HAZARD IDENTIFICATION AND RISK ASSESSMENT

Contract Name: Contract No:

Risk Assessment for: ☒ Routine Activity ☐ Non-Routine Activity Assessment Date: 05.04.2021
Activity: Block Works and Plastering Works Rev Date :

Residual Risk Person


Who is at Degree of Risk
Sub-Activity Hazard Consequence (s) Control Measure (s) Responsible
Risk
L S R L S R
Entering to the 1.Without safety All project 1.Minor or major 1.All the project personnel must be holding Site Engineer
project site Induction involved injury 3 3 9 valid Visa, and emirates ID and project 2 3 6 Site Supervisor
through the 2.Entering to the site personnel security access card EHS Inspector
project security without PPE’s 2. All the operatives shall be wearing suitable All involved
gate. 3.Unaware of the PPE, s hand glove, safety helmet, high operatives
site condition reflective safety jacket and safety goggles.
4.Entering to the 3.Operative must be undergone client /internal
restricted area. HSE induction training prior starting the task
5.Snake & at site.
venomous 4.All the operatives must be stay in the inside
the project premises and unauthorized entry
strictly prohibited
5.Ensure no operatives will enter restricted
area bird/dog and other pet cages, ensure
feeding pets are prohibited
6.Site supervisor must be delivered the
specific TBT to all involved operatives Do, s
and don’ts, emergency preparedness, snake
bit etc.
7.Specific safety signages must be placed for
the project personnel awareness.
8.All the visitor must be reported to the
project security gate.
9.Photography strictly prohibited inside the
project premises, obtain the permission from
the authorities (if required)
10.Treat all snakes as if they are venomous,
report immediately concern supervisor.
11.Dont killed or injured snake or any
venomous.
12.Responsible person must be undergone
HAZARD IDENTIFICATION AND RISK ASSESSMENT
snake bit training and full time available on
site, required first aid treatment resources
must be available on site
13.Project emergency contact number must be
displayed at site.
Offloading the 1.Collisoin Operator 1.Major/ Minor
block & mortar 2.Incompetent Banksman injuries. 4 4 16 1.TBT & Job Awareness training shall be given 2 4 8
materials in the Operatives. Nearby 2.Property Damaged. to all operatives.
designated area 3.Uneven ground operatives 2.All personnel shall be fit for the task.
using boom 4.Improper access 3.Boom loader & Hiab crane must be holding
loader & hiab and egress valid third-party certificates.
5.Overreaching 4.Ensure work area shall be free from
6.Blind spot obstacles.
7.Existing overhead 5.Operatives shall be wear proper PPE, s at
lines (if any nearby) site. (Hand -gloves, Safety goggles, Safety
8.Underground Shoes, High visibility Jacket.)
utilities 6.Work area shall be barricade to prevent the
9.Excavated unauthorized entry. placing suitable signages
Trench/pit 7.Ensure proper access and egress shall be
10.Sharpedges/pinch maintained and ensure housekeeping
points surrounding the working area.
8.Effective supervision in place to guide the
operatives.
9.Ensure maintain a safe distance between the
overhead lines if any near by
10.Lifting accessories shall be suitable and
certified by competent 3rd party agency.
11.Ensure underground utilities shall be
protected by providing the steel plate
(wherever required)
12.Ensure maintain/keep safe distance
between hiab crane & existing excavated pit or
trench. (additionally, excavated pit shall be
hard barricaded with proper signages.
13.Ensure tag line shall be long enough at
least 6 mtr to control or hold the load.
14.Offloading activity shall be paused when
the wind speed exceeds to 38 km/h
15.Becon light shall be provided to the plant &
equipment.
16.Lifting checklist must be prepared and
communicate to operators.
Mortar mixing 1.Poor access and Mason 1.Major /Minor injuries 1.TBT shall be conduct to all involved Site Supervisor
by using the egress Helper 2.Property damaged 4 4 16 operatives 2 4 8 Electrician
mortar machine 2.Entanglement Electricians 3.Enviornmental 2.All operatives shall be internally trained for
HAZARD IDENTIFICATION AND RISK ASSESSMENT
3.Vibration the task.
assets.
4.Noise 3.Ensure mortar mixer shall be good condition
5.Rotating parts and inspected by electrician before usage at
6.Improper Manual site.
handling 4.Ensure proper access and egress shall be
7.Defective sockets maintained and ensure housekeeping
and cables surrounding the working area.
8.Inhalation of the 5.Ensure all rotating parts shall be cover and
dust secured properly.
6.Ensure use right tools for right job not
allowed to use homemade tools.
7.Operatives shall be wearing proper PPE, s at
site. (Anti impact Hand -gloves, Safety
goggles, Safety Shoes, High visibility Jacket
earmuff, Dust mask)
8.Ensure effective supervision and close
monitoring system in place.
9.Ensure mortar mixing area shall be
isolated/barricaded with signages.
10.Ensure operator shall not wear any loose
cloths and jewelries.
11.Ensure operatives job rotation in place.
12.Ensure mortar mixing third party certificate
shall be available at site.
13.Ensure eye wash station near by

Placing the 1.Poor access and Mason 1.Major /Minor injuries 1.PTW and TBT shall be obtained prior
blocks using egress Helpers 2.Property damaged 4 4 16 commencing the task. 2 4 8 Site Supervisor
mortar 2.Sharp Edges 3.Muscle strain 2. Dont try to lift or pull heavy objects,get help
3.Men & material or use wheel barrows.
may fall
4.Overload platform 3.Ensure operatives shall be wear full body
5.Falling/collapse of harness more than 1.8mtr.
wet wall 4.Ensure provide staircase access to the
6.Improper manual working area.
handling 5.Ensure dont stock the blocks on working
platform.

Prepare seperete platform to keep the blocks


converting in to heavy duty platform(shall
be prepared by DAC approced Scaffolders)
6.Ensure only trained and competent Mason
team only deploy for the task
7.Be aware of dropping of blocks,personnel
working around or beneath,use firm grip on
HAZARD IDENTIFICATION AND RISK ASSESSMENT
blocks
8.Ensure safe access and egress shall be
provided.
9.Certified(green Tag) scaffold to be used
10.All opeartives shall be undergone working
at height training(internal)

11.Operatives shall be used suitable PPE, s


based on the activity
 Head protection

 Double eye protection with safety


goggles with face shield

 Ear Plug or earmuff

 Disposal cover all

 Safety shoes

12.Load allowed for worker is as per his age


and shall follow DM COP7-Material handling
and storage.
Plastering 1.Improper Manual Mason 1.Major /Minor injuries 1.TBT shall be given to all involved operatives.
Works Manually Handling Helpers 2.Sprains & Strains 4 4 16 2.Ensure only trained and competent Mason 2 4 8 Site Supervisor
& using mortar 2.Men & Material 3.Asthama team only deploy for the task.
machine May fall 4.Enviornmenatl 3.Ensure provide stair case access to the
3.Home Made Tools aspects working area.
4.Noise from Mortar 5.Skin irritation 4.Dont keep a large quality of mortor onthe
Mixer working patform to aviod the over load.
5.Vibrtaion 5.Ensure dont use any homemade tools,use
6.Inhaltion of the right tools for right job.
mortar 6.Exclusion zone shall be provide working area
7.Soil Contamination and underneath the working area.
8.Nonstandard or
improper working 7.Opeartives shall be used double lanyard full
platform body harness working more than 1.8 mtr.
9.Electrocution 8.Ensure underneath the working area
polyethene sheet shall be
Placed to avoid the soil contamination.
9.Operatives certified (Green Tag) shall be
used.
10.All operatives shall be undergone working
at height.
11.Ensure eye wash station near by the
working area.
12.Ensure working platform shall be free from
HAZARD IDENTIFICATION AND RISK ASSESSMENT
debris, carried out
The periodically housekeeping.
13.Operatives shall be used suitable PPE, s
based on the activity
 Head protection

 Double eye protection with safety


goggles with face shield

 Ear Plug or earmuff

 Disposal cover all

 Safety shoes

14. Load allowed for worker is as per his age


and shall follow DM COP7-Material handling
and storage. (load shall not be exceeded not
more than 25 kg)
15.Ensure power source must be taken from
approved DB
16.All the electrical accessories free from
defectives
17.Ensure proper cable hose and cable
management.
18.Ensure work area must be clean and tidy.
Working at 1.Opeartives may Mason 1.Minor or major 1.TBT shall be conduct to all involved
height fall Helpers injury 4 4 16 operatives 2 4 8 Site Supervisor
2.Objects materials 2.Fatality 2.PTW shall be obtained prior commencing the
may fall. 3.Property damaged. task.
3.Platform may 3.Trained and competent operatives only
overload. allowed to work at height.
4.Poor material 4.Ensure working plat form shall be freeform
management obstacles.
5.Remove all unwanted materials from the
platform.
6.working area shall be barricaded prevent the
unauthorized entry placing suitable signages.
7.Maintain 3-point contact while climbing the
ladder.
8.Ensure access/egress shall be free from
obstacles.
9.Effective supervision in place to guide the
team members.
10.Job specific training shall be given to all
involved operatives.
HAZARD IDENTIFICATION AND RISK ASSESSMENT

11. Full body double lanyard shall be wear


working more than 1.8 mtr.
12.All the edges and opening shall be
protected by physical barrier using scaffolding
components.
13.Scaffold shall be inspected and approved
by scaffolding inspector
14.Scaffold shall be erected by competent and
trained scaffolders holding 3rd party certificate
(DAC)
15.Workshall be paused during poor weather
condition such as heavy fog, wind, sandstorm
and rain season.
16.Scaffold shall be reinspection after the
adverse weather.

1.Poor Illumination Mason 1.Minor/major injury 2.The work area shall be adequately CM
Performing the 2.Operatives. are Helper 2.Fatality 3 3 9 illuminated. 2 3 6 SE
plan task during not aware of Electricians 3.Electrocution 2.Pedestrian access should be clearly HSEO
night shift or potential hazards 4.Burns illuminated. Storekeeper
extension 3.Plant Movement. 3.All the plant & equipment, tools, tower lights Sub-contractor
hours. 4.Lone working shall be checked and approved prior
5.Slip/Trip/Fall commencing the night works.
6.Improper handling 4.Maintain a good housekeeping surrounding
of the electrical the working area.
accessories. 5.No lone working allowed at site.
6.Welfare facilities such as rest shelter, dining
area, drinking water areas should be provided
and well illuminated.
7.Adequate PPE for night works shall be
provided such a hi visibility, Jackets, Clear
safety goggles etc.
8.Ensure operatives job rotation in a place.
9.All work force shall be aware about the
reporting system in case of any ill-ness,
injuries immediate report to the concern
supervisors or EHS dept.
HAZARD IDENTIFICATION AND RISK ASSESSMENT

PREPARED BY REVIEWED BY (HSE Officer) REVIEWED BY APPROVED BY (Dar Al Omran)


Name: Vishakh M Nair Name: Vikas IV Name: Name:
Designation Project Designation: Safety Officer Designation: Designation:
: Engineer
Signature: Signature: Signature: Signature: