Design Works for a renovation for a block of terraced houses on Hassop Way, Liverpool

Activity ID Activity Name Original Start Finish 2023


Duration Jul Aug Sep Oct Nov Dec
6 7 8 9 10 11
90 on
Design Works for a renovation for a block of terraced houses 01-Aug-23 28-Oct-23
Hassop Way, Liverpool
A1010 Design Commecement Works 0 01-Aug-23
Pre-Design Phase 38 01-Aug-23 06-Sep-23

Project Initiation 4 01-Aug-23 05-Aug-23


A1000 Establish Project Team 4 01-Aug-23 05-Aug-23
Site Selection and Analysis 6 05-Aug-23 11-Aug-23
A1020 Conduct a site selection process 4 05-Aug-23 09-Aug-23
A1030 Evaluate the site's environmental impact 4 07-Aug-23 11-Aug-23
Research and Data Collection 9 11-Aug-23 20-Aug-23
A1040 Gather data on the specific needs of veterans and Armed Forces with
4 disabilities
11-Aug-23 16-Aug-23
A1050 Study sustainable design principles 4 16-Aug-23 20-Aug-23
Conceptual Design 9 20-Aug-23 29-Aug-23
A1060 Develop initial design concepts 4 20-Aug-23 24-Aug-23
A1070 3D modeling and simulations works 4 24-Aug-23 29-Aug-23
Sustainable Strategies and Technologies 9 29-Aug-23 06-Sep-23
A1080 Explore renewable energy sources 4 29-Aug-23 02-Sep-23
A1090 Explore energy-efficient insulation and building materials 4 02-Sep-23 06-Sep-23
Construction Phase 53 07-Sep-23 28-Oct-23

Detailed Design Development 9 07-Sep-23 15-Sep-23


A1100 Refine the design based on feedback from stakeholders 4 07-Sep-23 11-Sep-23
A1110 Ensure compliance with local building codes and accessibility standards
4 11-Sep-23 15-Sep-23
Accessibility Features 11 15-Sep-23 26-Sep-23
A1120 Incorporate universal design elements like step-free entrances, wide4doorways
15-Sep-23 20-Sep-23
A1130 Install ramps, handrails, and grab bars for mobility support 4 17-Sep-23 22-Sep-23
A1220 Integrate visual and auditory aids for individuals 4 22-Sep-23 26-Sep-23
Sustainable Materials and Construction 11 26-Sep-23 07-Oct-23
A1140 Procurement of eco-friendly building materials with low carbon footprint
4 26-Sep-23 30-Sep-23
A1150 Use energy-efficient windows and doors 4 30-Sep-23 05-Oct-23
A1230 Optimize the building's orientation for natural lighting and ventilation 4 02-Oct-23 07-Oct-23
Waste Management 4 07-Oct-23 11-Oct-23
A1160 Implement a waste management plan to minimize construction waste
4 07-Oct-23 11-Oct-23
Quality Control and Testing 9 11-Oct-23 20-Oct-23
A1180 Perform regular inspections 4 11-Oct-23 15-Oct-23
A1190 Conduct accessibility tests 4 15-Oct-23 20-Oct-23
Landscaping and Outdoor Spaces 9 20-Oct-23 28-Oct-23
A1200 Design accessible outdoor areas with pathways 4 20-Oct-23 24-Oct-23
A1210 Utilize native plants for water conservation and biodiversity 4 24-Oct-23 28-Oct-23

Remaining Level of Effort Critical Remaining Work


Actual Work Milestone
Remaining Work
ACTIVITY DETAILED PROGRAMME Page 1 of 1