DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023.

21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
Total 359 21-Jan-22 18-Mar-23 7228

MILESTONES MMR 0 09-Jan-23 09-Jan-23 0


MMR101141 Start Electrical Construction Works 0 09-Jan-23* 0
YARD AREA 30 12-Jan-23 15-Feb-23 276

EQUIPMENT INSTALLATION 19 12-Jan-23 02-Feb-23 14


MEDIUM SWGR 19 12-Jan-23 02-Feb-23 8
Installation 11 12-Jan-23 24-Jan-23 4
A100190 Set SWGR MV-A 5 12-Jan-23 17-Jan-23 1
A105084 Set SWGR MV-B 5 18-Jan-23 23-Jan-23 1
A105242 Grounding SWGR MV-A 1 18-Jan-23 18-Jan-23 1
A105243 Grounding SWGR MV-B 1 24-Jan-23 24-Jan-23 1
Installation Complete 6 26-Jan-23 01-Feb-23 2
A105493 Installation Complete - SWGR MV-A 1 26-Jan-23 26-Jan-23 1
A105494 Installation Complete - SWGR MV-B 1 01-Feb-23 01-Feb-23 1
Site Acceptance Test 6 27-Jan-23 02-Feb-23 2
A105495 Site Acceptance Test - SWGR MV-A 1 27-Jan-23 27-Jan-23 1
A105496 Site Acceptance Test - SWGR MV-B 1 02-Feb-23 02-Feb-23 1
GENERATORS 6 24-Jan-23 30-Jan-23 4
Installation 4 24-Jan-23 27-Jan-23 2
A100350 Installation on site GEN HS 3 24-Jan-23 26-Jan-23 1
A105227 Grounding Gen HS 1 27-Jan-23 27-Jan-23 1
Installation Complete 1 28-Jan-23 28-Jan-23 1
A105530 Installation Complete - GEN HS 1 28-Jan-23 28-Jan-23 1
Site Acceptance Test 1 30-Jan-23 30-Jan-23 1
A105531 Site Acceptance Test - GEN HS 1 30-Jan-23 30-Jan-23 1
TRANSFORMERS 4 27-Jan-23 31-Jan-23 2
Installation 4 27-Jan-23 31-Jan-23 2
A100255 Set on site House Service-XFMR 3 27-Jan-23 30-Jan-23 1
A105233 Grounding Transformer HS-XFMR 1 31-Jan-23 31-Jan-23 1
PULL and LAYING CABLE 10 24-Jan-23 03-Feb-23 259
A105311 MT-UTL-1 Install Cable Utility SubStation to SWGR MV-A 10 24-Jan-23 03-Feb-23 80
A105413 MT-UTL-2 Install Cable Utility SubStation to SWGR MV-B 10 24-Jan-23 03-Feb-23 170
A105119 MT-04 Install Cable SWGR MV-B to House Service - XFMR 4 31-Jan-23 03-Feb-23 9
CABLE TESTING 10 04-Feb-23 15-Feb-23 3

Actual Level of Effort Remaining Work Page 1 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A105424 VLF Testing - MT-04 Cable SWGR MV-B to House Service - XFMR 1 04-Feb-23 04-Feb-23 1
A105433 VLF Testing - MT-UTL-1 Cable Utility SubStation to SWGR MV-A 10 04-Feb-23 15-Feb-23 1
A105434 VLF Testing - MT-UTL-2 Cable Utility SubStation to SWGR MV-B 10 04-Feb-23 15-Feb-23 1
ELECTRICAL ROOM 30 14-Jan-23 17-Feb-23 80

COMMON 30 14-Jan-23 17-Feb-23 12


SUPPORTS 30 14-Jan-23 17-Feb-23 2
A105362 Install Supports Cable Trays - Electrical Room 30 14-Jan-23 17-Feb-23 1
A105375 Supports Equipments and Panels - Electrical Room 20 14-Jan-23 06-Feb-23 1
CABLE TRAYS 2 21-Jan-23 23-Jan-23 10
Cable Tray 4046mm (8) 2 21-Jan-23 23-Jan-23 10
A107086 Cable Trays CT-MSDBA-01 2 21-Jan-23 23-Jan-23 5
A107087 Cable Trays CT-MSDBA-02 2 21-Jan-23 23-Jan-23 5
USB ELECTRICAL ROOM 16 18-Jan-23 04-Feb-23 23
EQUIPMENT INSTALLATION 16 18-Jan-23 04-Feb-23 23
Installation 16 18-Jan-23 04-Feb-23 17
LV Switchgears 11 18-Jan-23 30-Jan-23 8
A100280 Install Switch Board USB 1.1B 3 18-Jan-23 20-Jan-23 1
A100695 Install COP 1.1B 2 21-Jan-23 23-Jan-23 1
A105553 Grounding Switch Board USB 1.1B 1 21-Jan-23 21-Jan-23 1
A100690 Install COP 1.1A 2 24-Jan-23 25-Jan-23 1
A105554 Grounding COP 1.1B 1 24-Jan-23 24-Jan-23 1
A100087 Install Switch Board USB 1.1A 3 26-Jan-23 28-Jan-23 1
A105555 Grounding COP 1.1A 1 26-Jan-23 26-Jan-23 1
A105556 Grounding Switch Board USB 1.1A 1 30-Jan-23 30-Jan-23 1
Panels 6 30-Jan-23 04-Feb-23 9
A101306 Install MSDB 1.1B1 2 30-Jan-23 31-Jan-23 1
A103626 Install CUPP 1.1A 2 30-Jan-23 31-Jan-23 1
A101308 Install MSDB 1.1B2 2 01-Feb-23 02-Feb-23 1
A105549 Install HUPP 1.1 1 01-Feb-23 01-Feb-23 1
A105568 Grounding MSDB 1.1B1 1 01-Feb-23 01-Feb-23 1
A105559 Grounding CUPP 1.1A 1 01-Feb-23 01-Feb-23 1
A105564 Grounding HUPP 1.1 1 02-Feb-23 02-Feb-23 1
A101310 Install MSDB 1.1B3 2 03-Feb-23 04-Feb-23 1
A105569 Grounding MSDB 1.1B2 1 03-Feb-23 03-Feb-23 1

Actual Level of Effort Remaining Work Page 2 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
Installation Complete 5 30-Jan-23 03-Feb-23 3
LV Switchgears 5 30-Jan-23 03-Feb-23 3
A105656 Installation Complete - USB 1.1B 1 30-Jan-23 30-Jan-23 1
A105654 Installation Complete - COP 1.1B 1 01-Feb-23 01-Feb-23 1
A105653 Installation Complete - COP 1.1A 1 03-Feb-23 03-Feb-23 1
Site Acceptance Test 5 31-Jan-23 04-Feb-23 3
LV Switchgears 5 31-Jan-23 04-Feb-23 3
A105660 Site Acceptance Test - USB 1.1B 1 31-Jan-23 31-Jan-23 1
A105658 Site Acceptance Test - COP 1.1B 1 02-Feb-23 02-Feb-23 1
A105657 Site Acceptance Test - COP 1.1A 1 04-Feb-23 04-Feb-23 1
CHILLER ROOM 14 20-Jan-23 04-Feb-23 26
EQUIPMENT INSTALLATION 14 20-Jan-23 04-Feb-23 26
Installation 14 20-Jan-23 04-Feb-23 21
LV Switchgears 6 20-Jan-23 26-Jan-23 4
A100380 Install Switch Board CH USB 1.1 3 20-Jan-23 23-Jan-23 1
A101298 Install CH COP 1.1 2 24-Jan-23 25-Jan-23 1
A105587 Grounding Switch Board CH USB 1.1 1 24-Jan-23 24-Jan-23 1
A105586 Grounding CH COP 1.1 1 26-Jan-23 26-Jan-23 1
Panels 2 03-Feb-23 04-Feb-23 3
A101330 Install CH MSDB 1.1A 1 03-Feb-23 03-Feb-23 1
A101590 Install CH MSDB 1.1B 1 04-Feb-23 04-Feb-23 1
A105593 Grounding CH MSDB 1.1A 1 04-Feb-23 04-Feb-23 1
ATSs 8 26-Jan-23 03-Feb-23 14
A103658 Install ATS CH 1.1-04 (Not included in Equipment Lis t) 1 26-Jan-23 26-Jan-23 1
A103656 Install ATS CH 1.1-03 1 27-Jan-23 27-Jan-23 1
A105601 Grounding ATS CH 1.1-04 1 27-Jan-23 27-Jan-23 1
A103654 Install ATS CH 1.1-02 1 28-Jan-23 28-Jan-23 1
A105602 Grounding ATS CH 1.1-03 1 28-Jan-23 28-Jan-23 1
A103646 Install ATS CH 1.1A 1 30-Jan-23 30-Jan-23 1
A105603 Grounding ATS CH 1.1-02 1 30-Jan-23 30-Jan-23 1
A103648 Install ATS CH 1.1B 1 31-Jan-23 31-Jan-23 1
A105600 Grounding ATS CH 1.1A 1 31-Jan-23 31-Jan-23 1
A103650 Install ATS CH 1.1C 1 01-Feb-23 01-Feb-23 1
A105599 Grounding ATS CH 1.1B 1 01-Feb-23 01-Feb-23 1

Actual Level of Effort Remaining Work Page 3 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A103652 Install ATS CH 1.1-01 1 02-Feb-23 02-Feb-23 1
A105598 Grounding ATS CH 1.1C 1 02-Feb-23 02-Feb-23 1
A105604 Grounding ATS CH 1.1-01 1 03-Feb-23 03-Feb-23 1
Installation Complete 4 01-Feb-23 04-Feb-23 3
LV Switchgears 3 01-Feb-23 03-Feb-23 2
A105719 Installation Complete - Switch Board CH USB 1.1 1 01-Feb-23 01-Feb-23 1
A105720 Installation Complete - CH COP 1.1 1 03-Feb-23 03-Feb-23 1
ATSs 1 04-Feb-23 04-Feb-23 1
A105753 Installation Complete - ATS CH 1.1-04 1 04-Feb-23 04-Feb-23 1
Site Acceptance Test 3 02-Feb-23 04-Feb-23 2
LV Switchgears 3 02-Feb-23 04-Feb-23 2
A105721 Site Acceptance Test - Switch Board CH USB 1.1 1 02-Feb-23 02-Feb-23 1
A105722 Site Acceptance Test - CH COP 1.1 1 04-Feb-23 04-Feb-23 1
CATCHER 1 ROOM 13 21-Jan-23 04-Feb-23 15
EQUIPMENT INSTALLATION 13 21-Jan-23 04-Feb-23 15
Installation 8 21-Jan-23 30-Jan-23 8
LV Switchgears 4 21-Jan-23 25-Jan-23 2
A100305 Install Switch Board USB C1 3 21-Jan-23 24-Jan-23 1
A105614 Grounding Switch Board USB C1 1 25-Jan-23 25-Jan-23 1
Panels 3 27-Jan-23 30-Jan-23 4
A106002 Install HUPP C1 1 27-Jan-23 27-Jan-23 1
A106003 Grounding HUPP C1 1 28-Jan-23 28-Jan-23 1
A106285 Install HLP C1 1 28-Jan-23 28-Jan-23 1
A106286 Grounding HLP C1 1 30-Jan-23 30-Jan-23 1
AMCOP 3 25-Jan-23 27-Jan-23 2
A103995 Install AMCOP Panel C1 2 25-Jan-23 26-Jan-23 1
A105615 Grounding AMCOP Panel C1 1 27-Jan-23 27-Jan-23 1
Installation Complete 6 30-Jan-23 04-Feb-23 4
LV Switchgears 1 02-Feb-23 02-Feb-23 1
A105777 Installation Complete - Board USB C1 1 02-Feb-23 02-Feb-23 1
Panels 1 30-Jan-23 30-Jan-23 2
A106004 Installation Complete HUPP C1 1 30-Jan-23 30-Jan-23 1
A106287 Installation Complete HLP C1 1 30-Jan-23 30-Jan-23 1
AMCOP 1 04-Feb-23 04-Feb-23 1
A105779 Installation Complete - AMCOP Panel C1 1 04-Feb-23 04-Feb-23 1

Actual Level of Effort Remaining Work Page 4 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
Site Acceptance Test 4 31-Jan-23 03-Feb-23 3
LV Switchgears 1 03-Feb-23 03-Feb-23 1
A105778 Site Acceptance Test - Board USB C1 1 03-Feb-23 03-Feb-23 1
Panels 1 31-Jan-23 31-Jan-23 2
A106005 Site Acceptance Test - HUPP C1 1 31-Jan-23 31-Jan-23 1
A106288 Site Acceptance Test - HLP C1 1 31-Jan-23 31-Jan-23 1
CATCHER 2 ROOM 6 25-Jan-23 31-Jan-23 4
EQUIPMENT INSTALLATION 6 25-Jan-23 31-Jan-23 4
Installation 6 25-Jan-23 31-Jan-23 4
LV Switchgears 4 25-Jan-23 28-Jan-23 2
A100330 Install Switch Board USB C2 3 25-Jan-23 27-Jan-23 1
A105616 Grounding Switch Board USB C2 1 28-Jan-23 28-Jan-23 1
AMCOP 3 28-Jan-23 31-Jan-23 2
A104000 Install AMCOP Panel C2 2 28-Jan-23 30-Jan-23 1
A105617 Grounding AMCOP Panel C2 1 31-Jan-23 31-Jan-23 1
BUS DUCT 24 16-Jan-23 11-Feb-23 0
BUS DUCT C1 8 16-Jan-23 24-Jan-23 0
A103664 Install Hangers - Busduct C1 8 16-Jan-23 24-Jan-23 0
BUS DUCT C2 24 16-Jan-23 11-Feb-23 0
A103666 Install Hangers - Busduct C2 8 16-Jan-23 24-Jan-23 0
A105804 Install - Busduct C2 16 25-Jan-23 11-Feb-23 0
DATA HALL 5 28-Jan-23 02-Feb-23 90

CABLE TRAYS 5 28-Jan-23 02-Feb-23 90


A106744 Install Supports Cable Trays (9050mm) - Data Hall 2 28-Jan-23 30-Jan-23 1
Cable Tray 9050mm (2) 3 31-Jan-23 02-Feb-23 89
A106390 Cable Trays 2 CT-EF-11 3 31-Jan-23 02-Feb-23 14
A106391 Cable Trays 2 CT-EF-12 3 31-Jan-23 02-Feb-23 14
A106392 Cable Trays 2 CT-EF-08 3 31-Jan-23 02-Feb-23 6
A106393 Cable Trays 2 CT-EF-09 3 31-Jan-23 02-Feb-23 4
A106394 Cable Trays 2 CT-EF-06 3 31-Jan-23 02-Feb-23 10
A106395 Cable Trays 2 CT-EF-04 3 31-Jan-23 02-Feb-23 7
A106396 Cable Trays 2 CT-EF-02 3 31-Jan-23 02-Feb-23 9
A106397 Cable Trays 2 CT-EF-07 3 31-Jan-23 02-Feb-23 10
A106398 Cable Trays 2 CT-EF-03 3 31-Jan-23 02-Feb-23 15

Actual Level of Effort Remaining Work Page 5 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
DAHU 1 5 31-Jan-23 04-Feb-23 1

CABLE TRAYS 5 31-Jan-23 04-Feb-23 1


A106468 Install Supports Cable Trays - DAHU-1 5 31-Jan-23 04-Feb-23 1
OFFICE 41 09-Jan-23 24-Feb-23 6780
A101159 Office Area Available 0 09-Jan-23* 0
COMMON 25 09-Jan-23 06-Feb-23 1
A105256 Supports Conduits and Cable Trays 25 09-Jan-23 06-Feb-23 1
EQUIPMENT INSTALLATION 21 09-Jan-23 01-Feb-23 61
Supports and Boxes 13 09-Jan-23 23-Jan-23 21
A105258 Supports of Panels 3 09-Jan-23 11-Jan-23 7
A105259 Supports of Boxes Distribution 2 20-Jan-23 21-Jan-23 7
A105261 Install Boxes Distribution 3 20-Jan-23 23-Jan-23 7
Installation Equipments 10 12-Jan-23 23-Jan-23 18
LV Panels 9 12-Jan-23 21-Jan-23 16
A104105 Install LV Panel OLP 1 12-Jan-23 12-Jan-23 1
A104107 Install LV Panel OMP2 1 13-Jan-23 13-Jan-23 1
A105623 Grounding Panel OLP 1 13-Jan-23 13-Jan-23 1
A104109 Install LV Panel OPP1A4 1 14-Jan-23 14-Jan-23 1
A106006 Grounding Panel OMP2 1 14-Jan-23 14-Jan-23 1
A104111 Install LV Panel OUPP1A2 1 16-Jan-23 16-Jan-23 1
A106007 Grounding Panel OPP1A4 1 16-Jan-23 16-Jan-23 1
Installation Install LV Panel OPP1A3 1 17-Jan-23 17-Jan-23 1
A106008 Grounding Panel OUPP1A2 1 17-Jan-23 17-Jan-23 1
A104115 Install LV Panel OPP1A2 1 18-Jan-23 18-Jan-23 1
A106009 Grounding Panel OPP1A3 1 18-Jan-23 18-Jan-23 1
A104117 Install LV Panel OPP1A1 1 19-Jan-23 19-Jan-23 1
A106010 Grounding Panel OPP1A2 1 19-Jan-23 19-Jan-23 1
A105620 Install LV Panel OMP1 1 20-Jan-23 20-Jan-23 1
A106011 Grounding Panel OPP1A1 1 20-Jan-23 20-Jan-23 1
A106012 Grounding Panel OMP1 1 21-Jan-23 21-Jan-23 1
LV XFMR 2 21-Jan-23 23-Jan-23 2
A104119 Install Transformer OPP-XFMR 1 21-Jan-23 21-Jan-23 1
A106013 Grounding OPP-XFMR 1 23-Jan-23 23-Jan-23 1

Actual Level of Effort Remaining Work Page 6 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
Installation Complete 9 21-Jan-23 31-Jan-23 9
LV Panels 8 21-Jan-23 30-Jan-23 8
A106014 Installation Complete - Panel OLP 1 21-Jan-23 21-Jan-23 1
A106015 Installation Complete - Panel OMP2 1 23-Jan-23 23-Jan-23 1
A106016 Installation Complete - Panel OPP1A4 1 24-Jan-23 24-Jan-23 1
A106017 Installation Complete - Panel OUPP1A2 1 25-Jan-23 25-Jan-23 1
A106018 Installation Complete - Panel OPP1A3 1 26-Jan-23 26-Jan-23 1
A106019 Installation Complete - Panel OPP1A2 1 27-Jan-23 27-Jan-23 1
A106020 Installation Complete - Panel OPP1A1 1 28-Jan-23 28-Jan-23 1
A105787 Installation Complete - OMP1 1 30-Jan-23 30-Jan-23 1
LV XFMR 1 31-Jan-23 31-Jan-23 1
A106021 Installation Complete - Transformer OPP-XFMR 1 31-Jan-23 31-Jan-23 1
Site Acceptance Test 9 23-Jan-23 01-Feb-23 9
LV Panels 8 23-Jan-23 31-Jan-23 8
A106022 Site Acceptance Test - Panel OLP 1 23-Jan-23 23-Jan-23 1
A106023 Site Acceptance Test - Panel OMP2 1 24-Jan-23 24-Jan-23 1
A106024 Site Acceptance Test - Panel OPP1A4 1 25-Jan-23 25-Jan-23 1
A106025 Site Acceptance Test - Panel OUPP1A2 1 26-Jan-23 26-Jan-23 1
A106026 Site Acceptance Test - Panel OPP1A3 1 27-Jan-23 27-Jan-23 1
A106027 Site Acceptance Test - Panel OPP1A2 1 28-Jan-23 28-Jan-23 1
A106028 Site Acceptance Test - Panel OPP1A1 1 30-Jan-23 30-Jan-23 1
A105790 Site Acceptance Test - OMP1 1 31-Jan-23 31-Jan-23 1
LV XFMR 1 01-Feb-23 01-Feb-23 1
A106029 Site Acceptance Test - Transformer OPP-XFMR 1 01-Feb-23 01-Feb-23 1
BUS DUCT C1 and C2 OFFICE AREA 9 09-Jan-23 18-Jan-23 4
Installation 7 09-Jan-23 16-Jan-23 2
B105307 Install Bus Duct C1 and C2 Office Area 6 09-Jan-23 14-Jan-23 1
A106049 Grounding - Busduct C1 and C2 Office Area 1 16-Jan-23 16-Jan-23 1
Installation Complete 1 17-Jan-23 17-Jan-23 1
B105308 Installation Complete Bus Duct C1 and C2 Office Area 1 17-Jan-23 17-Jan-23 1
Site Acceptance Test 1 18-Jan-23 18-Jan-23 1
B105309 Site Acceptance Test Bus Duct C1 and C2 Office Area 1 18-Jan-23 18-Jan-23 1
CABLE TRAYS 22 16-Jan-23 09-Feb-23 361
Cable Tray 3080mm (13) 22 16-Jan-23 09-Feb-23 361
A106516 Cable Trays 13 CT-HSSB-08 22 16-Jan-23 09-Feb-23 38

Actual Level of Effort Remaining Work Page 7 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A106517 Cable Trays 13 CT-HSSB-09 22 16-Jan-23 09-Feb-23 25
A106518 Cable Trays 13 CT-HSSB-10 22 16-Jan-23 09-Feb-23 4
A106519 Cable Trays 13 CT-HSSB-11 22 16-Jan-23 09-Feb-23 18
A106520 Cable Trays 13 CT-HSSB-12 22 16-Jan-23 09-Feb-23 24
A106521 Cable Trays 13 CT-HSSB-13 22 16-Jan-23 09-Feb-23 6
A106522 Cable Trays 13 CT-HSSB-14 22 16-Jan-23 09-Feb-23 4
A106523 Cable Trays 13 CT-HSSB-15 22 16-Jan-23 09-Feb-23 4
A106524 Cable Trays 13 CT-HSSB-16 22 16-Jan-23 09-Feb-23 11
A106525 Cable Trays 13 CT-HSSB-17 22 16-Jan-23 09-Feb-23 28
A106526 Cable Trays 13 CT-HSSB-18 22 16-Jan-23 09-Feb-23 7
A106527 Cable Trays 13 CT-HSSB-19 22 16-Jan-23 09-Feb-23 2
A106528 Cable Trays 13 CT-HSSB-20 22 16-Jan-23 09-Feb-23 7
A106529 Cable Trays 13 CT-HSSB-21 22 16-Jan-23 09-Feb-23 4
A106530 Cable Trays 13 CT-HSSB-22 22 16-Jan-23 09-Feb-23 11
A106531 Cable Trays 13 CT-HSSB-23 22 16-Jan-23 09-Feb-23 24
A106532 Cable Trays 13 CT-HSSB-24 22 16-Jan-23 09-Feb-23 16
A106533 Cable Trays 13 CT-HSSB-25 22 16-Jan-23 09-Feb-23 3
A106534 Cable Trays 13 CT-HSSB-26 22 16-Jan-23 09-Feb-23 31
A106535 Cable Trays 13 CT-HSSB-27 22 16-Jan-23 09-Feb-23 33
A106536 Cable Trays 13 CT-HSSB-28 22 16-Jan-23 09-Feb-23 4
A106537 Cable Trays 13 CT-HSSB-29 22 16-Jan-23 09-Feb-23 9
A106538 Cable Trays 13 CT-HSSB-30 22 16-Jan-23 09-Feb-23 12
A106539 Cable Trays 13 CT-HSSB-31 22 16-Jan-23 09-Feb-23 12
A106540 Cable Trays 13 CT-HSSB-32 22 16-Jan-23 09-Feb-23 6
A106541 Cable Trays 13 CT-HSSB-33 22 16-Jan-23 09-Feb-23 8
A106542 Cable Trays 13 CT-HSSB-34 22 16-Jan-23 09-Feb-23 2
A106543 Cable Trays 13 CT-HSSB-35 22 16-Jan-23 09-Feb-23 8
CONDUITS 35 16-Jan-23 24-Feb-23 6220
EMT 35 16-Jan-23 24-Feb-23 5176
A106581 C-BT-HS-130 OPP1A1 to DISK DESTRUCTION - Conduit EMT 1" 35 16-Jan-23 24-Feb-23 61
A106582 C-BT-HS-162 OPP1A1 to WH-1-4 - Conduit EMT 1" 35 16-Jan-23 24-Feb-23 63
A106583 C-BT-HS-146 OPP1A1 to WORK STATION FURNITURE RED ZONE OFFICE
35 -16-Jan-23
Conduit EMT 24-Feb-23
3/4" 56
A106584 C-BT-HS-148 OPP1A1 to WORK STATION FURNITURE RED ZONE OFFICE
35 -16-Jan-23
Conduit EMT 24-Feb-23
3/4" 56

Actual Level of Effort Remaining Work Page 8 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A106585 C-BT-HS-149 OPP1A1 to REC CORRIDOR FIRE RISER, FILTER - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 70
A106586 C-BT-HS-152 OPP1A1 to REC-FIBER CLOSET CORRIDOR - Conduit EMT
35 3/4"16-Jan-23 24-Feb-23 60
A106587 C-BT-HS-153 OPP1A1 to REC CORRIDOR FIRE RISER - Conduit EMT
353/4" 16-Jan-23 24-Feb-23 93
A106588 C-BT-HS-154 OPP1A1 to REC-FLEX ROOM STORAGE - Conduit EMT35
3/4" 16-Jan-23 24-Feb-23 60
A106589 C-BT-HS-155 OPP1A1 to REC-WATER TANKS - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 120
A106590 C-BT-HS-157 OPP1A1 to RED ZONE HALLWAYS - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 80
A106592 C-BT-HS-161 OPP1A1 to REC-CORRIDOR, MEDICAL, LACTATION - Conduit
35 16-Jan-23
EMT 3/4" 24-Feb-23 66
A106593 C-BT-HS-163 OPP1A1 to SYSTEM FURNITURE - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 35
A106591 C-BT-HS-159 OPP1A1 to REC-STORAGE , FIBER CLOSET - Conduit 35
EMT 3/4"
16-Jan-23 24-Feb-23 198
A106597 C-BT-HS-179 OPP1A2 to REC-ROOF - Conduit EMT 1" 35 16-Jan-23 24-Feb-23 118
A106598 C-BT-HS-165 OPP1A2 to SECURITY EQUIPMENT-RED ZONE - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 45
A106599 C-BT-HS-166 OPP1A2 to LTS-ROOF - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 118
A106600 C-BT-HS-167 OPP1A2 to SECURITY EQUIPMENT-RED ZONE - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 45
A106601 C-BT-HS-168 OPP1A2 to REC-CONFERENCE RM FLOOR - Conduit35EMT 3/4"
16-Jan-23 24-Feb-23 15
A106602 C-BT-HS-169 OPP1A2 to SECURITY EQUIPMENT-RED ZONE - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 45
A106603 C-BT-HS-171 OPP1A2 to SECURITY EQUIPMENT-RED ZONE - Condui
35 t EMT
16-Jan-23
3/4" 24-Feb-23 45
A106604 C-BT-HS-174 OPP1A2 to REC-VEND MACHINE BREAKROOM - Conduit
35 EMT
16-Jan-23
3/4" 24-Feb-23 55
A106605 C-BT-HS-176 OPP1A2 to REC-VEND MACHINE BREAKROOM - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 55
A106606 C-BT-HS-182 OPP1A2 to DISK DEGAUSSER - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 54
A106607 C-BT-HS-183 OPP1A2 to SYSTEM FURNITURE - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 40
A106608 C-BT-HS-184 OPP1A2 to SYSTEM FURNITURE - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 40
A106609 C-BT-HS-185 OPP1A2 to SYSTEM FURNITURE - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 50
A106610 C-BT-HS-187 OPP1A2 to DISK DEGAUSSER - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 54
A106611 C-BT-HS-188 OPP1A2 to RECEPT OFFICE AREA - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 88
A106612 C-BT-HS-189 OPP1A2 to RECEPT OFFICE AREA - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 118
A106613 C-BT-HS-190 OPP1A2 to REC-VEND MACHINE BREAKROOM - Conduit
35 EMT
16-Jan-23
3/4" 24-Feb-23 55
A106614 C-BT-HS-192 OPP1A2 to BRANCH SELECTOR - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 68
A106615 C-BT-HS-193 OPP1A2 to FACP - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 59
A106616 C-BT-HS-194 OPP1A2 to SYSTEM FURNITURE - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 44
A106617 C-BT-HS-195 OPP1A2 to DISK DESTRUCCION - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 54
A106618 C-BT-HS-196 OPP1A3 to HSSB CONTROL POWER - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 66
A106619 C-BT-HS-200 OPP1A3 to SECURITY CONNECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 16
A106620 C-BT-HS-201 OPP1A3 to SECURITY CONNECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 16

Actual Level of Effort Remaining Work Page 9 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A106621 C-BT-HS-202 OPP1A3 to SECURITY CONNECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 16
A106622 C-BT-HS-203 OPP1A3 to SECURITY CONNECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 16
A106623 C-BT-HS-205 OPP1A3 to WH 1-1 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 19
A106624 C-BT-HS-208 OPP1A3 to MDF RM - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 15
A106625 C-BT-HS-213 OPP1A3 to FCU 1-01 TROUGHT 1-19 - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 200
A106626 C-BT-HS-215 OPP1A3 to TP-1 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 79
A106627 C-BT-HS-217 OPP1A3 to HWCP - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 45
A106628 C-BT-HS-219 OPP1A3 to FCU 2-01 TROUGHT2-10 - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 121
A106629 C-BT-HS-220 OPP1A3 to METAL DETECTOR - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 37
A106630 C-BT-HS-221 OPP1A3 to METAL DETECTOR - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 24
A106631 C-BT-HS-222 OPP1A3 to FCU 3-01 TROUGHT 3-12 - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 136
A106632 C-BT-HS-223 OPP1A3 to MDF ROOM SERVER - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 17
A106633 C-BT-HS-197 OPP1A3 to CU1-5 - Conduit EMT/RMC 1" 35 16-Jan-23 24-Feb-23 63
A106634 C-BT-HS-218 OPP1A3 to CU-1-10 - Conduit EMT/RMC 1" 35 16-Jan-23 24-Feb-23 69
A106635 C-BT-HS-224 OPP1A3 to CU-1-8 - Conduit EMT/RMC 1" 35 16-Jan-23 24-Feb-23 82
A106636 C-BT-HS-198 OPP1A3 to CU-1-4 - Conduit EMT/RMC 2" 35 16-Jan-23 24-Feb-23 110
A106637 C-BT-HS-212 OPP1A3 to CU-1-9 - Conduit EMT/RMC 2" 35 16-Jan-23 24-Feb-23 96
A106642 C-BT-HS-243 OUPP1A2 to SECURITY EQUIPMENT RED ZONE - Conduit
35 EMT
16-Jan-23
3/4" 24-Feb-23 42
A106643 C-BT-HS-244 OUPP1A2 to REC-VEND HALLWAY - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 48
A106644 C-BT-HS-245 OUPP1A2 to SECURITY EQUIPMENT RED ZONE - Conduit
35 EMT
16-Jan-23
3/4" 24-Feb-23 42
A106645 C-BT-HS-246 OUPP1A2 to REC-VEND HALLWAY - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 48
A106646 C-BT-HS-247 OUPP1A2 to SECURITY EQUIPMENT RED ZONE - Conduit
35 EMT
16-Jan-23
3/4" 24-Feb-23 42
A106647 C-BT-HS-250 OUPP1A2 to SECURITY CONECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 17
A106648 C-BT-HS-251 OUPP1A2 to DOOR ACCESS - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 95
A106649 C-BT-HS-252 OUPP1A2 to SECURITY CONECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 17
A106650 C-BT-HS-253 OUPP1A2 to SECURITY CONECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 17
A106651 C-BT-HS-254 OUPP1A2 to SECURITY CONECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 17
A106652 C-BT-HS-255 OUPP1A2 to MDF RECEPT - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 15
A106653 C-BT-HS-256 OUPP1A2 to SECURITY CAMERA - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 47
A106654 C-BT-HS-257 OUPP1A2 to PERIMETER SECURITY CAMERA - Conduit
35 EMT16-Jan-23
3/4" 24-Feb-23 84
A106655 C-BT-HS-258 OUPP1A2 to MDF SERVER - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 15
A106656 C-BT-HS-260 OUPP1A2 to REC-SEC CHECKPOINT - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 30
A106657 C-BT-HS-262 OUPP1A2 to REC-SEC CHECKPOINT - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 32

Actual Level of Effort Remaining Work Page 10 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A106658 C-BT-HS-264 OUPP1A2 to AMCOP HS - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 64
A106659 C-BT-HS-265 OUPP1A2 to HSSB CONTROL POWER - Conduit EMT35
3/4" 16-Jan-23 24-Feb-23 68
A106660 C-BT-HS-266 OUPP1A2 to REC-SEC CHECKPOINT - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 32
A106661 C-BT-HS-267 OUPP1A2 to REC-SEC CHECKPOINT - Conduit EMT 3/4"
35 16-Jan-23 24-Feb-23 32
A106662 C-BT-HS-241 OUPP1A2 to SECURITY CONECTIONS MDF - Conduit35
EMT 3/4"
16-Jan-23 24-Feb-23 42
A106663 C-BT-HS-242 OUPP1A2 to REC-VEND HALLWAY - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 48
A106664 C-BT-HS-225 OMP1 to ELECTRIC UNIT HEATER - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 64
A106665 C-BT-HS-226 OMP1 to ELECTRIC UNIT HEATER - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 64
A106666 C-BT-HS-229 OMP1 to ELECTRIC UNIT HEATER - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 65
A106667 C-BT-HS-230 OMP1 to ELECTRIC UNIT HEATER - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 74
A106668 C-BT-HS-231 OMP1 to ELECTRIC UNIT HEATER - Conduit EMT 3/4"35 16-Jan-23 24-Feb-23 40
A106669 C-BT-HS-227 OMP1 to CONDENSING UNIT - Conduit EMT/RMC 3/4"35 16-Jan-23 24-Feb-23 46
A106670 C-BT-HS-228 OMP1 to CONDENSING UNIT - Conduit EMT/RMC 3/4"35 16-Jan-23 24-Feb-23 46
A106671 C-BT-HS-232 OMP1 to CONDENSING UNIT - Conduit EMT/RMC 3/4"35 16-Jan-23 24-Feb-23 48
A106672 C-BT-HS-233 OMP1 to CONDENSING UNIT - Conduit EMT/RMC 3/4"35 16-Jan-23 24-Feb-23 49
A106674 C-BT-HS-234 OMP2 to WH 1-3 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 17
A106675 C-BT-HS-236 OMP2 to WH 1-2 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 60
A106676 C-BT-HS-214 OMP2 to WP-1.1.01 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 80
A106677 C-BT-HS-216 OMP2 to WP-1.1.02 - Conduit EMT 3/4" 35 16-Jan-23 24-Feb-23 80
A107194 C-BT-HS-40 from Panel OMP1 to Panel OMP2 35 16-Jan-23 24-Feb-23 6
A107195 C-BT-HS-41 from Panel OPP-XFMR to Panel OPP 1A1 35 16-Jan-23 24-Feb-23 7
A107196 C-BT-HS-43 from Panel OPP1A2 to Panel OPP 1A3 35 16-Jan-23 24-Feb-23 5
A107197 C-BT-HS-42 from Panel OPP 1A1 to Panel OPP 1A2 35 16-Jan-23 24-Feb-23 5
RMC 12 23-Jan-23 04-Feb-23 1043
A106594 C-BT-HS-151 OPP1A1 to REC MECHANICAL - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 90
A106595 C-BT-HS-158 OPP1A1 to LIGHTING DUMPSTER AREA - Conduit RMC
12 3/4" 23-Jan-23 04-Feb-23 123
A106596 C-BT-HS-160 OPP1A1 to RECEPT DUMPSTER AREA - Conduit RMC12
3/4" 23-Jan-23 04-Feb-23 121
A106638 C-BT-HS-206 OPP1A3 to GLY-01 - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 73
A106639 C-BT-HS-209 OPP1A3 to GLY-01B - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 73
A106640 C-BT-HS-210 OPP1A3 to CHL-01 - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 77
A106641 C-BT-HS-211 OPP1A3 to CHL-02 - Conduit R MC 3/4" 12 23-Jan-23 04-Feb-23 73
A106673 C-BT-HS-235 OMP2 to DOAS 1 - CABLE TRAY/Conduit RMC 2" 12 23-Jan-23 04-Feb-23 14
A106678 C-BT-HS-239 OMP2 to DOCK LEVELER 1 - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 59

Actual Level of Effort Remaining Work Page 11 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation
DETAIL MMR JOB NUMBER MX01000LS TASK filter: Activities start less than 04-feb-2023. 21-Dec-22 12:59
Activity ID Activity Name Original Start Finish Budgeted 2023
Duration Nonlabor January February March
Units 01 08 15 22 29 05 12 19 26 0512
A106679 C-BT-HS-240 OMP2 to DOCK LEVELER 2 - Conduit RMC 3/4" 12 23-Jan-23 04-Feb-23 54
A106680 C-BT-HS-269 OLP to EXTERIOR BUILDING WALL - PERIMETER LIGHTING
12 -23-Jan-23
Conduit RMC 04-Feb-23
3/4" 193
A106681 C-BT-HS-271 OLP to EXTERIOR BUILDING WALL - PERIMETER LIGHTING
12 -23-Jan-23
Conduit RMC 04-Feb-23
3/4" 93
Telecom 13 23-Jan-23 06-Feb-23 1
A104274 Telecom Device Rough-In 13 23-Jan-23 06-Feb-23 1
LIGHTING AND CONTROL 15 23-Jan-23 08-Feb-23 136
Lights 15 23-Jan-23 08-Feb-23 136
A107199 Lighting Supports Roof 6 23-Jan-23 28-Jan-23 68
A106948 Lightings - Roof 9 30-Jan-23 08-Feb-23 68
TELECOM 13 24-Jan-23 07-Feb-23 1
A103946 Telecom Receptacle Rough-in 13 24-Jan-23 07-Feb-23 1

DUMPSTER AREA 1 04-Feb-23 04-Feb-23 1


A104258 Dumpster Area Availa ble 0 04-Feb-23* 0
CONDUITS 1 04-Feb-23 04-Feb-23 1
Supports 1 04-Feb-23 04-Feb-23 1
A104259 Conduits Supports 1 04-Feb-23 04-Feb-23 1
MILESTONES FROM AWS SCHEDULE 195 01-Aug-22 18-Mar-23 0

PROCUREMENT 247 21-Jan-22 02-Jan-23 0

No CONSTRUCTION AREAS 356 21-Jan-22 15-Mar-23 0

Actual Level of Effort Remaining Work Page 12 of 12 Layout Trabajos proximas 3 semanas
Actual Work Critical Remainin... © Oracle Corporation