BOROUGE 4 PROJECT - EPC PACKAGE 4 (PO U O)

Activity ID Activity Name Original Start Finish


Duration

BOROUGE 4 PROJECT - EPC PACKAGE 4 (PO & U & O) 192 06-Feb-23 31-Oct-23

HDPE PIPING WORKS AND RELATED LAYING WORKS 192 06-Feb-23 31-Oct-23
PROJECT MILESTONES 184 06-Feb-23 30-Oct-23
A1500 Contract Award 0 06-Feb-23
A1510 KOM 0 10-Feb-23*
A1520 Mobilization 0 11-Feb-23*
A1540 Survey and Earthwork start 0 25-Feb-23*
A1530 TSF 0 04-Mar-23*
A1570 Mechanical works 0 15-Mar-23*
A1550 PO works completion 0 31-Jul-23
A1560 U&O works completion 0 30-Oct-23
A1580 Mechanical Completion 0 30-Oct-23
COSTRUCTION 170 25-Feb-23 30-Oct-23
U&O 170 25-Feb-23 30-Oct-23
PRIORITY 1 (GROUP 1A,1B & 8) 36 25-Feb-23 18-Apr-23
PRIORITY 2 (GROUP 3,7 & 1C) 34 19-Apr-23 07-Jun-23
PRIORITY 3 (GROUP 4) 34 07-Jun-23 26-Jul-23
PRIORITY 4 (GROUP 5A & 6A) 34 27-Jul-23 14-Sep-23
PRIORITY 5 (GROUP 5B & 6B) 32 14-Sep-23 30-Oct-23
PO 107 25-Feb-23 31-Jul-23
PRIORITY 1 (GROUP 2A) 57 25-Feb-23 19-May-23
PRIORITY 2 (GROUP 2B) 57 09-May-23 31-Jul-23
Mechanical Completion 1 30-Oct-23 30-Oct-23
Hand Over 1 31-Oct-23 31-Oct-23

Page 1 of 1 TASK filter: All Activities