Activity ID Activity Name Original Current Start Current Finish 101 102

Duration Aug 22 Aug 29 Sep 05 Sep 12 Sep 19 Sep 26 Oct 03


Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat
Telecom Towers Y80 Masantol 45 23-Aug-21 06-Oct-21

Construction Telecom Tower Y80 Masantol 45 23-Aug-21 06-Oct-21


Milestone 45 23-Aug-21 06-Oct-21
MS1000 Kick-off Meeting 0 23-Aug-21
MS1010 Notice to Proceed 0 23-Aug-21
MS1020 Hand over of site (by client) 0 23-Aug-21
MS1030 Micro-piling Completed 0 14-Sep-21
MS1040 Footing/Pedestal Completed 0 29-Sep-21
MS1050 Tower Lattice Erection Completed 0 06-Oct-21
General Requirements 2 23-Aug-21 24-Aug-21
GR1000 Mobilization 1 23-Aug-21 23-Aug-21
GR1010 Setting up Temporary Facilities 1 23-Aug-21 23-Aug-21
GR1020 Site Layout 1 24-Aug-21 24-Aug-21
Procurement 9 23-Aug-21 31-Aug-21
Micropile 8 23-Aug-21 30-Aug-21
Rebars 5 23-Aug-21 27-Aug-21
PROC1000 Rebar P.O 2 23-Aug-21 24-Aug-21
PROC1010 Rebar Delivery 3 25-Aug-21 27-Aug-21
Pile Cage 24" 8 23-Aug-21 30-Aug-21
PROC1020 Steel Drum P.O 2 23-Aug-21 24-Aug-21
PROC1030 Steel Drum Delivery 6 25-Aug-21 30-Aug-21
PIle Cage 12" 8 23-Aug-21 30-Aug-21
PROC1040 Black Iron Pipe P.O 2 23-Aug-21 24-Aug-21
PROC1050 Black Iron Pipe Delivery 6 25-Aug-21 30-Aug-21
Others Materials 8 23-Aug-21 30-Aug-21
PROC1060 Miscellaneous Materials P.O 2 23-Aug-21 24-Aug-21
PROC1070 Miscellaneous Materials Delivery 6 25-Aug-21 30-Aug-21
Footing Pile Cap 9 23-Aug-21 31-Aug-21
Rebars & Formworks 9 23-Aug-21 31-Aug-21
PROC1080 Rebars & Formworks P.O 2 23-Aug-21 24-Aug-21
PROC1090 Rebars & Formworks Delivery 7 25-Aug-21 31-Aug-21
Other Materials 7 23-Aug-21 29-Aug-21
PROC1100 Miscellaneous Materials P.O 2 23-Aug-21 24-Aug-21
PROC1110 Miscellaneous Materials Delivery 7 23-Aug-21 29-Aug-21
Piling Services 4 23-Aug-21 26-Aug-21
PROC1120 Micropile Service P.O 2 23-Aug-21 24-Aug-21
PROC1130 Micropile Service Mobilization 2 25-Aug-21 26-Aug-21
Construction 41 27-Aug-21 06-Oct-21
Foundation 34 27-Aug-21 29-Sep-21
Micro Pile Foundation 33 27-Aug-21 28-Sep-21
Micro Piling (F1) 33 27-Aug-21 28-Sep-21
CONF1010 Borehole Excavation 4 27-Aug-21 30-Aug-21
CONF1000 Rebar Fabrication 5 28-Aug-21 01-Sep-21
CONF1020 Pile Casing Installation 5 31-Aug-21 04-Sep-21
CONF1030 Rebar Installation 4 01-Sep-21 04-Sep-21
CONF1040 Concrete Pouring 4 01-Sep-21 04-Sep-21
CONF1050 Concrete Curing 28 01-Sep-21 28-Sep-21
Micro Piling (F2) 17 31-Aug-21 16-Sep-21
CONF1070 Borehole Excavation 4 31-Aug-21 03-Sep-21
CONF1080 Pile Casing Installation 5 31-Aug-21 04-Sep-21
CONF1060 Rebar Fabrication 5 02-Sep-21 06-Sep-21
CONF1090 Rebar Installation 4 03-Sep-21 06-Sep-21
CONF1100 Concrete Pouring 4 03-Sep-21 06-Sep-21
CONF1110 Concrete Curing 14 03-Sep-21 16-Sep-21
Micro Piling (F3) 11 04-Sep-21 14-Sep-21
CONF1130 Borehole Excavation 4 04-Sep-21 07-Sep-21
CONF1140 Pile Casing Installation 5 04-Sep-21 08-Sep-21
CONF1120 Rebar Fabrication 5 07-Sep-21 11-Sep-21
CONF1150 Rebar Installation 4 08-Sep-21 11-Sep-21
CONF1160 Concrete Pouring 4 08-Sep-21 11-Sep-21
CONF1170 Concrete Curing 7 08-Sep-21 14-Sep-21
Footing Foundation (1, 2, 3) 15 15-Sep-21 29-Sep-21
CONF1180 Lean Concreting 2 15-Sep-21 16-Sep-21
CONF1190 Rebar & Formworks Installation 7 15-Sep-21 21-Sep-21
CONF1200 Concrete Pouring 1 22-Sep-21 22-Sep-21
CONF1210 Concrete Curing 7 23-Sep-21 29-Sep-21
Pedestal (1, 2, 3) 12 18-Sep-21 29-Sep-21
CONF1220 Rebar & Formworks Installation 7 18-Sep-21 24-Sep-21
CONF1230 Bolt Setting 5 19-Sep-21 23-Sep-21
CONF1240 Concrete Pouring 1 24-Sep-21 24-Sep-21
CONF1250 Concrete Curing 5 25-Sep-21 29-Sep-21
Structural steel tower 7 30-Sep-21 06-Oct-21
CONSS1000 Steel Structure Erection 7 30-Sep-21 06-Oct-21

Date Revision Checked Approved Actual Work Milestone


Y80 Masantol Tower Replacement Project Schedule 03-Aug-11 Issued for Informa on RBB RBB
Remaining Work Critical Miles...
CONSTRUCTION OF SELF-SUPPORTING TOWER (A2DN TYPE) Y80 BRGY.
Critical Remaining Work Summary
STO.NINO, MASANTOL PAMPANGA
Baseline Milestone