VILLA - A 114

Activity ID Activity Name Start Finish Original Total Float J A S O N D J F M A M J J A S O N D J


Duration 2

ITEM-3 VILLA - A114 08-Aug-23 07-Nov-24 409 0 07-Nov-24, ITEM-3 VILLA

ITEM-3.1 MILESTONE 08-Aug-23 07-Nov-24 409 0 07-Nov-24, ITEM-3.1 MIL


A1680 Commencement Date 08-Aug-23 0 0 Commencement Date, 08-Aug-23
A1760 Cast raft foundation 23-Oct-23 0 341 Cast raft foundation,
A1740 Cast ground floor slab 12-Dec-23 0 296 Cast ground floor slab,
A1720 Cast first floor slab 29-Jan-24 0 253 Cast first floor slab,
A1790 Casting roof floor slab 08-Mar-24 0 218 Casting roof floor slab,
A1770 Cast for top roof slab 09-Apr-24 0 190 Cast for top roof slab,
A1690 Completion Date 07-Nov-24 0 0 Completion Date,
ITEM-3.5 ID PACKAGE WILL BE ADDED LATER 0 0

ITEM-3.7 SITE WORK 08-Aug-23 09-Sep-23 30 0 09-Sep-23, ITEM-3.7 SITE WORK

ITEM-3.7.1 MOBILIZATION 08-Aug-23 09-Sep-23 30 0 09-Sep-23, ITEM-3.7.1 MOBILIZATION


A1700 Site Mobilization 08-Aug-23 09-Sep-23 30 0 Site Mobilization
ITEM-3.3 ENGINEERING 08-Aug-23 31-Oct-23 75 334 31-Oct-23, ITEM-3.3 ENGINEERING

ITEM-3.3.4 SHOP DRAWINGS 09-Sep-23 30-Sep-23 19 360 30-Sep-23, ITEM-3.3.4 SHOP DRAWINGS
ITEM-3.3.4.4 MEP 09-Sep-23 30-Sep-23 19 360 30-Sep-23, ITEM-3.3.4.4 MEP
ITEM-3.3.4.4.1 PREPARATION & SUBMISSION 09-Sep-23 26-Sep-23 15 361 26-Sep-23, ITEM-3.3.4.4.1 PREPARATION & SUBMISSION
ITEM-3.3.4.4.1.1 CIVIL 09-Sep-23 15-Sep-23 5 360 15-Sep-23, ITEM-3.3.4.4.1.1 CIVIL
A3270 Prepare & Submit - Civil 09-Sep-23 15-Sep-23 5 360 Prepare & Submit - Civil
ITEM-3.3.4.4.1.2 ELECTRICAL 09-Sep-23 13-Sep-23 3 160 13-Sep-23, ITEM-3.3.4.4.1.2 ELECTRICAL
MH.ENG.SD.VA.1030 Prepare & Submit - Electrical 09-Sep-23 13-Sep-23 3 160 Prepare & Submit - Electrical
ITEM-3.3.4.4.1.4 PLUMBING 09-Sep-23 18-Sep-23 7 337 18-Sep-23, ITEM-3.3.4.4.1.4 PLUMBING
MH.ENG.SD.VA.1090 Prepare & Submit - Plumbing 09-Sep-23 18-Sep-23 7 337 Prepare & Submit - Plumbing
ITEM-3.3.4.4.1.3 HVAC 18-Sep-23 26-Sep-23 7 337 26-Sep-23, ITEM-3.3.4.4.1.3 HVAC
MH.ENG.SD.VA.1130 Prepare & Submit - HVAC 18-Sep-23 26-Sep-23 7 337 Prepare & Submit - HVAC
ITEM-3.3.4.4.2 REVIEW & APPROVAL 16-Sep-23 30-Sep-23 11 337 30-Sep-23, ITEM-3.3.4.4.2 REVIEW & APPROVAL
ITEM-3.3.4.4.2.1 CIVIL 19-Sep-23 22-Sep-23 3 335 22-Sep-23, ITEM-3.3.4.4.2.1 CIVIL
MH.ENG.SD.VA.1120 Review & Approve - Civil 19-Sep-23 22-Sep-23 3 335 Review & Approve - Civil
ITEM-3.3.4.4.2.2 ELECTRICAL 16-Sep-23 20-Sep-23 3 160 20-Sep-23, ITEM-3.3.4.4.2.2 ELECTRICAL
MH.ENG.SD.VA.1060 Review & Approve - Electrical 16-Sep-23 20-Sep-23 3 160 Review & Approve - Electrical
ITEM-3.3.4.4.2.4 PLUMBING 21-Sep-23 25-Sep-23 3 341 25-Sep-23, ITEM-3.3.4.4.2.4 PLUMBING
MH.ENG.SD.VA.1110 Review & Approve - Plumbing 21-Sep-23 25-Sep-23 3 341 Review & Approve - Plumbing
ITEM-3.3.4.4.2.3 HVAC 26-Sep-23 30-Sep-23 3 337 30-Sep-23, ITEM-3.3.4.4.2.3 HVAC
MH.ENG.SD.VA.1140 Review & Approve - HVAC 26-Sep-23 30-Sep-23 3 337 Review & Approve - HVAC
ITEM-3.3.1 MATERIALS 08-Aug-23 31-Oct-23 75 334 31-Oct-23, ITEM-3.3.1 MATERIALS
ITEM-3.3.1.3 CIVIL 22-Sep-23 03-Oct-23 8 335 03-Oct-23, ITEM-3.3.1.3 CIVIL
ITEM-3.3.1.3.1 GENERAL 22-Sep-23 03-Oct-23 8 335 03-Oct-23, ITEM-3.3.1.3.1 GENERAL
ITEM-3.3.1.3.1.1 PREPARATION & SUBMISSION 22-Sep-23 25-Sep-23 2 335 25-Sep-23, ITEM-3.3.1.3.1.1 PREPARATION & SUBMISSION
MH.ENG.MA.1510 Prepare & Submit MAT - Steel reinforcement & formwork 22-Sep-23 25-Sep-23 2 335 Prepare & Submit MAT - Steel reinforcement & formwork
ITEM-3.3.1.3.1.2 REVIEW & APPROVAL 30-Sep-23 03-Oct-23 2 335 03-Oct-23, ITEM-3.3.1.3.1.2 REVIEW & APPROVAL
MH.ENG.MA.1520 Review & Approve MAT - Steel reinforcement & formwork 30-Sep-23 03-Oct-23 2 335 Review & Approve MAT - Steel reinforcement & formwork
ITEM-3.3.1.8 ARCHITECTURAL 08-Aug-23 21-Sep-23 39 344 21-Sep-23, ITEM-3.3.1.8 ARCHITECTURAL
ITEM-3.3.1.8.4 PLUMBING 08-Aug-23 14-Aug-23 6 377 14-Aug-23, ITEM-3.3.1.8.4 PLUMBING
ITEM-3.3.1.8.4.1 PREPARATION & SUBMISSION 08-Aug-23 11-Aug-23 4 377 11-Aug-23, ITEM-3.3.1.8.4.1 PREPARATION & SUBMISSION
MH.ENG.MA.1530 Prepare & Submit MAT - Pipes & Fittings 08-Aug-23 08-Aug-23 1 377 Prepare & Submit MAT - Pipes & Fittings
MH.ENG.MA.1540 Prepare & Submit MAT - Drains & Clean Out 11-Aug-23 11-Aug-23 1 377 Prepare & Submit MAT - Drains & Clean Out
ITEM-3.3.1.8.4.4 REVIEW & APPROVAL 09-Aug-23 14-Aug-23 5 377 14-Aug-23, ITEM-3.3.1.8.4.4 REVIEW & APPROVAL
MH.ENG.MA.1550 Review & Approve MAT - Pipes & Fittings 09-Aug-23 10-Aug-23 2 377 Review & Approve MAT - Pipes & Fittings
MH.ENG.MA.1560 Review & Approve MAT - Drains & Clean Out 12-Aug-23 14-Aug-23 2 377 Review & Approve MAT - Drains & Clean Out

Actual Level of Effort Remaining Work Milestone Page 1 of 5 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
VILLA - A 114
Activity ID Activity Name Start Finish Original Total Float J A S O N D J F M A M J J A S O N D J
Duration 2
ITEM-3.3.1.8.1 GENERAL 13-Sep-23 21-Sep-23 7 262 21-Sep-23, ITEM-3.3.1.8.1 GENERAL
ITEM-3.3.1.8.1.1 PREPARATION & SUBMISSION 13-Sep-23 14-Sep-23 1 262 14-Sep-23, ITEM-3.3.1.8.1.1 PREPARATION & SUBMISSION
MH.ENG.MA.1030 Prepare & Submit MAT - Waterproofing 13-Sep-23 14-Sep-23 1 262 Prepare & Submit MAT - Waterproofing
ITEM-3.3.1.8.1.2 REVIEW & APPROVAL 19-Sep-23 21-Sep-23 2 262 21-Sep-23, ITEM-3.3.1.8.1.2 REVIEW & APPROVAL
MH.ENG.MA.1280 Review & Approve MAT - Waterproofing 19-Sep-23 21-Sep-23 2 262 Review & Approve MAT - Waterproofing
ITEM-3.3.1.2 MEP 07-Oct-23 31-Oct-23 20 334 31-Oct-23, ITEM-3.3.1.2 MEP
ITEM-3.3.1.2.1 ELECTRICAL 07-Oct-23 21-Oct-23 12 319 21-Oct-23, ITEM-3.3.1.2.1 ELECTRICAL
ITEM-3.3.1.2.1.1 PREPARATION & SUBMISSION 07-Oct-23 12-Oct-23 4 319 12-Oct-23, ITEM-3.3.1.2.1.1 PREPARATION & SUBMISSION
MH.ENG.MA.1080 Prepare & Submit MAT - Conduits 07-Oct-23 09-Oct-23 1 291 Prepare & Submit MAT - Conduits
MH.ENG.MA.1100 Prepare & Submit MAT - Wiring 07-Oct-23 12-Oct-23 4 319 Prepare & Submit MAT - Wiring
ITEM-3.3.1.2.1.2 REVIEW & APPROVAL 13-Oct-23 21-Oct-23 7 319 21-Oct-23, ITEM-3.3.1.2.1.2 REVIEW & APPROVAL
MH.ENG.MA.1310 Review & Approve MAT - Conduits 13-Oct-23 16-Oct-23 2 291 Review & Approve MAT - Conduits
MH.ENG.MA.1500 Review & Approve MAT - Wiring 17-Oct-23 21-Oct-23 4 319 Review & Approve MAT - Wiring
ITEM-3.3.1.2.4 PLUMBING 13-Oct-23 27-Oct-23 12 314 27-Oct-23, ITEM-3.3.1.2.4 PLUMBING
ITEM-3.3.1.2.4.1 PREPARATION & SUBMISSION 13-Oct-23 21-Oct-23 7 314 21-Oct-23, ITEM-3.3.1.2.4.1 PREPARATION & SUBMISSION
MH.ENG.MA.1110 Prepare & Submit MAT - Pipes & Fittings 13-Oct-23 14-Oct-23 1 291 Prepare & Submit MAT - Pipes & Fittings
MH.ENG.MA.1120 Prepare & Submit MAT - Drains & Clean Out 20-Oct-23 21-Oct-23 1 314 Prepare & Submit MAT - Drains & Clean Out
ITEM-3.3.1.2.4.4 REVIEW & APPROVAL 18-Oct-23 27-Oct-23 8 314 27-Oct-23, ITEM-3.3.1.2.4.4 REVIEW & APPROVAL
MH.ENG.MA.1320 Review & Approve MAT - Pipes & Fittings 18-Oct-23 20-Oct-23 2 314 Review & Approve MAT - Pipes & Fittings
MH.ENG.MA.1330 Review & Approve MAT - Drains & Clean Out 25-Oct-23 27-Oct-23 2 314 Review & Approve MAT - Drains & Clean Out
ITEM-3.3.1.2.2 HVAC 14-Oct-23 31-Oct-23 14 334 31-Oct-23, ITEM-3.3.1.2.2 HVAC
ITEM-3.3.1.2.2.1 PREPARATION & SUBMISSION 14-Oct-23 20-Oct-23 5 338 20-Oct-23, ITEM-3.3.1.2.2.1 PREPARATION & SUBMISSION
MH.ENG.MA.1570 Prepare & Submit MAT - VRF AC Unites 14-Oct-23 16-Oct-23 1 318 Prepare & Submit MAT - VRF AC Unites
MH.ENG.MA.1610 Prepare & Submit MAT- FCU 14-Oct-23 20-Oct-23 5 313 Prepare & Submit MAT- FCU
MH.ENG.MA.1580 Prepare & Submit MAT - Grills & Diffusers 16-Oct-23 17-Oct-23 1 318 Prepare & Submit MAT - Grills & Diffusers
ITEM-3.3.1.2.2.4 REVIEW & APPROVAL 20-Oct-23 31-Oct-23 9 334 31-Oct-23, ITEM-3.3.1.2.2.4 REVIEW & APPROVAL
MH.ENG.MA.1630 Prepare & Submit MAT - VRF AC Unites 20-Oct-23 21-Oct-23 1 318 Prepare & Submit MAT - VRF AC Unites
MH.ENG.MA.1640 Prepare & Submit MAT - Grills & Diffusers 21-Oct-23 23-Oct-23 1 318 Prepare & Submit MAT - Grills & Diffusers
MH.ENG.MA.1620 Prepare & Submit MAT- FCU 25-Oct-23 31-Oct-23 5 313 Prepare & Submit MAT- FCU

ITEM-3.4 CONSTRUCTION WORKS 08-Aug-23 15-Oct-24 388 21 15-Oct-24, ITEM-3.4 CONSTR

ITEM-3.4.3 MAIN BUILDING & SWIMMING POOL 08-Aug-23 06-Aug-24 326 83 06-Aug-24, ITEM-3.4.3 MAIN BUILDING & S
ITEM-3.4.3.8 CONCRETE WORKS 08-Aug-23 09-Apr-24 219 190 09-Apr-24, ITEM-3.4.3.8 CONCRETE WORKS
ITEM-3.4.3.8.4 BASMENT FLOOR 08-Aug-23 14-Dec-23 115 294 14-Dec-23, ITEM-3.4.3.8.4 BASMENT FLOOR
ITEM-3.4.3.8.4.1 FOUNDATION 08-Aug-23 23-Oct-23 68 341 23-Oct-23, ITEM-3.4.3.8.4.1 FOUNDATION
A1110 Filling and Compaction 08-Aug-23 12-Aug-23 5 404 Filling and Compaction
A1030 Plan Concrete formwork and casting ( PCC) 09-Sep-23 15-Sep-23 5 0 Plan Concrete formwork and casting ( PCC)
A1060 Waterproofin g for Raft 19-Sep-23 30-Sep-23 10 0 Waterproofin g for Raft
A1080 Screed for waterproofing 30-Sep-23 05-Oct-23 5 0 Screed for waterproofing
A1010 Steel reinforcement & Formwork for raft foundation 06-Oct-23 23-Oct-23 15 0 Steel reinforcement & Formwork for raft foundation
A1020 cast raft foundation 21-Oct-23 23-Oct-23 1 0 cast raft foundation
ITEM-3.4.3.8.4.2 BASMENT WALLS 23-Oct-23 14-Dec-23 47 166 14-Dec-23, ITEM-3.4.3.8.4.2 BASMENT WALLS
A1040 Steel reinforcement & Formwork Basment Wall s 23-Oct-23 04-Nov-23 12 0 Steel reinforcement & Formwork Basment Wall s
A1050 cast basment wall 04-Nov-23 04-Nov-23 0 166 cast basment wall
A1070 Waterproofin g for walls 28-Nov-23 14-Dec-23 15 166 Waterproofin g for walls
ITEM-3.4.3.8.4.5 COULMNS 23-Oct-23 09-Nov-23 16 0 09-Nov-23, ITEM-3.4.3.8.4.5 COULMNS
A1090 Steel reinforcement & Formwork & piping for Basment coulmn 23-Oct-23 08-Nov-23 15 0 Steel reinforcement & Formwork & piping for Basment coulmn
A1100 Coulmn Casting for Basment 08-Nov-23 09-Nov-23 1 0 Coulmn Casting for Basment
ITEM-3.4.3.8.6 GROUND FLOOR 15-Nov-23 03-Jan-24 44 276 03-Jan-24, ITEM-3.4.3.8.6 GROUND FLOOR
ITEM-3.4.3.8.6.3 SLAB 15-Nov-23 20-Dec-23 31 289 20-Dec-23, ITEM-3.4.3.8.6.3 SLAB
A2800 Slab Steel reinforcement & Formwork & piping for ground floor 15-Nov-23 07-Dec-23 20 0 Slab Steel reinforcement & Formwork & piping for ground floor

Actual Level of Effort Remaining Work Milestone Page 2 of 5 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
VILLA - A 114
Activity ID Activity Name Start Finish Original Total Float J A S O N D J F M A M J J A S O N D J
Duration 2
A2810 cast ground floor slab 07-Dec-23 12-Dec-23 4 0 cast ground floor slab
A2840 slab on grade works 08-Dec-23 20-Dec-23 10 289 slab on grade works
ITEM-3.4.3.8.6.5 COULMNS 16-Dec-23 03-Jan-24 16 0 03-Jan-24, ITEM-3.4.3.8.6.5 COULMNS
A1610 Coulmn Steel reinforcement & Formwork & piping for ground floor 16-Dec-23 02-Jan-24 15 0 Coulmn Steel reinforcement & Formwork & piping for ground floor
A1620 Coulmn Casting for ground floor 02-Jan-24 03-Jan-24 1 0 Coulmn Casting for ground floor
ITEM-3.4.3.8.2 FIRST FLOOR 03-Jan-24 14-Feb-24 37 0 14-Feb-24, ITEM-3.4.3.8.2 FIRST FLOOR
ITEM-3.4.3.8.2.3 SLAB 03-Jan-24 29-Jan-24 23 0 29-Jan-24, ITEM-3.4.3.8.2.3 SLAB
A2820 Slab Steel reinforcement & Formwork & piping for first floor 03-Jan-24 27-Jan-24 22 0 Slab Steel reinforcement & Formwork & piping for first floor
A2830 cast first floor slab 27-Jan-24 29-Jan-24 1 0 cast first floor slab
ITEM-3.4.3.8.2.5 COULMNS 30-Jan-24 14-Feb-24 13 0 14-Feb-24, ITEM-3.4.3.8.2.5 COULMNS
A1660 Coulmn Steel reinforcement & Formwork & piping for first floor 30-Jan-24 13-Feb-24 12 0 Coulmn Steel reinforcement & Formwork & piping for first floor
A1670 Casting Coulmn for first floor 13-Feb-24 14-Feb-24 1 0 Casting Coulmn for first floor
ITEM-3.4.3.8.1 ROOF FLOOR 14-Feb-24 23-Mar-24 35 0 23-Mar-24, ITEM-3.4.3.8.1 ROOF FLOOR
ITEM-3.4.3.8.1.5 SLAB 14-Feb-24 08-Mar-24 21 0 08-Mar-24, ITEM-3.4.3.8.1.5 SLAB
A2900 Slab Steel reinforcement & Formwork & piping for roof floor 14-Feb-24 07-Mar-24 20 0 Slab Steel reinforcement & Formwork & piping for roof floor
A2910 casting slab for roof floor 07-Mar-24 08-Mar-24 1 0 casting slab for roof floor
ITEM-3.4.3.8.1.1 COULMNS 14-Mar-24 23-Mar-24 9 0 23-Mar-24, ITEM-3.4.3.8.1.1 COULMNS
A2880 Coulmn Steel reinforcement & Formwork & piping for roof floor 14-Mar-24 22-Mar-24 8 0 Coulmn Steel reinforcement & Formwork & piping for roof floor
A2890 Coulmn Casting for roof floor 23-Mar-24 23-Mar-24 1 0 Coulmn Casting for roof floor
ITEM-3.4.3.8.5 TOP ROOF 28-Mar-24 09-Apr-24 10 0 09-Apr-24, ITEM-3.4.3.8.5 TOP ROOF
ITEM-3.4.3.8.5.1 SLAB 28-Mar-24 09-Apr-24 10 0 09-Apr-24, ITEM-3.4.3.8.5.1 SLAB
A3070 Steel reinforcement & Formwork & piping for top roof floor slab 28-Mar-24 08-Apr-24 9 0 Steel reinforcement & Formwork & piping for top roof floor slab
A3080 Slab casting for top roof 08-Apr-24 09-Apr-24 1 0 Slab casting for top roof
ITEM-3.4.3.3 MASONARY WORKS 28-Dec-23 03-May-24 114 0 03-May-24, ITEM-3.4.3.3 MASONARY WORKS
ITEM-3.4.3.3.4 BASMENT FLOOR 28-Dec-23 12-Jan-24 14 69 12-Jan-24, ITEM-3.4.3.3.4 BASMENT FLOOR
A2920 Masonry and Lintels for basment floor 28-Dec-23 12-Jan-24 14 69 Masonry and Lintels for basment floor
ITEM-3.4.3.3.1 GROUND FLOOR 14-Feb-24 29-Feb-24 14 34 29-Feb-24, ITEM-3.4.3.3.1 GROUND FLOOR
A1710 Masonry and Lintels for ground floor 14-Feb-24 29-Feb-24 14 34 Masonry and Lintels for ground floor
ITEM-3.4.3.3.2 FIRST FLOOR 23-Mar-24 09-Apr-24 14 11 09-Apr-24, ITEM-3.4.3.3.2 FIRST FLOOR
A1730 Masonry and Lintels for first floor 23-Mar-24 09-Apr-24 14 11 Masonry and Lintels for first floor
ITEM-3.4.3.3.3 ROOF FLOOR 24-Apr-24 03-May-24 8 0 03-May-24, ITEM-3.4.3.3.3 ROOF FLOOR
A1750 Masonry and Lintels for roof floor 24-Apr-24 03-May-24 8 0 Masonry and Lintels for roof floor
ITEM-3.4.3.5 MEP WORKS 08-Aug-23 06-Aug-24 326 83 06-Aug-24, ITEM-3.4.3.5 MEP WORKS
ITEM-3.4.3.5.1 ELECTRICAL & ETISALATE AND FIRE ALARM WORKS 12-Jan-24 03-Jul-24 154 93 03-Jul-24, ITEM-3.4.3.5.1 ELECTRICAL & ETISALAT
ITEM-3.4.3.5.1.2 LOW CURRENT WORK 12-Jan-24 21-May-24 116 0 21-May-24, ITEM-3.4.3.5.1.2 LOW CURRENT WORK
ITEM-3.4.3.5.1.2.4 BASMENT FLOOR 12-Jan-24 27-Jan-24 14 69 27-Jan-24, ITEM-3.4.3.5.1.2.4 BASMENT FLOOR
A3170 Pipe conduit in basment floor 12-Jan-24 27-Jan-24 14 69 Pipe conduit in basment floor
ITEM-3.4.3.5.1.2.1 GROUND FLOOR 29-Feb-24 18-Mar-24 16 34 18-Mar-24, ITEM-3.4.3.5.1.2.1 GROUND FLOOR
A1890 Pipe conduit in ground floor 29-Feb-24 18-Mar-24 16 34 Pipe conduit in ground floor
ITEM-3.4.3.5.1.2.3 FIRST FLOOR 09-Apr-24 26-Apr-24 16 11 26-Apr-24, ITEM-3.4.3.5.1.2.3 FIRST FLOOR
A1840 Pipe conduit in first floor 09-Apr-24 26-Apr-24 16 11 Pipe conduit in first floor
ITEM-3.4.3.5.1.2.2 ROOF FLOOR 03-May-24 21-May-24 16 0 21-May-24, ITEM-3.4.3.5.1.2.2 ROOF FLOOR
A1920 Pipe conduit in roof floor 03-May-24 21-May-24 16 0 Pipe conduit in roof floor
ITEM-3.4.3.5.1.1 POWER WORKS 30-Jan-24 03-Jul-24 138 93 03-Jul-24, ITEM-3.4.3.5.1.1 POWER WORKS
ITEM-3.4.3.5.1.1.4 BASMENT FLOOR 30-Jan-24 07-Jun-24 115 93 07-Jun-24, ITEM-3.4.3.5.1.1.4 BASMENT FLOOR
A3210 Wiring in basment floor 30-Jan-24 10-Feb-24 10 69 Wiring in basment floor
A3310 Distribution board in basment floor 28-May-24 07-Jun-24 9 93 Distribution board in basment floor
ITEM-3.4.3.5.1.1.1 GROUND FLOOR 21-Mar-24 17-Jun-24 79 93 17-Jun-24, ITEM-3.4.3.5.1.1.1 GROUND FLOOR
A3190 Wiring in ground floor 21-Mar-24 01-Apr-24 10 34 Wiring in ground floor
A3320 Distribution board in ground floor 07-Jun-24 17-Jun-24 9 93 Distribution board in ground floor
ITEM-3.4.3.5.1.1.3 FIRST FLOOR 26-Apr-24 25-Jun-24 53 93 25-Jun-24, ITEM-3.4.3.5.1.1.3 FIRST FLOOR

Actual Level of Effort Remaining Work Milestone Page 3 of 5 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
VILLA - A 114
Activity ID Activity Name Start Finish Original Total Float J A S O N D J F M A M J J A S O N D J
Duration 2
A3180 Wiring in first floor 26-Apr-24 09-May-24 11 11 Wiring in first floor
A3330 Distribution board in ground floor 17-Jun-24 25-Jun-24 7 93 Distribution board in ground floor
ITEM-3.4.3.5.1.1.2 ROOF FLOOR 21-May-24 03-Jul-24 38 93 03-Jul-24, ITEM-3.4.3.5.1.1.2 ROOF FLOOR
A3200 Wiring in roof floor 21-May-24 04-Jun-24 12 0 Wiring in roof floor
A3340 Distribution board in ground floor 25-Jun-24 03-Jul-24 7 93 Distribution board in ground floor
ITEM-3.4.3.5.1.3 EXTERIOR WORKS 04-Jun-24 01-Jul-24 24 95 01-Jul-24, ITEM-3.4.3.5.1.3 EXTERIOR WORKS
A2090 Exterior wairing 04-Jun-24 19-Jun-24 14 93 Exterior wairing
A2060 Electrical & Etisalate Manhole 07-Jun-24 01-Jul-24 21 95 Electrical & Etisalate Manhole
ITEM-3.4.3.5.2 PLUMPING & HVAC 08-Aug-23 06-Aug-24 326 83 06-Aug-24, ITEM-3.4.3.5.2 PLUMPING & HV
ITEM-3.4.3.5.2.2 WATER PIPE & HVAC 08-Aug-23 06-Aug-24 326 83 06-Aug-24, ITEM-3.4.3.5.2.2 WATER PIPE &
ITEM-3.4.3.5.2.2.5 BASMENT FLOOR 29-Feb-24 19-Jun-24 99 126 19-Jun-24, ITEM-3.4.3.5.2.2.5 BASMENT FLOOR
A3390 Water dranig e & supply first fix in basment floor 29-Feb-24 12-Mar-24 10 215 Water dranig e & supply first fix in basment floor
A3220 Water dranig e & supply second fix in basment floor 25-May-24 10-Jun-24 14 126 Water dranig e & supply second fix in basment floor
A3350 HVAC pipe works in basment floor 11-Jun-24 19-Jun-24 8 126 HVAC pipe works in basment floor
ITEM-3.4.3.5.2.2.1 GROUND FLOOR 09-Apr-24 15-Jul-24 87 103 15-Jul-24, ITEM-3.4.3.5.2.2.1 GROUND FLOOR
A3400 Water dranig e & supply first fix in ground floor 09-Apr-24 19-Apr-24 10 180 Water dranig e & supply first fix in ground floor
A3410 Water dranig e & supply second fix in ground floor 17-Jun-24 03-Jul-24 14 103 Water dranig e & supply second fix in ground floor
A3360 HVAC pipe works in ground floor 06-Jul-24 15-Jul-24 8 103 HVAC pipe works in ground floor
ITEM-3.4.3.5.2.2.3 FIRST FLOOR 03-May-24 06-Aug-24 85 83 06-Aug-24, ITEM-3.4.3.5.2.2.3 FIRST FLOOR
A3420 Water dranig e & supply first fix in first floor 03-May-24 14-May-24 10 148 Water dranig e & supply first fix in first floor
A3430 Water dranig e & supply second fix in ground floor 10-Jul-24 25-Jul-24 14 83 Water dranig e & supply second fix in ground floo
A3440 HVAC pipe works in ground floor 29-Jul-24 06-Aug-24 8 83 HVAC pipe works in ground floor
ITEM-3.4.3.5.2.2.2 ROOF FLOOR 08-Aug-23 25-May-24 261 148 25-May-24, ITEM-3.4.3.5.2.2.2 ROOF FLOOR
A3460 Water dranig e & supply second fix in ground floor 08-Aug-23 23-Aug-23 14 384 Water dranig e & supply second fix in ground floor
A3470 HVAC pipe works in ground floor 26-Aug-23 04-Sep-23 8 384 HVAC pipe works in ground floor
A3450 Water dranig e & supply first fix in ground floor 15-May-24 25-May-24 10 148 Water dranig e & supply first fix in ground floor
ITEM-3.4.3.5.2.2.4 TOP ROOF FLOOR 28-Jun-24 13-Jul-24 14 83 13-Jul-24, ITEM-3.4.3.5.2.2.4 TOP ROOF FLOOR
A2200 Water supply in top roof flo or 28-Jun-24 13-Jul-24 14 83 Water supply in top roof flo or
ITEM-3.4.3.7 THERMAL AND MOISTURE PROTECTION 03-May-24 15-Jul-24 65 103 15-Jul-24, ITEM-3.4.3.7 THERMAL AND MOISTU
ITEM-3.4.3.7.1 WET AREA & WASHROOM 03-May-24 15-Jul-24 65 103 15-Jul-24, ITEM-3.4.3.7.1 WET AREA & WASHRO
A1300 Waterproofin g & testin g for wet area in basment floor 03-May-24 25-May-24 20 83 Waterproofin g & testin g for wet area in basment floor
A2270 Waterproofin g & testin g for washroom and wet area in ground floor 25-May-24 17-Jun-24 20 83 Waterproofing & testing for washroom and wet area in gro
A2280 Waterproofin g & testin g for washroom and wet area & and balacony in first floor 17-Jun-24 09-Jul-24 20 83 Waterproofing & testin g for washroom and wet area
A2290 Waterproofin g for roof flo or 10-Jul-24 15-Jul-24 5 103 Waterproofin g for roof flo or
ITEM-3.4.3.7.3 TOP ROOF 17-Jun-24 28-Jun-24 10 0 28-Jun-24, ITEM-3.4.3.7.3 TOP ROOF
A2340 Top roof Waterproofing 17-Jun-24 28-Jun-24 10 0 Top roof Waterproofing
ITEM-3.4.9 BOUNDARY WALL 07-Dec-23 13-Apr-24 114 165 13-Apr-24, ITEM-3.4.9 BOUNDARY WALL
ITEM-3.4.9.1 CONCRETE WORKS 07-Dec-23 12-Mar-24 85 165 12-Mar-24, ITEM-3.4.9.1 CONCRETE WORKS
ITEM-3.4.9.1.3 FOUNDATION 07-Dec-23 05-Jan-24 26 165 05-Jan-24, ITEM-3.4.9.1.3 FOUNDATION
A2970 Steel reinforcement & Formwork for fence foundation 07-Dec-23 04-Jan-24 25 165 Steel reinforcement & Formwork for fence foundation
A2980 cast fence foundation 04-Jan-24 05-Jan-24 1 165 cast fence foundation
ITEM-3.4.9.1.1 RETANING WALL 17-Jan-24 13-Feb-24 24 165 13-Feb-24, ITEM-3.4.9.1.1 RETANING WALL
A2990 Steel reinforcement & Formwork for retaning wall 17-Jan-24 08-Feb-24 20 165 Steel reinforcement & Formwork for retaning wall
A3000 cast retaning wall 08-Feb-24 13-Feb-24 4 165 cast retaning wall
ITEM-3.4.9.1.2 CAPATECT ETICS SYSTEM A MW 16-Feb-24 12-Mar-24 22 165 12-Mar-24, ITEM-3.4.9.1.2 CAPATECT ETICS SYSTEM A MW
A3010 Steel reinforcement & Formwork for etics 16-Feb-24 11-Mar-24 21 165 Steel reinforcement & Formwork for etics
A3020 cast fence etics 11-Mar-24 12-Mar-24 1 165 cast fence etics
ITEM-3.4.9.3 MEP WORKS 12-Mar-24 13-Apr-24 29 165 13-Apr-24, ITEM-3.4.9.3 MEP WORKS
A3050 Coulmn pipe conduit in boundary wall 12-Mar-24 30-Mar-24 17 165 Coulmn pipe conduit in boundary wall
A3060 wiring in in boundary wall 30-Mar-24 13-Apr-24 12 165 wiring in in boundary wall

Actual Level of Effort Remaining Work Milestone Page 4 of 5 Mouhajer Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
VILLA - A 114
Activity ID Activity Name Start Finish Original Total Float J A S O N D J F M A M J J A S O N D J
Duration 2
ITEM-3.4.1 SWIMMING POOL & Water Feature 09-Apr-24 18-May-24 36 154 18-May-24, ITEM-3.4.1 SWIMMING POOL & Water Feature
A3240 Water Feature concrete 09-Apr-24 24-Apr-24 14 129 Water Feature concrete
A3250 MEP Works 26-Apr-24 10-May-24 12 129 MEP Works
A3260 Thermal Protection 10-May-24 18-May-24 8 154 Thermal Protection
ITEM-3.4.2 EXTERNAL WORKS 10-May-24 15-Oct-24 141 21 15-Oct-24, ITEM-3.4.2 EXTER
A2520 Earthling System 10-May-24 23-May-24 12 129 Earthling System
A2560 Metal Works 28-Jun-24 29-Jul-24 27 0 Metal Works
A2510 External Stone cladding 29-Jul-24 31-Aug-24 30 0 External Stone cladding
A2570 Aluminum glazing 31-Aug-24 28-Sep-24 25 36 Aluminum glazing
A2540 Landscape Works 11-Sep-24 15-Oct-24 30 0 Landscape Works
ITEM-3.2 CLOSING PROJECT 15-Oct-24 07-Nov-24 21 0 07-Nov-24, ITEM-3.2 CLO

ITEM-3.2.2 HANDOVER 15-Oct-24 07-Nov-24 21 0 07-Nov-24, ITEM-3.2.2 H


A2730 Test and commissioning 15-Oct-24 30-Oct-24 14 0 Test and commissioning
A2940 Handover 31-Oct-24 07-Nov-24 7 0 Handover