SCHEDULE OF REMOVING
Activity ID Activity Name Planned Remaining Start Finish
Duration Duration

032023 New UAT Set in site 17 17 23-Feb-23 11-Mar-23

A1000 Tools and Equipment mobilization to Site (Batch 1) 1 1 24-Feb-23* 24-Feb-23


A1010 Remove the Gravel from the New UAT Box unloading position. 1 1 25-Feb-23* 25-Feb-23
A1020 Sand filling of New UAT Box loading position. 1 1 25-Feb-23* 25-Feb-23
A1030 Preparation of the UAT Accessory box unloading area 1 1 25-Feb-23* 25-Feb-23
A1040 Remove the Sump pump system and One electric post. 1 1 25-Feb-23* 25-Feb-23
A1050 Erecting Scaffolding for cover for protecting the rain. 5 5 23-Feb-23* 27-Feb-23

032023.030223.1 UAT Before shutdown 6 6 27-Feb-23 04-Mar-23


A1060 Inspection body & part by TA 1 1 27-Feb-23* 27-Feb-23
A1070 Assembly Conservator set 1 1 27-Feb-23* 27-Feb-23
A1080 Assemly Radiator and Fan (13set) 3 3 27-Feb-23* 01-Mar-23
A1085 Mobilization equipment ( Batch 2) 2 2 01-Mar-23* 02-Mar-23
A1090 Assembly the any Pipe line and cables, HV bushing 1 1 02-Mar-23* 02-Mar-23
A1100 Installation the Skidding Rail for installation for New UAT 1 1 02-Mar-23* 02-Mar-23
A1110 Install scaffolding, Remove fence & IBP temporary close cover and firefighting 2 2 02-Mar-23* 03-Mar-23

A1120 Prepare the 30,000L temporary Oil tank for purifier the new oil. 2 2 03-Mar-23* 04-Mar-23
A1130 Site test of the supplyed LV(XV, YV) & HV bushing ( by TA) 1 1 03-Mar-23* 03-Mar-23

032023.1 UAT Shutdown 9 9 03-Mar-23 11-Mar-23


A1140 Remove the all Fire fighting line and another touching point. 2 2 03-Mar-23* 04-Mar-23
A1150 Skidding UAT to the foundation 1 1 04-Mar-23* 04-Mar-23
A1160 Erection Cover IPB upside protection for rain and assembly/ connection for remaining work. 2 2 05-Mar-23* 06-Mar-23
Remove skidding rail

A1170 Assembly the IPB, MV terminal box and bus bar 2 2 06-Mar-23* 07-Mar-23
A1180 Erection the Vacuum machine for in the New box Make the vacuum. 2 2 07-Mar-23* 08-Mar-23
A1190 Reinstall fire fighting 2 2 08-Mar-23* 09-Mar-23
A1200 Filling the New oil and the Purified oil into the New UAT box and Holding (48hr) 4 4 06-Mar-23* 09-Mar-23
A1210 Remove the scaffolding and connect the earthing cable 5 5 06-Mar-23* 10-Mar-23
A1220 Any testing item point's test after all assembled 1 1 09-Mar-23* 09-Mar-23
A1225 Connection the Main control box. 3 3 06-Mar-23* 08-Mar-23
A1230 Energizing the Unit #2 Transmission line, Install fence and housekeeping 2 2 10-Mar-23* 11-Mar-23

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Baseline Milestone summary © Oracle Corporation