You are on page 1of 9

PROJECT:

METHOD STATEMENT FOR PAINTING WORKS

Doc. No:

00 05.04.2021 For Approval Ajin Arun


REV DATE REASON FOR REVISION BY CHECK APPROVED
Contents

1. SCOPE............................................................................................................................................... 3
2. ABBREVIATION................................................................................................................................ 3
3. REFERENCES................................................................................................................................... 3
4. RESPONSIBILITIES.......................................................................................................................... 4
5. SITE PLANNING AND PREPARATIONS.......................................................................................... 4
6. RESOURCES..................................................................................................................................... 5
6.1 PLANT, TOOLS & EQUIPMENT 5
6.2 MATERIALS 5
6.3 MANPOWER 6
7. Approvals......................................................................................................................................... 6
7.1 Training and Toolbox Talk: 6
8.0 GENERAL WORK METHODOLOGY.............................................................................................. 6
8.1 PRELIMINARY PREPARATION. 6
8.2 MATERIALS HANDLING AND PREPARATION.............................................................................7
................................................................................................................................................................ 7
9. Health & Safety 8
9.1 Risk Assessment Process Summary 8
9.2 Risk Assessments 8
9.3 General Work Instructions 8
10 Environmental Issues 8
10.1 Introduction 8
10.2 Definitions. 9
10.3 MITIGATION MEASURES............................................................................................................. 9
11. PERSONNEL PROTECTIVE EQUIPMENTS 10
12. EMERGENCY AND UNDESIRED CONDITIONS..........................................................................10
13. APPENDIX..................................................................................................................................... 11
13.1. RISK ASSESSMENT FOR PAINTING WORKS11
1. SCOPE

This method statement covers the general requirements and all operations in connection with
Internal and external painting work. and should be read in conjunction with the Project Quality Plan,
HSE Plan, Project Specifications, standard details & Issued for construction Drawings.

2. ABBREVIATION

1. MS - Method Statement
2. RA - Risk Assessment
3. E/E - Employer /Engineer
4. PPE -Personal Protective Equipment
5. HSE - Health Safety and Environment
6. PTW – Permit to Work
7. EPCM- Engineering, Procurement, and Construction management.

Other abbreviations are within the document.

3. REFERENCES

1. IFC Drawings

2. Architectural General Notes.

4. RESPONSIBILITIES

Construction Manager: Shall be responsible for the site implementation of these


procedures and to provide all the resources from competent and trained manpower, tools,
equipment and approved materials. He shall coordinate with the Quality Control Inspector for
inspections and issuance of Request for Inspections (RFI). He shall be responsible for the
safety of all personnel working on these activities.

Safety Manager: Shall be responsible for the implementation of safety procedures on site
and to ensure that the Risk Assessment within this method statement is followed. He shall
assign a competent Safety Officer to enforce these procedures and to provide guidance to
the operations where applicable.

QA / QC Manager: Shall be responsible for the proper implementation of these procedures


and ensure that inspections and tests are carried out according to the relevant approved
Inspection Test Plan. He shall assign a competent Quality Control Inspector to perform
inspections.

Site Engineer: Shall be responsible for overall execution of works, and also responsible for
following all HSE and quality procedures. He shall be responsible for the safety of all
personnel working on these activities.
Safety Officers: Shall be responsible for the implementation of all safety requirements and
to ensure that the works are undertaken in a safe and proper manner, all in accordance with
the approved Construction Phase HSE Plan, the approved method statement and the
approved Risk assessment.

Quality Control Inspector: Shall be responsible for inspection and verification that the
procedures are properly implemented and that inspections are undertaken in accordance
with the approved Inspection Test Plan in a timely manner.

5. SITE PLANNING AND PREPARATIONS

1. Ensure all the employees attend site-specific induction covering safety, environment and
quality.
1. Permit to work shall be obtained for all work activities.
2. First aiders shall be available during all work activities on site
3. All works shall be carried out under competent supervision.
4. Access to the working area is required for.

1. Plant and Equipment Access


2. Labor Access
3. Material deliveries

6. 1/3ton Trucks will be utilized to deliver materials in site in predetermined locations and storage
areas. The storage area will be located in such a manner that takes into account future works.

6. RESOURCES

6.1 PLANT, TOOLS & EQUIPMENT


The following items of equipment/ tools shall be utilized to complete the works:
 Painting Brush
 Roller
 Airless spray gun
 Scrappers
 Sandpaper
 Safety Equipment’s:
- Safety Barriers, warning tapes, Respirators, Nose masks, Face shield, etc.

6.2 MATERIALS

The specific materials for which approvals are required prior commencement of works are as
follow:
 Primer.
 Stucco Filler.
 Emulsion Paint.
 Texture compound.

Mockup samples of paint shall be approved prior to commencement of painting activity.

6.3 MANPOWER

The required manpower shall be reassessed for each activity. In general, the following
Supervision & resources will be in deployed:

All the site team will be working maximum 10hours on site at one shift.

 Painters
 helper
 QA/QC Engineer, Site Engineer, Safety Officer
 Foreman and charge hands
 Flag Man
 Operators for machineries.

7. Approvals

Internal Permit to work shall be obtained prior to start of work, Material approvals are required,
and Inspection request shall be raised and approved prior to start of Painting activity and during
the stages of painting activity.

7.1 Training and Toolbox Talk:

Training, QA/QC toolbox talk, and health & safety toolbox talks for all the activities shall be given
to all workmen involved on daily and weekly basis prior to commencement of task.

Third party training shall be carried out for the following personnel

1. Plant operators
2. Scaffolders
3. flagman
4. Lifting Supervisors
5. First aiders/ Fire wardens.

All other trainings include Site safety induction, Prestart briefing etc.

8.0 GENERAL WORK METHODOLOGY


8.1 PRELIMINARY PREPARATION.

 Hardware materials which are already fixed and not to be painted shall be removed.
Removal if not possible, it shall be covered/protected appropriately before surface
preparation and painting will commence.

 Clean and prepare concrete or cement plaster surfaces to be painted. Efflorescence, chalk,
dust, dirt, grease and oils shall be removed.
 The surface of the area to be painted would be prepared by removing loose particles,
blemishes, and deleterious materials by way of sanding.

 All oil and grease shall be removed with clean cloth prior to painting

 No exterior or exposed painting activity shall be carried out under adverse weather
conditions such as rain and dust storm etc.

 For working at height, fixed and movable scaffolding would be erected as per area
requirements. Scaffolding when erected shall be inspected with Safety officer prior to usage.
Operatives will be inductive before working at site. Pre-start meeting would be conducted
before the start of painting activities and toolbox meeting would be regularly conducted by
safety officer for all concern operatives.

 Inspection Request to be submitted for checking and approval of the Engineer.

8.2 MATERIALS HANDLING AND PREPARATION.

 Delivery materials to project site in original factory wrappings and in containers clearly
labeled with identification of approved manufacturer, brand name, fire-hazard classification,
lot number and quality or grade.
 Paint shall be stirred in their original container until smooth before use. It should be
thoroughly mixed and ground it shall not be settled shall not be thickened to such a degree
that it cannot be mixed easily with a paddle by stirring to a good uniform consistency.
 Paint shall show easy brushing good flowing and levelling properties.
 Follow approved manufacturer’s recommendations for special delivery, storage and handling
of materials.

8.3 PAINTING ON PLASTER, RENDERING, CONCRETE AND BLOCKWORK.

 The surface to receive paint shall be allowed to dry completely prior to application of paint, Plaster
surface shall be dry enough to commence painting application.

 The surface to receive paint shall be thoroughly clean, all crack blow hole shall be repaired
completely prior to application of paint.

 All Plastered and rendered surfaces shall be twice stopped with approved putty filler, the first coat
of putty shall be applied after the primer coat has completely dried out and the second coat after
first coat becomes dry as well.

 The Emulsion paint PVA Paint shall be applied in three coats the first thin coat and the other two
full coat each coat shall be allowed to dry before the next week.
 Paint shall dry to a uniform, smooth and flat appearance under ordinary condition, there shall be no
laps, skips, highlighted spots or brush marks.

 Recoating of previously painted surface shall not produce lighting, softening or other film
irregularities.

 Proper working platform shall be provided for the painters and full body harness must be wear
working more than 2mt height.

9. Health & Safety

9.1 Risk Assessment Process Summary

 The Health Safety and Environment Project Management Plan institutes the overall
mechanism for the risk management processes with regard to the Project. Processes are
implemented at the earliest stages within the project cycle, identifying risk and facilitating
opportunity for the application of appropriate mitigation strategies. As an integral part of the
planning process, prior to the commencement of any operational activity a suitable and
sufficient specific assessment of the risks associated with the works should be undertaken.

9.2 Risk Assessments

 A variety of mechanisms, such as method statement briefings and toolbox talks will be
implemented to ensure all relevant personnel are appropriately informed. STARRT Card is
explained to all workmen before start of activity.

 In addition to their safety induction received at their arrival on site, all the workers will have a
toolbox meeting in order to be briefed about the risks of their specific work task, prior to start
of works.

 A detailed risk assessment is attached to this Method Statement.

9.3 General Work Instructions

Starting instructions will be given by the supervisors at the start of each activity to explain the
methodology of works and to communicate safe working procedures to the operatives. These talks
are structured in a way to highlight to major risks involved in the activity and the various control
measures required in order to minimize the risk. It is delivered in a manner such as the key points
will be remembered by the operatives receiving it.

Toolbox talk meetings will be held for each crew, on group of employees, regarding more general
topics of the Project HSE Policy; in example lesson learned, near miss reports, implementation of
the requirements and message from the management or Engineer’s HSE Officers.

10 Environmental Issues

10.1 Introduction

As part of the development of the Organization’s Environmental Management System(s) the


significant issues that are faced both on site and within offices or other facilities should be
addressed. This approach subsequently allows for a systematic focus upon the important
environmental aspects to be adopted which in turn facilitates prioritization of limited resources.

10.2 Definitions.

An environmental aspect can be defined as an element of an organization’s activities, products


and/or services that can interact with the environment.

In general, environmental issues arising from the construction activities covered in the scope of this
Method Statement are mainly:

- Dust generation impact

- Mud generation

- Contamination

- Water usage

- Waste management

- Noise pollution

10.3 MITIGATION MEASURES

 Plant and Machinery shall be visually inspected regularly and serviced whenever required.

 Roads shall be dumped by water spraying to reduce dust.

 Toolbox talks and care shall be taken to avoid excessive usage of water.

 Waste materials be disposed to designated area

 General housekeeping rules for all operatives shall be observed.

11. PERSONNEL PROTECTIVE EQUIPMENTS

All workers will be issued and trained in use of the required PPE equipment to comply with contract
procedures and local regulations and will be supplemented with PPE as required by MSDS & Risk
assessments. This will include but will not be limited to;

 Hard Hats
 Safety Boots with ankle support and steel toe caps
 Safety Goggles
 High Visibility Vests / Overalls with integrated reflective strips
 Hand gloves
 Face Mask
 Disposal Cover all for concreting team

12. EMERGENCY AND UNDESIRED CONDITIONS

The following precautions have to be maintained to meet an Emergency or an undesired condition


on site.
1. Assembly point must be clearly identified & kept clear at all time.
2. All the work force has to be aware where to go to reach a place of safety or to get rescue
equipment in case of emergency. This shall be ensured in all toolbox talks.
3. Emergency direction signs and enough emergency exists are to be provided for everyone to
escape quickly and keep emergency door/walkways and escape routes are not obstructed
and clearly marked.
4. Nominate competent person to take control (a competent person is someone with the
necessary skills, knowledge and experience to manage emergency response procedure).
5. Sufficient first aiders and first aid box must be available at site.
6. Drinking water should be provided at a reasonable distance from the work location.
7. Sufficient number of fire ceasing (extinguisher) should be available at site with clear
identification.
8. Fire warden must be available at site. (DAC Certified) to plan essential action such as
emergency plant/work shutdown, isolation or making process safe.
9. Clearly identified important items like fire point, assembly point shut off valves and electrical
isolators etc.
10. Emergency procedure, don’t forget the needs of people with disabilities and vulnerable
workers
11. The workers should be trained for emergency procedures.
12. Work should not resume after an emergency if a serious danger remains.

13. APPENDIX

13.1. RISK ASSESSMENT FOR PAINTING WORKS

You might also like