EJN764-NEW HAZARDOUS WASTE AREA FOR AMINES PLANT PROGRESS 19-Dec-21 01:20 PM

Activity ID Activity Name Original Budgeted BL Project Start BL Project Finish Start Finish Units % 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Duration Labor Complete ay
Nov Dec Jan Feb Mar Apr
Units
EJN764-NEW HAZARDOUS WASTE AREA 125 13220 15-Nov-21 07:00 AM 14-Mar-22 05:00 PM 15-Nov-21 07:00 AM A 09-Apr-22 05:00 PM 2.72% 09-Apr-22

BIDDING AND
A CONTRACT AWARD 20 120 15-Nov-21 07:00 AM 22-Nov-21 05:00 PM 15-Nov-21 07:00 AM A 05-Dec-21 03:00 PM A 100% 05-Dec-21 03:00 PM A, BIDDING AND CONTRACT AWARD
A1000 Contract Award Notification 1 10 15-Nov-21 07:00 AM 15-Nov-21 05:00 PM 15-Nov-21 07:00 AM A 15-Nov-21 05:00 PM A 100% Contract Award Notification

A1010 Receipt of Purchase order 1 10 16-Nov-21 07:00 AM 16-Nov-21 05:00 PM 16-Nov-21 07:00 AM A 16-Nov-21 05:00 PM A 100% Receipt of Purchase order

A1020 GIH Training 2 40 16-Nov-21 07:00 AM 17-Nov-21 05:00 PM 05-Dec-21 01:00 PM A 05-Dec-21 03:00 PM A 100% GIH Training

A1030 Kick off Meeting 1 10 16-Nov-21 07:00 AM 16-Nov-21 05:00 PM 16-Nov-21 07:00 AM A 16-Nov-21 05:00 PM A 100% Kick off Meeting

A1040 Document Submision 5 50 17-Nov-21 07:00 AM 22-Nov-21 05:00 PM 25-Nov-21 07:00 AM A 25-Nov-21 02:00 PM A 100% Document Submision

PROJECT M
MILE STONES 123 100 16-Nov-21 07:00 AM 13-Mar-22 05:00 PM 16-Nov-21 07:00 AM A 07-Apr-22 05:00 PM 100% 07-Apr-22 0

A1050 Project Start 0 0 16-Nov-21 07:00 AM 01-Dec-21 07:00 AM A 0% Project Start, 01-Dec-21 07:00 AM A

A1060 Project Finish 0 0 13-Mar-22 05:00 PM 07-Apr-22 05:00 PM 0% Project Fini

A1710 P6 Schedule Submission 4 40 16-Nov-21 07:00 AM 20-Nov-21 05:00 PM 16-Nov-21 07:00 AM A 20-Nov-21 05:00 PM A 100% P6 Schedule Submission

A1720 Refining of P6 Schedule 2 30 21-Nov-21 07:00 AM 22-Nov-21 05:00 PM 21-Nov-21 07:00 AM A 22-Nov-21 05:00 PM A 100% Refining of P6 Schedule

A1730 Finalization of P6 Schedule 2 30 23-Nov-21 07:00 AM 24-Nov-21 05:00 PM 23-Nov-21 07:00 AM A 24-Nov-21 05:00 PM A 100% Finalization of P6 Schedule

PROCUREMENT
PROCUREM 79 790 17-Nov-21 07:00 AM 16-Feb-22 05:00 PM 17-Nov-21 07:00 AM A 02-Mar-22 09:00 AM 17.72% 02-Mar-22 09:00 AM, PROC

A1070 Structural Materials by GACC 31 60 17-Nov-21 07:00 AM 22-Dec-21 05:00 PM 17-Nov-21 07:00 AM A 16-Jan-22 03:00 PM 20% Structural Materials by GACC

A1080 Civil TPER Materials Procurement by 79 70 17-Nov-21 07:00 AM 16-Feb-22 05:00 PM 17-Nov-21 07:00 AM A 02-Mar-22 09:00 AM 20% Civil TPER Materials Procure
GACC
A1090 Electrical Panel Drawing Submission & 6 80 17-Nov-21 07:00 AM 23-Nov-21 05:00 PM 06-Dec-21 07:00 AM A 23-Dec-21 03:00 PM 20% Electrical Panel Drawing Submission & Approvel by Sadara
Approvel by Sadara
A1100 PO Issue for Electrical Panel 5 50 24-Nov-21 07:00 AM 29-Nov-21 05:00 PM 23-Dec-21 03:00 PM 29-Dec-21 03:00 PM 0% PO Issue for Electrical Panel

A1110 Panel Material Reciving & Inspection 31 60 30-Nov-21 07:00 AM 04-Jan-22 05:00 PM 29-Dec-21 03:00 PM 03-Feb-22 03:00 PM 0% Panel Material Reciving & Inspection

A1120 Electrical Light Data Sheet & Catalog 6 80 17-Nov-21 07:00 AM 23-Nov-21 05:00 PM 06-Dec-21 07:00 AM A 23-Dec-21 03:00 PM 20% Electrical Light Data Sheet & Catalog Approvel by Sadara
Approvel by Sadara
A1130 PO Issue for Electrical Light 5 50 24-Nov-21 07:00 AM 29-Nov-21 05:00 PM 23-Dec-21 03:00 PM 29-Dec-21 03:00 PM 0% PO Issue for Electrical Light

A1140 Electrical Light Material Recieving & 31 60 30-Nov-21 07:00 AM 04-Jan-22 05:00 PM 12-Dec-21 07:00 AM A 27-Jan-22 01:00 PM 20% Electrical Light Material Recieving & Inspectio
Inspection
A1150 Light Pole Catalog Approvel by Sadara. 6 60 17-Nov-21 07:00 AM 23-Nov-21 05:00 PM 19-Dec-21 07:00 AM 25-Dec-21 05:00 PM 0% Light Pole Catalog Approvel by Sadara.

A1160 PO Issue for Light Pole 5 50 24-Nov-21 07:00 AM 29-Nov-21 05:00 PM 26-Dec-21 07:00 AM 30-Dec-21 05:00 PM 0% PO Issue for Light Pole

A1170 Light Pole Material reciving & Inspection 31 60 30-Nov-21 07:00 AM 04-Jan-22 05:00 PM 01-Jan-22 07:00 AM 05-Feb-22 05:00 PM 0% Light Pole Material reciving & Inspection

A1260 Fencing Material by GACC 46 50 30-Nov-21 07:00 AM 22-Jan-22 05:00 PM 17-Nov-21 07:00 AM A 12-Feb-22 03:00 PM 20% Fencing Material by GACC

A1920 Rebar & Form Work Material by GACC 60 60 17-Nov-21 07:00 AM 25-Jan-22 05:00 PM 17-Nov-21 07:00 AM A 10-Dec-21 05:00 PM A 100% Rebar & Form Work Material by GACC

SHOP WORKS
WOR 22 760 23-Dec-21 07:00 AM 17-Jan-22 05:00 PM 16-Jan-22 03:00 PM 10-Feb-22 03:00 PM 0% 10-Feb-22 03:00 PM, SHOP WORKS

Structure Fo
For Electrical Panel 22 760 23-Dec-21 07:00 AM 17-Jan-22 05:00 PM 16-Jan-22 03:00 PM 10-Feb-22 03:00 PM 0% 10-Feb-22 03:00 PM, Structure For El

Actual Level of Effort Remaining Work Milestone Page 1 of 4


Actual Work Critical Remaining Work summary © Oracle Corporation
EJN764-NEW HAZARDOUS WASTE AREA FOR AMINES PLANT PROGRESS 19-Dec-21 01:20 PM
Activity ID Activity Name Original Budgeted BL Project Start BL Project Finish Start Finish Units % 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Duration Labor Complete ay
Nov Dec Jan Feb Mar Apr
Units
A1180 Material Reciving Inspection 2 40 23-Dec-21 07:00 AM 25-Dec-21 05:00 PM 16-Jan-22 03:00 PM 18-Jan-22 03:00 PM 0% Material Reciving Inspection

A1190 Structural Fabrication 7 320 26-Dec-21 07:00 AM 02-Jan-22 05:00 PM 18-Jan-22 03:00 PM 26-Jan-22 03:00 PM 0% Structural Fabrication

A1200 Welding works 6 240 03-Jan-22 07:00 AM 09-Jan-22 05:00 PM 26-Jan-22 03:00 PM 02-Feb-22 03:00 PM 0% Welding works

A1210 Inspection after Welding 2 40 10-Jan-22 07:00 AM 11-Jan-22 05:00 PM 02-Feb-22 03:00 PM 05-Feb-22 03:00 PM 0% Inspection after Welding

A1220 Galvanizing & Inspection 5 120 12-Jan-22 07:00 AM 17-Jan-22 05:00 PM 05-Feb-22 03:00 PM 10-Feb-22 03:00 PM 0% Galvanizing & Inspection

SITE WORKS
WORK 91 11190 17-Nov-21 07:00 AM 08-Mar-22 05:00 PM 19-Dec-21 07:00 AM 03-Apr-22 05:00 PM 0% 03-Apr-22 05

Scaffolding Works 6 450 17-Nov-21 07:00 AM 23-Nov-21 05:00 PM 19-Dec-21 07:00 AM 25-Dec-21 05:00 PM 0% 25-Dec-21 05:00 PM, Scaffolding Works
A1230 Scaffolding Material Mobilization for 3 210 17-Nov-21 07:00 AM 20-Nov-21 05:00 PM 19-Dec-21 07:00 AM 21-Dec-21 05:00 PM 0% Scaffolding Material Mobilization for Barricading Works
Barricading Works
A1240 Barricading Works. 3 240 21-Nov-21 07:00 AM 23-Nov-21 05:00 PM 22-Dec-21 07:00 AM 25-Dec-21 05:00 PM 0% Barricading Works.

Civil Works 70 8080 23-Nov-21 07:00 AM 16-Feb-22 05:00 PM 19-Dec-21 07:00 AM 09-Mar-22 03:00 PM 0% 09-Mar-22 03:00 PM, Civ
A1700 Radar Survey 7 210 23-Nov-21 07:00 AM 30-Nov-21 05:00 PM 19-Dec-21 07:00 AM 26-Dec-21 05:00 PM 0% Radar Survey

Fencing W
Works 22 1210 23-Jan-22 07:00 AM 16-Feb-22 05:00 PM 12-Feb-22 03:00 PM 09-Mar-22 03:00 PM 0% 09-Mar-22 03:00 PM, Fe
A1270 Material Mobilization 4 200 23-Jan-22 07:00 AM 26-Jan-22 05:00 PM 12-Feb-22 03:00 PM 16-Feb-22 03:00 PM 0% Material Mobilization

A1280 Fencing Works 11 700 27-Jan-22 07:00 AM 08-Feb-22 05:00 PM 16-Feb-22 03:00 PM 01-Mar-22 03:00 PM 0% Fencing Works

A1290 Inspection 3 150 09-Feb-22 07:00 AM 12-Feb-22 05:00 PM 01-Mar-22 03:00 PM 05-Mar-22 03:00 PM 0% Inspection

A1300 Existing Fence Cutting after Isolation 4 160 13-Feb-22 07:00 AM 16-Feb-22 05:00 PM 05-Mar-22 03:00 PM 09-Mar-22 03:00 PM 0% Existing Fence Cutting af

Paving Works
Wo for New Hazaed Waste Area 53 3040 01-Dec-21 07:00 AM 31-Jan-22 05:00 PM 27-Dec-21 07:00 AM 26-Feb-22 05:00 PM 0% 26-Feb-22 05:00 PM, Paving
A1340 Clear & Grub 11 400 01-Dec-21 07:00 AM 13-Dec-21 05:00 PM 27-Dec-21 07:00 AM 08-Jan-22 05:00 PM 0% Clear & Grub

A1350 Excavation 8 640 14-Dec-21 07:00 AM 22-Dec-21 05:00 PM 09-Jan-22 07:00 AM 17-Jan-22 05:00 PM 0% Excavation

A1360 Backfilling & Compaction for Concrete 11 660 23-Dec-21 07:00 AM 04-Jan-22 05:00 PM 18-Jan-22 07:00 AM 30-Jan-22 05:00 PM 0% Backfilling & Compaction for Concrete

A1370 Rebar & Form Works 7 700 05-Jan-22 07:00 AM 12-Jan-22 05:00 PM 31-Jan-22 07:00 AM 07-Feb-22 05:00 PM 0% Rebar & Form Works

A1380 Concreting Work 5 240 13-Jan-22 07:00 AM 18-Jan-22 05:00 PM 08-Feb-22 07:00 AM 13-Feb-22 05:00 PM 0% Concreting Work

A1390 Curing & Inspection 7 160 19-Jan-22 07:00 AM 26-Jan-22 05:00 PM 14-Feb-22 07:00 AM 21-Feb-22 05:00 PM 0% Curing & Inspection

A1470 Paniting For Paving Area 4 240 27-Jan-22 07:00 AM 31-Jan-22 05:00 PM 22-Feb-22 07:00 AM 26-Feb-22 05:00 PM 0% Paniting For Paving Area

Electrical Panel Foundation 30 1630 16-Dec-21 07:00 AM 19-Jan-22 05:00 PM 11-Jan-22 07:00 AM 14-Feb-22 05:00 PM 0% 14-Feb-22 05:00 PM, Electrical Pan
A1400 Excavation 6 420 16-Dec-21 07:00 AM 22-Dec-21 05:00 PM 11-Jan-22 07:00 AM 17-Jan-22 05:00 PM 0% Excavation

A1410 Compaction for Concrete 5 400 23-Dec-21 07:00 AM 28-Dec-21 05:00 PM 18-Jan-22 07:00 AM 23-Jan-22 05:00 PM 0% Compaction for Concrete

A1420 Rebar & Form Works 7 450 29-Dec-21 07:00 AM 05-Jan-22 05:00 PM 24-Jan-22 07:00 AM 31-Jan-22 05:00 PM 0% Rebar & Form Works

A1430 Concreting Work 5 200 06-Jan-22 07:00 AM 11-Jan-22 05:00 PM 01-Feb-22 07:00 AM 06-Feb-22 05:00 PM 0% Concreting Work

A1440 Curing & Inspection 7 160 12-Jan-22 07:00 AM 19-Jan-22 05:00 PM 07-Feb-22 07:00 AM 14-Feb-22 05:00 PM 0% Curing & Inspection

Actual Level of Effort Remaining Work Milestone Page 2 of 4


Actual Work Critical Remaining Work summary © Oracle Corporation
EJN764-NEW HAZARDOUS WASTE AREA FOR AMINES PLANT PROGRESS 19-Dec-21 01:20 PM
Activity ID Activity Name Original Budgeted BL Project Start BL Project Finish Start Finish Units % 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Duration Labor Complete ay
Nov Dec Jan Feb Mar Apr
Units
Lighting P
Pole Foundation 35 1630 19-Dec-21 07:00 AM 27-Jan-22 05:00 PM 13-Jan-22 07:00 AM 22-Feb-22 05:00 PM 0% 22-Feb-22 05:00 PM, Lighting P
A1490 Excavation 8 420 19-Dec-21 07:00 AM 27-Dec-21 05:00 PM 13-Jan-22 07:00 AM 22-Jan-22 05:00 PM 0% Excavation

A1500 Compaction for Concrete 7 400 28-Dec-21 07:00 AM 04-Jan-22 05:00 PM 23-Jan-22 07:00 AM 30-Jan-22 05:00 PM 0% Compaction for Concrete

A1510 Rebar & Form Works 8 450 05-Jan-22 07:00 AM 13-Jan-22 05:00 PM 31-Jan-22 07:00 AM 08-Feb-22 05:00 PM 0% Rebar & Form Works

A1520 Concreting Work 5 200 15-Jan-22 07:00 AM 19-Jan-22 05:00 PM 09-Feb-22 07:00 AM 14-Feb-22 05:00 PM 0% Concreting Work

A1530 Curing & Inspection 7 160 20-Jan-22 07:00 AM 27-Jan-22 05:00 PM 15-Feb-22 07:00 AM 22-Feb-22 05:00 PM 0% Curing & Inspection

Structural Installation 9 360 29-Jan-22 07:00 AM 07-Feb-22 05:00 PM 23-Feb-22 07:00 AM 05-Mar-22 05:00 PM 0% 05-Mar-22 05:00 PM, Struc
A1740 Panel Structure Installation 4 200 29-Jan-22 07:00 AM 01-Feb-22 05:00 PM 23-Feb-22 07:00 AM 27-Feb-22 05:00 PM 0% Panel Structure Installation

A1750 Alignment & Bolt Tightining 3 120 02-Feb-22 07:00 AM 05-Feb-22 05:00 PM 28-Feb-22 07:00 AM 02-Mar-22 05:00 PM 0% Alignment & Bolt Tightining

A1760 Inspection 2 40 06-Feb-22 07:00 AM 07-Feb-22 05:00 PM 03-Mar-22 07:00 AM 05-Mar-22 05:00 PM 0% Inspection

Electrical Works
W 34 2660 29-Jan-22 07:00 AM 08-Mar-22 05:00 PM 23-Feb-22 07:00 AM 03-Apr-22 05:00 PM 0% 03-Apr-22 05
Light Panel
Pane Installation 13 530 08-Feb-22 07:00 AM 22-Feb-22 05:00 PM 06-Mar-22 07:00 AM 20-Mar-22 05:00 PM 0% 20-Mar-22 05:00 PM
A1770 Light Panel Installation 4 200 08-Feb-22 07:00 AM 12-Feb-22 05:00 PM 06-Mar-22 07:00 AM 09-Mar-22 05:00 PM 0% Light Panel Installation

A1780 Cabling Laying 3 120 13-Feb-22 07:00 AM 15-Feb-22 05:00 PM 10-Mar-22 07:00 AM 13-Mar-22 05:00 PM 0% Cabling Laying

A1790 Glanding & Termination Work 3 120 16-Feb-22 07:00 AM 19-Feb-22 05:00 PM 14-Mar-22 07:00 AM 16-Mar-22 05:00 PM 0% Glanding & Terminatio

A1850 Testing & Inspection 3 90 20-Feb-22 07:00 AM 22-Feb-22 05:00 PM 17-Mar-22 07:00 AM 20-Mar-22 05:00 PM 0% Testing & Inspection

Light Pole Installation 27 990 29-Jan-22 07:00 AM 28-Feb-22 05:00 PM 23-Feb-22 07:00 AM 26-Mar-22 05:00 PM 0% 26-Mar-22 05:00
A1800 Light Pole Installation 6 240 29-Jan-22 07:00 AM 03-Feb-22 05:00 PM 23-Feb-22 07:00 AM 01-Mar-22 05:00 PM 0% Light Pole Installation

A1810 Wall penetration for cabling 5 200 05-Feb-22 07:00 AM 09-Feb-22 05:00 PM 02-Mar-22 07:00 AM 07-Mar-22 05:00 PM 0% Wall penetration for cablin

A1820 Conduiting & sealing Works 5 180 10-Feb-22 07:00 AM 15-Feb-22 05:00 PM 08-Mar-22 07:00 AM 13-Mar-22 05:00 PM 0% Conduiting & sealing W

A1830 Cabling Laying 4 160 16-Feb-22 07:00 AM 20-Feb-22 05:00 PM 14-Mar-22 07:00 AM 17-Mar-22 05:00 PM 0% Cabling Laying

A1840 Glanding & Termination Works 4 120 21-Feb-22 07:00 AM 24-Feb-22 05:00 PM 19-Mar-22 07:00 AM 22-Mar-22 05:00 PM 0% Glanding & Termin

A1860 Testing & Inspection 3 90 26-Feb-22 07:00 AM 28-Feb-22 05:00 PM 23-Mar-22 07:00 AM 26-Mar-22 05:00 PM 0% Testing & Inspec

Electrical Light Installation 10 300 26-Feb-22 07:00 AM 08-Mar-22 05:00 PM 23-Mar-22 07:00 AM 03-Apr-22 05:00 PM 0% 03-Apr-22 05
A1930 Cable Laying 3 120 26-Feb-22 07:00 AM 28-Feb-22 05:00 PM 23-Mar-22 07:00 AM 26-Mar-22 05:00 PM 0% Cable Laying

A1940 Light Installaion 2 60 01-Mar-22 07:00 AM 02-Mar-22 05:00 PM 27-Mar-22 07:00 AM 28-Mar-22 05:00 PM 0% Light Installaion

A1950 Glanding & Termination 3 80 03-Mar-22 07:00 AM 06-Mar-22 05:00 PM 29-Mar-22 07:00 AM 31-Mar-22 05:00 PM 0% Glanding & Te

A1960 Inspection & Testing 2 40 07-Mar-22 07:00 AM 08-Mar-22 05:00 PM 02-Apr-22 07:00 AM 03-Apr-22 05:00 PM 0% Inspection &

Grounding Work 21 840 09-Feb-22 07:00 AM 05-Mar-22 05:00 PM 01-Mar-22 03:00 PM 26-Mar-22 03:00 PM 0% 26-Mar-22 03:00
A1870 Ground rod Installation 5 200 09-Feb-22 07:00 AM 14-Feb-22 05:00 PM 01-Mar-22 03:00 PM 07-Mar-22 03:00 PM 0% Ground rod Installation

Actual Level of Effort Remaining Work Milestone Page 3 of 4


Actual Work Critical Remaining Work summary © Oracle Corporation
EJN764-NEW HAZARDOUS WASTE AREA FOR AMINES PLANT PROGRESS 19-Dec-21 01:20 PM
Activity ID Activity Name Original Budgeted BL Project Start BL Project Finish Start Finish Units % 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Duration Labor Complete ay
Nov Dec Jan Feb Mar Apr
Units
A1880 Ground Cable Installation 5 200 15-Feb-22 07:00 AM 20-Feb-22 05:00 PM 07-Mar-22 03:00 PM 13-Mar-22 03:00 PM 0% Ground Cable Installati

A1890 CAD Welding 4 160 21-Feb-22 07:00 AM 24-Feb-22 05:00 PM 13-Mar-22 03:00 PM 17-Mar-22 03:00 PM 0% CAD Welding

A1900 Grounding Lug Installation 4 160 26-Feb-22 07:00 AM 01-Mar-22 05:00 PM 17-Mar-22 03:00 PM 22-Mar-22 03:00 PM 0% Grounding Lug Ins

A1910 Grounding Resistance test. 3 120 02-Mar-22 07:00 AM 05-Mar-22 05:00 PM 22-Mar-22 03:00 PM 26-Mar-22 03:00 PM 0% Grounding Resis

MC WALK DOWN & PUNCH CLEARANCE 4 140 09-Mar-22 07:00 AM 13-Mar-22 05:00 PM 04-Apr-22 07:00 AM 07-Apr-22 05:00 PM 0% 07-Apr-22 0

A1650 MC Walk Down & Punch Clearance 2 80 09-Mar-22 07:00 AM 10-Mar-22 05:00 PM 04-Apr-22 07:00 AM 05-Apr-22 05:00 PM 0% MC Walk Do

A1660 PSSR walk Down & Punch Clearance 2 60 12-Mar-22 07:00 AM 13-Mar-22 05:00 PM 06-Apr-22 07:00 AM 07-Apr-22 05:00 PM 0% PSSR walk

HAND OVER
OVE 3 120 12-Mar-22 07:00 AM 14-Mar-22 05:00 PM 06-Apr-22 07:00 AM 09-Apr-22 05:00 PM 0% 09-Apr-22

A1670 Document Submission 1 40 12-Mar-22 07:00 AM 12-Mar-22 05:00 PM 06-Apr-22 07:00 AM 06-Apr-22 05:00 PM 0% Document S

A1680 Construction Completion 1 40 13-Mar-22 07:00 AM 13-Mar-22 05:00 PM 07-Apr-22 07:00 AM 07-Apr-22 05:00 PM 0% Constructio

A1690 Hand Over 1 40 14-Mar-22 07:00 AM 14-Mar-22 05:00 PM 09-Apr-22 07:00 AM 09-Apr-22 05:00 PM 0% Hand Ove

Actual Level of Effort Remaining Work Milestone Page 4 of 4


Actual Work Critical Remaining Work summary © Oracle Corporation