Activity ID Activity Name Start Finish Original Duration Total Float Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024

Start Finish Original Duration Total Float Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
NEWPROJ MOCKUP ROOMS 11-Jul-23 15-Sep-23 60 0 15-Sep-23, NEWPROJ MOCKUP ROOMS

NEWPROJ.2 TIME FOR COMPLETION 11-Jul-23 15-Sep-23 60 0 15-Sep-23, NEWPROJ.2 TIME FOR COMPLETION
A1000 Commencement Date 11-Jul-23 0 27 Commencement Date, 11-Jul-23
A1010 Project Completion 15-Sep-23 0 0 Project Completion,
NEWPROJ.4 PRE- CONSTRUCTION 11-Jul-23 11-Jul-23 1 27 11-Jul-23, NEWPROJ.4 PRE- CONSTRUCTION
A1350 Site Visit 11-Jul-23 11-Jul-23 1 27 Site Visit
A1360 Receipt of As-Built Drawings 11-Jul-23 11-Jul-23 1 27 Receipt of As-Built Drawings
NEWPROJ.6 DETAILED DRAWINGS DEVELOPMENT 14-Jul-23 25-Jul-23 10 27 25-Jul-23, NEWPROJ.6 DETAILED DRAWINGS DEVELOPMENT

NEWPROJ.6.1 INTERIOR DESIGN 14-Jul-23 25-Jul-23 10 27 25-Jul-23, NEWPROJ.6.1 INTERIOR DESIGN


A1370 Final ID Drawings 14-Jul-23 25-Jul-23 10 27 Final ID Drawings
NEWPROJ.7 PERMITTING & APPROVALS 14-Jul-23 19-Jul-23 5 52 19-Jul-23, NEWPROJ.7 PERMITTING & APPROVALS

NEWPROJ.7.1 DESIGN DRAWING SUBMISSION TO CLIENT 14-Jul-23 19-Jul-23 5 52 19-Jul-23, NEWPROJ.7.1 DESIGN DRAWING SUBMISSION TO CLIENT
A1380 Submission of Detailed Design / Coordinated Drawings to WASL/HYATT 14-Jul-23 14-Jul-23 1 33 Submission of Detailed Design / Coordinated Drawings to WASL/HYATT
A1390 Comments / Approval from WASL/ HYATT 15-Jul-23 18-Jul-23 3 52 Comments / Approval from WASL/ HYATT
A1400 Resubmission of Final Drawings to WASL/ HYATT 18-Jul-23 19-Jul-23 1 52 Resubmission of Final Drawings to WASL/ HYATT
NEWPROJ.1 CONTRACTOR SUBMITTALS 13-Jul-23 16-Aug-23 31 27 16-Aug-23, NEWPROJ.1 CONTRACTOR SUBMITTALS

NEWPROJ.1.2 SHOP DRAWINGS 13-Jul-23 16-Aug-23 31 27 16-Aug-23, NEWPROJ.1.2 SHOP DRAWINGS


NEWPROJ.1.2.3 ARCHITECTURAL SHOP DRAWINGS 13-Jul-23 09-Aug-23 25 33 09-Aug-23, NEWPROJ.1.2.3 ARCHITECTURAL SHOP DRAWINGS
A1020 Drawing Submittals 13-Jul-23 29-Jul-23 15 33 Drawing Submittals
A1030 Submittal Review and Approval by WASL/ HYATT 29-Jul-23 02-Aug-23 3 33 Submittal Review and Approval by WASL/ HYATT
A1040 Revisions / Resubmissions 29-Jul-23 05-Aug-23 7 33 Revisions / Resubmissions
A1050 Revised Submittal Review and Approval by WASL/ HYATT 07-Aug-23 09-Aug-23 3 33 Revised Submittal Review and Approval by WASL/ HYATT
NEWPROJ.1.2.4 MEP SHOP DRAWINGS 13-Jul-23 18-Jul-23 5 53 18-Jul-23, NEWPROJ.1.2.4 MEP SHOP DRAWINGS
A1060 Drawing Submittals 13-Jul-23 18-Jul-23 5 35 Drawing Submittals
A1070 Revisions / Resubmissions 13-Jul-23 15-Jul-23 3 55 Revisions / Resubmissions
NEWPROJ.1.2.1 MATERIALS SAMPLE SUBMITTAL 13-Jul-23 07-Aug-23 23 35 07-Aug-23, NEWPROJ.1.2.1 MATERIALS SAMPLE SUBMITTAL
A1080 Material Submittals 13-Jul-23 28-Jul-23 14 35 Material Submittals
A1090 Submittal Review and Approval by WASL/ HYATT 28-Jul-23 01-Aug-23 3 35 Submittal Review and Approval by WASL/ HYATT
A1100 Revisions / Resubmissions 01-Aug-23 04-Aug-23 3 35 Revisions / Resubmissions
A1110 Revised Submittal Review and Approval by WASL/ HYATT 04-Aug-23 07-Aug-23 3 35 Revised Submittal Review and Approval by WASL/ HYATT
NEWPROJ.1.2.2 MATERIALS DELIVERY 14-Jul-23 16-Aug-23 30 27 16-Aug-23, NEWPROJ.1.2.2 MATERIALS DELIVERY
A1120 Procurement - General / Non Critical Items 14-Jul-23 31-Jul-23 15 27 Procurement - General / Non Critical Items
A1130 General Construction Items Delivery 14-Jul-23 31-Jul-23 15 27 General Construction Items Delivery
A1140 Procurement - Long Lead Items 14-Jul-23 16-Aug-23 30 27 Procurement - Long Lead Items
NEWPROJ.5 MOCK UP ROOM 11-Jul-23 12-Sep-23 57 3 12-Sep-23, NEWPROJ.5 MOCK UP ROOM

NEWPROJ.5.1 CONSTRUCTION 11-Jul-23 09-Sep-23 55 5 09-Sep-23, NEWPROJ.5.1 CONSTRUCTION


A1160 Mobilization works 11-Jul-23 11-Jul-23 1 59 Mobilization works
A1170 Demolition works 11-Jul-23 11-Jul-23 1 0 Demolition works
A1180 MEP 1st Fix 19-Jul-23 28-Jul-23 8 0 MEP 1st Fix
A1190 Supply and installation of new gypsum ceiling 28-Jul-23 05-Aug-23 8 0 Supply and installation of new gypsum ceiling
A1200 Supply and installation of new outdoor flooring+ Repainting of existing wooden handrail 28-Jul-23 04-Aug-23 6 0 Supply and installation of new outdoor flooring+ Repainting of existing wooden handrail
A1210 Application of joint tapping, stucco and fenomastic paint of ceiling and walls 04-Aug-23 15-Aug-23 10 0 Application of joint tapping, stucco and fenomastic paint of ceiling and walls
A1220 Supply and installation of new Wooden flooring 17-Aug-23 25-Aug-23 7 0 Supply and installation of new Wooden flooring
A1230 Supply and installation of Joinery items, Vanity Counter,etc 19-Aug-23 29-Aug-23 8 0 Supply and installation of Joinery items, Vanity Counter,etc
A1240 MEP Final Fix 24-Aug-23 01-Sep-23 7 5 MEP Final Fix
A1250 Furniture Delivery & installation 01-Sep-23 09-Sep-23 8 5 Furniture Delivery & installation
NEWPROJ.5.2 MOCK UP CORRIDOR 11-Jul-23 12-Sep-23 57 3 12-Sep-23, NEWPROJ.5.2 MOCK UP CORRIDOR

Actual Level of Effort Remaining Work Milestone Page 1 of 2 Mouhajer International Design - Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Start Finish Original Duration Total Float Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
NEWPROJ.5.2.2 CONSTRUCTION 11-Jul-23 11-Sep-23 56 4 11-Sep-23, NEWPROJ.5.2.2 CONSTRUCTION
A1260 Demolition works 11-Jul-23 12-Jul-23 2 46 Demolition works
A1270 Existing wood refinishing 19-Jul-23 26-Jul-23 6 46 Existing wood refinishing
A1280 Joinery Installation 19-Aug-23 24-Aug-23 4 0 Joinery Installation
A1290 Ceiling and wall paint 25-Aug-23 31-Aug-23 5 0 Ceiling and wall paint
A1300 Supply and installation of Axminister carpet with underlay 31-Aug-23 06-Sep-23 6 0 Supply and installation of Axminister carpet with underlay
A1310 Supply and installation of electrical final fix items 04-Sep-23 06-Sep-23 3 0 Supply and installation of electrical final fix items
A1320 Furniture delivery & installation 07-Sep-23 11-Sep-23 4 0 Furniture delivery & installation
NEWPROJ.5.2.1 Landlord Final Integrations, Testing & Commissioning 07-Sep-23 12-Sep-23 5 0 12-Sep-23, NEWPROJ.5.2.1 Landlord Final Integrations, Testing & Commissioning
A1340 3rd Party / Landlord FM Team Testing & Commissioning 07-Sep-23 12-Sep-23 5 0 3rd Party / Landlord FM Team Testing & Commissioning
NEWPROJ.3 HANDOVER ( MOCK UP ROOM ) 12-Sep-23 15-Sep-23 3 0 15-Sep-23, NEWPROJ.3 HANDOVER ( MOCK UP ROOM )
A1330 HANDOVER MOCK UP ROOM 12-Sep-23 15-Sep-23 3 0 HANDOVER MOCK UP ROOM