SCHEDULE OF REMOVING
Activity ID Activity Name Planned Remaining Start Finish
Duration Duration
A1120 Prepare the 30,000L temporary Oil tank for purifier the new oil. 2 2 03-Mar-23* 04-Mar-23
A1130 Site test of the supplyed LV(XV, YV) & HV bushing ( by TA) 1 1 03-Mar-23* 03-Mar-23
A1170 Assembly the IPB, MV terminal box and bus bar 2 2 06-Mar-23* 07-Mar-23
A1180 Erection the Vacuum machine for in the New box Make the vacuum. 2 2 07-Mar-23* 08-Mar-23
A1190 Reinstall fire fighting 2 2 08-Mar-23* 09-Mar-23
A1200 Filling the New oil and the Purified oil into the New UAT box and Holding (48hr) 4 4 06-Mar-23* 09-Mar-23
A1210 Remove the scaffolding and connect the earthing cable 5 5 06-Mar-23* 10-Mar-23
A1220 Any testing item point's test after all assembled 1 1 09-Mar-23* 09-Mar-23
A1225 Connection the Main control box. 3 3 06-Mar-23* 08-Mar-23
A1230 Energizing the Unit #2 Transmission line, Install fence and housekeeping 2 2 10-Mar-23* 11-Mar-23
Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Baseline Milestone summary © Oracle Corporation