Byanstone Alterations Job-Henry Morris

Balmoral Dr Alterations
Standard Activity List
Activities: Entire program
Successor Imposed Current
Type Activity description Durn Act# Lead Lag LDur Date Start Finish Float Activity Remark

B A000 - PRELIMINARIES & GENERAL 1 30 May 23 30 May 23 30 May 23 0


1 A010 - GROUND FLOOR 116 30 May 23 07 Nov 23 0
2 A460 - DEMOLITION 10 30 May 23 12 Jun 23 6
s A100 - BILL NO. 10 -DEMOLITION _breaking down & 10 B000 30 May 23 30 May 23 12 Jun 23 6
removing as be the demolition plan in the drawings. A400 5

2 A710 - ROOFING SUBCONTRACTOR 9 21 Jun 23 03 Jul 23 0


B B000 - start alterations and checking other roofs to be 9 21 Jun 23 03 Jul 23 0
altered / extended

2 A470 - PLUMBING FIRST FIX 5 06 Jun 23 12 Jun 23 16


A400 - BILL NO. 11 -PLUMBING & DRAINAGE_ 5 A560 0 06 Jun 23 12 Jun 23 16
Demobilize existing plumbing, altertions to plumbing
including excavation _ all raw works

2 A550 - ELECTRICAL FIRST FIX 10 06 Jun 23 19 Jun 23 16


A560 - PC SUM _ Removal & overhaul of the electroical 10 A020 5 06 Jun 23 19 Jun 23 16
system to re align with the new build reconfiguration.
Isolate where applicable & ensure safety.

2 A480 - EXCAVATION FOR FOUNDATIONS 4 13 Jun 23 16 Jun 23 16


A020 - BILL NO. 2 - EARTHWORKS - 4 A030 13 Jun 23 16 Jun 23 16
PROVISIONAL_Excavation & prep work for all
foundations for Boundary wall, Retainer walls, New
walls

2 A490 - CONCRETE FOR FOUNDATIONS 3 19 Jun 23 21 Jun 23 16


A030 - BILL No 3 3 A040 19 Jun 23 21 Jun 23 16
-CONC/FORMWORK/REINFORCEMENT_ Placement of
steel in foundations and Casting of Concrete

2 A510 - BRICKWORK 5 06 Jul 23 12 Jul 23 6


A040 - BILL NO. 4 -Masonry _ bricklaying for all ground 5 A390 06 Jul 23 12 Jul 23 6
floor areas inclding the boundary wall and all internal A380
walls _ Include the endtertaiment area structure

2 A500 - PLUMBING SECOND FIX 4 14 Jul 23 19 Jul 23 9


A390 - BILL NO. 11 -PLUMBING & DRAINAGE_ New 4 A080 14 Jul 23 19 Jul 23 9
plumbing construction to specific points as per the
rebuilt structure including installation of built in bath
tubs

2 A520 - CONCRETE FOR SUSPENDED SLABS 8 17 Jul 23 26 Jul 23 4


A380 - BILL No 3 -Conc/Formwork/Reinforcement 8 A700 17 Jul 23 26 Jul 23 4
_prep work including formwork, props, lateral support
and placement of concerete for all sit in areas and
other ground floor sections

2 A690 - ROOFING SUBCONTRACTOR 10 31 Jul 23 11 Aug 23 2


A700 - PC SUM _Alterations to the existing roofs 10 A540 6 31 Jul 23 11 Aug 23 2

2 A530 - ELECTRICAL -SECOND FIX 10 10 Aug 23 23 Aug 23 0


B A540 - PC SUM _Reconfiguration and wiring to specific 10 10 Aug 23 23 Aug 23 0
points as per the rebuilt structures

2 A570 - INTERNAL & EXTERNAL PLASTER RENDER 16 25 Jul 23 15 Aug 23 6


A080 - BILL NO. 8 -Plastering FLOOR SCREEDS_ 16 A660 15 25 Jul 23 15 Aug 23 6
Plastering of walls, screeding of all affected floors and A050 5
on new floors including bathrooms and showers,
concrete roofs, boundary walls

2 A650 - ALUMINIUM WINDOWS AND DOORS 15 21 Aug 23 08 Sep 23 2


A660 - PC SUM _ Installation of aluminium windows 15 A680 21 Aug 23 08 Sep 23 2
and doors

2 A670 - FINAL PLASTERING 5 13 Sep 23 19 Sep 23 0


B A680 - BILL NO. 8 Plastering of reveals after installtion 5 13 Sep 23 19 Sep 23 0
of all external doors and windows. prep and make
ready dot painting

2 A580 - WATER PROOFING 5 01 Aug 23 07 Aug 23 6


A050 - BILL NO. 5 -Waterproofing _ On all new 5 A070 1 01 Aug 23 07 Aug 23 6
concrete roofs, on shower floors and on wall wall tops
and parapits

2 A590 - CEILINGS 9 07 Aug 23 17 Aug 23 3


A070 - BILL NO. 7 -Ceilings _ Attending to all ceiling 9 A600 07 Aug 23 17 Aug 23 3
repairs in the affected areas and a few new ceilings.
Prep ceiings and make ready for painting

2 A610 - FIRST PAINTING - PRIME & PAINT 15 18 Aug 23 07 Sep 23 3


A600 - BILL NO. 12 -Paintwork_ Prep and prime all 15 A090 8 18 Aug 23 07 Sep 23 3
sections that are completed. Paint ceilings prior to
flooring. Paint first coat paint to internal walls. Paint
first coat to external walls including boundary walls.

2 A620 - FLOOR FINISHINGS & TILING 21 30 Aug 23 27 Sep 23 3


A090 - BILL NO. 9 -Tiling Labour_ floors/walls_Start 21 A060 18 30 Aug 23 27 Sep 23 3
tiling with all bathrooms and then to the rest of the A110 9
apartments & external areas

2 A630 - DOORS,CABINETS, ETC 14 25 Sep 23 12 Oct 23 3


A060 - BILL NO. 6 -Carpentry & Joinery DOORS_ 14 A410 25 Sep 23 12 Oct 23 3
Installation of doors, cupboards,and any joinery items

2 A640 - SECOND PAINTING 10 13 Oct 23 26 Oct 23 3


A410 - BILL NO. 12 -Paintwork_ Second and final coats 10 A120 13 Oct 23 26 Oct 23 3
of painitng to walls. Painting of roofs and doors

Printed 04:43:23 26 May 2023 Page 1 of 2


Candy 2.01f14.5 (2 2 0) MJ
Byanstone Alterations Job-Henry Morris
Balmoral Dr Alterations
Standard Activity List
Activities: Entire program
Successor Imposed Current
Type Activity description Durn Act# Lead Lag LDur Date Start Finish Float Activity Remark

2 A720 - SANITARYWARE INSTALLATION 8 18 Oct 23 27 Oct 23 0


B A110 - BILL NO. 11 -Plumbing & Drainage_ Installation 8 18 Oct 23 27 Oct 23 0
of toilets, basins, sinks, shwer enclosures, taps and
fittings

2 A730 - FINAL PAINTING 5 01 Nov 23 07 Nov 23 0


B A120 - BILL NO. 12 -Paintwork_Final coats painting of 5 01 Nov 23 07 Nov 23 0
all internal and extersnl walls, touch ups and checking
to ensure all finishings are attended to

1 A130 - First FLOOR 95 04 Jul 23 13 Nov 23 0


2 A740 - CONCRETE WORKS 11 04 Jul 23 18 Jul 23 7
B A140 - BILL NO. 14 -SUSPENDED SLABS _CONCRETE_ 11 A370 1 04 Jul 23 04 Jul 23 18 Jul 23 7
prep work including formwork, props, lateral support A150 10
and placement of concerete for all sit in areas and
other first floor sections. Stair case to the first floor

2 A750 - BRICKWORK 18 24 Jul 23 16 Aug 23 3


A150 - BILL NO. 15 -Masonry_ bricklaying for all first 18 A840 4 24 Jul 23 16 Aug 23 3
floor areas

2 A870 - ROOFING SUBCONTRACTOR 0 30 May 23 0


- PC SUM_ New Roof as per the drawings , including
roof coverings installation

2 A830 - PLUMBING FIRST FIX 12 28 Jul 23 14 Aug 23 3


A840 - BILL NO. 21 -Plumbing _ all raw plumbing works 12 A860 10 28 Jul 23 14 Aug 23 3
& alterations

2 A850 - ELECTRICAL FIRST FIX 7 11 Aug 23 21 Aug 23 3


A860 - PC SUM _ Removal & overhaul of the electroical 7 A190 11 Aug 23 21 Aug 23 3
system to re align with the new build reconfiguration.
Isolate where applicable & ensure safety.

2 A780 - PLASTER RENDER 12 22 Aug 23 06 Sep 23 3


A190 - BILL NO. 19 -Plastering _BILL NO. 8 -Plastering 12 A160 22 Aug 23 06 Sep 23 3
FLOOR SCREEDS_ Plastering of walls, screeding of all
affected floors and on new floors including bathrooms
and showers, concrete roof.

2 A760 - WATERPROOFING 5 12 Sep 23 18 Sep 23 0


A160 - BILL NO. 16 -Waterproofing _ Waterproofing _ 5 A180 12 Sep 23 18 Sep 23 0
On all new concrete roofs, on shower floors. A330 1

2 A770 - CEILINGS 8 19 Sep 23 28 Sep 23 0


A180 - BILL NO. 18 -SUSPENDED CEILINGS _Attending 8 A930 7 19 Sep 23 28 Sep 23 0
to all ceiling repairs in the affected areas and a few A900 2
new ceilings. Prep ceiings and make ready for painting

2 A920 - FIRST PAINTING - PRIME & PAINT 5 28 Sep 23 04 Oct 23 0


B A930 - BILL NO. 22 -Paintwork_ Prep and prime all 5 28 Sep 23 04 Oct 23 0
sections that are completed. Paint ceilings prior to
flooring. Paint first coat paint to internal walls. Paint
first coat to external walls.

2 A880 - ELECTRICAL SECOND FIX 7 21 Sep 23 29 Sep 23 3


A900 - PC SUM _ Reconfiguration and wiring to specific 7 A910 1 21 Sep 23 29 Sep 23 3
points as per the rebuilt structures

2 A890 - PLUMBING SECOND FIX 6 22 Sep 23 29 Sep 23 3


A910 - BILL NO. 21 New plumbing construction to 6 A200 4 22 Sep 23 29 Sep 23 3
specific points as per the rebuilt structure including
installation of built in bath tubs

2 A790 - FLOOR FINISHINGS & TILING 14 28 Sep 23 17 Oct 23 3


A200 - BILL NO. 20-TILING LABOUR_ floors/walls_ 14 A170 8 28 Sep 23 17 Oct 23 3
floors/walls_Start tiling with all bathrooms and then to
the rest of the apartments & external areas. All tiling
materials Supplied by client

2 A820 - DOORS,CABINETS, ETC 9 10 Oct 23 20 Oct 23 3


A170 - BILL NO. 17 -CARPENTRY & JOINERY_ 9 A950 3 10 Oct 23 20 Oct 23 3
Installation of doors, cupboards,and any joinery items
related to the first floor

2 A940 - SECOND PAINTING 15 13 Oct 23 02 Nov 23 3


A950 - BILL NO. 22 -Paintwork_ Second and final coats 15 A210 3 13 Oct 23 02 Nov 23 3
of painitng to walls. Painting of roofs and doors

2 A800 - SANITARYWARE INSTALLATION 5 18 Oct 23 24 Oct 23 3


A210 - BILL NO. 21 -PLUMBING _ PLUMBING & 5 A220 4 18 Oct 23 24 Oct 23 3
DRAINAGE_ Installation of toilets, basins, sinks, shwer
enclosures, taps and fittings

2 A810 - FINAL PAINTING 12 27 Oct 23 13 Nov 23 0


A220 - BILL NO. 22 -PAINTWORK_ Paintwork_Final 12 A990 0 27 Oct 23 13 Nov 23 0
coats painting of all internal and extersnl walls, touch
ups and checking to ensure all finishings are attended
to

2 A980 - OTHER FINISHINGS 8 27 Oct 23 07 Nov 23 0


B A990 - Ballustrades, fittings, decor items 8 27 Oct 23 07 Nov 23 0

1 A230 - PROVISIONAL AMOUNTS & BUDGETARY 52 17 Aug 23 27 Oct 23 0


ALLOWANCES
A330 - PAVING 19 A360 1 02 Oct 23 26 Oct 23 4
B A360 - LANDSCAPING 15 09 Oct 23 27 Oct 23 0
B A370 - TREE CUTTING 5 17 Aug 23 23 Aug 23 0
Printed 04:43:23 26 May 2023 Page 2 of 2