2 2 4 Engr. Ibbo Yes
vehicle / equipment

• Housekeeping shall be done before, during and • Site management plan shall be prepared
after the job indicating all the location of personnel and
• Poor housekeeping in the workplace / equipment access, parking areas, offices,
Unorganized materials and access • Designate location for unloading of personnel materials storage area, disposal area,
• Property damage to equipment or materials and materials be stored only on a designated hazardous waste disposal and storage area,
storage area 3 2 6 rest shelter, evacuation area and etc. 2 2 4 Engr. Ibbo Yes

• Designate a dedicated personnel who is familiar • Designated access shall be free from any
with the site management plan to guide all obstruction
personnel and equipment in loading and unloading
• Struck with sharp and hard object • Accident resulting injury to personnel of materials and equipment 2 2 4 3 1 3 Engr. Ibbo Yes

• All material location and storage shall be • Designate material disposal area
barricaded and provided with adequate signage
• Area congestion • Vehicular accident 3 2 6 2 1 2 Engr. Ibbo Yes

• Designate parking area • Site management plan shall be prepared,


• Vehicular accident • Designate location for unloading of materials approved and implemented to avoid
2 2 4 property damage and personnel accident 2 2 4 Engr. Ibbo Yes

• Struck by moving equipment and vehicle


Site mobilization / selection of
7 equipment, operator and driver as
per the approved Method of
• Establish equipment access and shall be free
• Struck by moving equipment and vehicle from any obstruction
Site mobilization / selection of • Accident resulting Injury to personnel 2 1 2 0
equipment, operator and driver as
7 per the approved Method of
Statement • Designate spotter and flagman to guide all
• Property damage of adjacent structure or equipment and personnel movement 2 2 4 0
appurtenances
• Equipment operator and assist worker shall be
provided with earplugs
• Hearing loss • Earplugs or earmuff shall be worn properly to
effectively reduce the noise to permissible level 3 2 6 0

• Exposure to excessive noise


• As a PME requirement, there shall only be less
than 5 engine driven equipment to operate
• Miscommunication simultaneously at the project site 3 1 3 0

• All heavy equipment shall be inspected by the • All heavy equipment operator and driver
authorized operator on a daily basis to ensure that shall be oriented with the proper use on how
equipment is in good working condition before to fill out the daily inspection checklist
using to the site • Lease equipment and operator must be
• Heavy equipment shall not be used if found any from establish company
defects or damage that might affect its safe • Pre-selection of equipment and operator
operation should establish
• Dilapidated equipment • Repair of heavy equipment shall not be done on
• Damage or defective condition of the site. It must be brought to the designated work
• Property damage, fatality or injuries during 8 4 Engr. Ibbo Yes
equipment the operation of the equipment. shop and only certified mechanic shall make repair 4 2 2 2
of the equipment
• Select and mobilize only good condition
equipment

• Implementation of Log-in and Log-out from the


urity post. • All
• Unauthorized entry of the equipment to operator and driver must sign the drivers’ pledge
• Failure of equipment may lead to accident or • Recording and registry for all equipment,
the site. injuries
3 2 6 0
operator and driver shall be made.

• Equipment certification and registration must be


ured and available
• Operator and driver must have certification and
license
• Equipment / vehicle insurance •
All heavy equipment and its driver/operator shall
• Incompetent equipment operator or driver • Major accident, serious injuries, fatality, hold a valid third party certification authorizing 4 1 8 0
property damage for unauthorized operation
them on the specified equipment to operate

• Operator and driver shall carry out daily • Competency registry for all operator and
equipment inspection prior to work driver
• Operator must be ensuring the equipment are • Documentation of daily toolbox meeting
suitable for the task • Re-training schedule / plan for the flagman
• Ensure the competency of the operator and • Defensive driving course from accredited
driver company
• Failure of equipment may lead to accident or • Provide trained flagman with reflective vest • Registry / records of equipment
injuries along with Red and Green flags. maintenance
• Struck-by or hit moving vehicle
2 2 4 2 1 2 Engr. Ibbo Yes
• Complete barricade must be provided, and the
flagman shall position outside the barricade.
• Fastened of seat belt
• Equipment (skid loader, wheel loader,
dump trucks)

• Safe use of equipment must be discussed during • Verification for all equipment checklist by
daily toolbox meeting by the foreman or the safety personnel or foreman in-charge
supervisor
• Collision by sudden operation of equipment • Reverse audible alarm must be working properly
may cause serious injury or damage to • Periodical maintenance program for all 4 2 8 3 1 3 Engr. Ibbo Yes
property equipment and vehicle.
• Instruct all new personnel to report to the safety • Active participation / coordination from all
department or administration department. foreman / supervisor / engineers
• Close coordination between the management • Issuance of severe disciplinary actions
itself. • Recognition / award system
• Report all unfamiliar worker / personnel at site
• Replacement of equipment or operator by • Authority to stop the work if found without valid
surprise without coordination and • Major accident, serious injuries, fatality, license / certificate 4 2 8 2 1 2 Engr. Ibbo Yes
property damage for unauthorized operation • Issuance of disciplinary action
certification

• Orientation to the operator and driver regarding • No flagman, no movement of the


the site condition equipment
• Provide trained flagman with reflective vest • Foreman / supervisor must ensure the
along with Red and Green flags. competency of the operator / driver
• Remind the operator and driver to follow the • Refer to the Method of Statement
signal of the flagman
• Access must be properly compacted and even
• Equipment toppled and damage to property • Workers are advised / instruct to move away
while moving from the equipment.
• Positioning of equipment near to the edge • Injuries to the operator or driver • Equipment shall position more than 1.5m from
the edge of excavation 3 2 6 3 1 3 Engr. Ibbo Yes
of the excavation • Injuries to other personnel involved to the
activity • Fastened of seat belt
• Compliance with the work permit system and
requirement stated therein

• Workers shall use appropriate and good • Ensure monthly inspection for all hand
condition hand tools tools
• Defective hand tool shall not be use and must be • Certified first aider must be available
taken out of the project • Provision of first aid kit
• Use appropriate hand gloves
• Defective, damaged and improvised hand • Personal injury (laceration, etc.) due to • Avoid damaged tools and machine
• Supervisor and foreman must ensure the tools 2 2 4 2 2 4 Engr. Ibbo Yes
tools contact with sharp edge, tools and materials
and materials are free from damage
• No modification of tools and machine

Soil backfilling using dump truck


8
and skid load
• Good planning and position of lighting system. • Corrective action if the lighting survey
• Initiate in conducting lighting survey deviate from the requirement
• Issuance of clear safety glass
• All workers shall wear clear safety glass at all
• Accident to personnel times
• Damage to property • There shall be no activity allowed beyond 6:00 in
• Struck with nearby structure or personnel • Personal injury cause by other worker / the evening that hinders the visual capability of 3 2 6 2 1 2 Engr. Ibbo Yes
equipment as the vision impairment the workers

• Provide sufficient illumination to the work place • Monitoring and maintenance of the lighting
by installing HV lamp on the area system
• Lighting shall be installed on all locations that • Ensure sufficient stocks of lighting fixture /
• Insufficient lights / poorly illuminated • Slip, trip and fall could provide adequate illumination to the activity 2 2 4 accessories 2 1 2 Engr. Ibbo Yes

• Personnel and equipment access shall be free • Manual handling training


from any obstruction
• Materials should be stored in the designated
area
• Personal injury due to slips and trip hazards • Materials and tools should be store away from
• Access and egress (uneven, loose, blocked exposed edge
from the materials and surface area 3 2 6 2 2 4 Engr. Ibbo Yes
by materials, etc.) • Foot strain and sprain • Ensure that access is leveled and compacted

• All workers shall be provided and wear safety • Supervisor and Foreman shall ensure that
glass at all times all workers are adequate provided with right
• NIOSH approved dust mask shall be provided to PPE for the hazard being exposed
all personnel exposed to dust • Safety Officer shall ensure that adequate
• EYes, Skin and Respiratory irritation • All operator and workers shall be provided with 2 stock is available at the site to issue workers 2
2 4 1 2 Engr. Ibbo Yes
• Ill health to personnel dust mask and wear it properly as necessary
• Exposure to dust and other airborne
particles through inhalation and skin
absorption
• Gradually backfill the soil to minimize airborne • Educate the worker / staff about the dust
dust related hazards
• Accident resulting injury to personnel • Spray water to control the dust
2 2 4 2 1 2 Engr. Ibbo Yes
• Visual impairment
• Approved emergency plan and procedure must • Trained the urity guard for emergency
available and posted cases
• Emergency contact numbers must be available • Issuance of whistle to the safety personnel
and posted
• Site "assembly point" must be clearly visible,
identified and isolated
• The risk of fatality / major injuries once • Appointed and trained fire coordinator must be
getting stocked and not move during available
emergency cases. • Standby / emergency vehicle must be provided 4 2 8 3 1 3 Engr. Ibbo Yes
• No emergency plan during emergency and available at all times.
cases (fire, gas release, explosion, tsunami, • Provide and install alarm system in strategic
flood, medical case, earthquake, etc.) or location.
unfamiliar to the jobsite

• Initiate emergency evacuation plan and fire drill • Coordinate or call the local authorities for
• Misleading or getting lost at site can lead to every 6 months. uncontrolled scenario.
injuries • Facilitate and attend the safety induction / 3 2 6 • Initiate daily toolbox meeting 2 2 4 Engr. Ibbo Yes
• Running can cause stain and sprain orientation

• Only competent and skillful operator shall • Retraining for flagman and operator
operate the roller compactor • Records and monitoring for equipment
• Allowing periodical rest of the operator certificate and operator’s license
• Ensuring the operator cabin in good condition • Availability of equipment spare parts
• Provide trained flagman to assist the operator
and wearing reflective vest
• Certificate and license for both equipment and
• Expose to continuous vibration and sound
• Struck-by the moving equipment operator
• Daily inspection by the operator prior to work
• Equipment toppled due to miscalculation by
and logging the results. 2 2 4 2 1 2 Engr. Ibbo Yes
the operator
• Property damage during the operation • Issuance and wearing of ear plugs
• Fastened of seat belt

• Incompetent equipment operator

• Mechanical failure of the equipment that • Check the equipment on a daily basis using the • Records keeping of equipment
leads to the accident prescribe checklist and refrain using the maintenance and scheduling
• Continuous operation that leads to over equipment for any defects found
fatigue and stress • Check and ensure that seat spring are working
• Overheating of the equipment during properly to absorb the vibration 3 2 6 2 2 4 Engr. Ibbo Yes
operation

• Provide trained flagman to assist the driver • Defensive driving course to the driver
• Isolating or provide barricade and signage to the • Continuous orientation and training to all
water container operators
• Driver shall conduct daily inspection and record
result through checklist
• Maintenance of the vehicle must be done
• Serious injury to personnel regularly
• Vehicle (water trucks, hose, water
• Electrocution • Driver to ensure that the hose is free from any 4
container, etc.) 2 8 2 1 2 Engr. Ibbo Yes
Soil compaction using roller • Tripping and injuries from the uncoiled hose damage
9 • Damage or defective hose shall be replaced
compactor, plate compactor
immediately

• Remove or hang all electrical cables in the area


• Conduct housekeeping after the work
• Periodical maintenance and inspection for all
water pumps.
• uring vehicle registration and driving license to
• Struck-by or collision with other moving • Fire the driver 3 2 6 0
equipment • Property damage from vehicular accident • Fastened of seat belt

• Ensure that seat spring that absorbs the vibration • Records / registry of certification
is in good condition • Verification of equipment daily checklist
• Less exposure to the process • Equipment spare parts availability
• Move few meters from the workplace
• Good spreading and asphalt materials
• Exposure to vibration produced by the • Equipment certification
• Whole body vibration syndrome 2 2 4 2 1 2 Engr. Ibbo Yes
compactor • Periodical inspection of equipment
• Equipment maintenance

• Issuance and wearing of ear plug / defender ANSI • PPE acceptance pledge of the workers
S3.19 – 1974 or equivalent) • Good stocks and availability of PPE’s
• Hearing loss or impairment due to continuous • Periodical replacement of PPE’s
• Expose to high noise (above 85dB) • Avoid more than 8hrs exposure to sound 85dB 3 2 6 2 1 2 Engr. Ibbo Yes
exposure
above level
• Manual handling can lead to musculoskeletal • Facilitate training for manual handling.
• Manual handling disorder • Observe proper posture during manual lifting,
pushing, pulling, etc. 3 2 6 3 1 3 Engr. Ibbo Yes

• Provide storage box for cables • • Daily inventory of the equipment •


Labeling of storage box (good items, scrap / Training / awareness regarding the
damage items, by capacity, etc.) segregation of waste
• Tools & materials etc. lying on the ground • Property damage • Immediate disposal or sending the damage one 2 2 4 2 1 2 Engr. Ibbo Yes
to the store keeper
Housekeeping, clearing the area
with all used materials, tools and
10 equipment and brought to the • Remove all unwanted / protruding materials / • Good housekeeping at the site
designated storage and disposal • Protruding object / materials at the site • Accident resulting injury to worker / Slip, trip, object at the site • Daily toolbox meeting
falls
3 2 6 3 1 3 Engr. Ibbo Yes
area
• Provision of standby fire extinguisher • Records and registry for fire extinguisher
• Periodical inspection and / or color coding for fire • Records /
extinguisher registry for the quantity of waste disposed
• Provision of waste skip in the strategic location
• Uncollected / scattered rubbish • Fire at the site with marking 3 2 6 2 1 2 Engr. Ibbo Yes
• Provision of color coded waste bins at the site

You might also like