Phase 2 - Albawani GAQ Building Draft Baseline Schedule 10-Mar-24 12:04

Activity ID Activity Name Original Start Finish Total Qtr


Float
1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Phase 2 - Albawani GAQ Building 331 03-Mar-24 28-Jan-25 0 28-Jan-25, Phase 2 - Albawani GAQ Buil

Project Milestone 331 03-Mar-24 28-Jan-25 0 28-Jan-25, Project Milestone

MS-0010 Project Start Date 0 03-Mar-24 0 Project Start Date, 03-Mar-24


MS-0040 Receving Signed Contract 13 03-Mar-24 15-Mar-24 6 Receving Signed Contract
MS-0050 Receving Down Payment 13 03-Mar-24 15-Mar-24 6 Receving Down Payment
MS-0030 Project Completion Date 0 28-Jan-25 0 Project Completion Date,
Engineering & Procurement 95 16-Mar-24 18-Jun-24 6 18-Jun-24, Engineering & Procurement
Proc-0023 Procurement (Mill ) By IBSF 95 16-Mar-24 18-Jun-24 6 Procurement (Mill ) By IBSF
Zones 331 03-Mar-24 28-Jan-25 0 28-Jan-25, Zones

Zone No. 01 182 03-Mar-24 01-Sep-24 0 01-Sep-24, Zone No. 01


Engineering 106 03-Mar-24 16-Jun-24 15 16-Jun-24, Engineering
ENG-552 Prepare and Submit Approval Drawings 49 03-Mar-24 20-Apr-24 0 Prepare and Submit Approval Drawings
ENG-562 Review & Approval of the Approval Drawings by Customer 21 21-Apr-24 11-May-24 0 Review & Approval of the Approval Drawings by Customer
ENG-572 Prepare and Release of Fabrication Drawings 36 12-May-24 16-Jun-24 15 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 72 19-May-24 30-Jul-24 30 30-Jul-24, Fabrication and Delivery
Fabrication 15 19-May-24 05-Jun-24 12 05-Jun-24, Fabrication
FAB-440 Fabrication of Structural Steel, Delivery to Site 15 19-May-24 05-Jun-24 12 Fabrication of Structural Steel, Delivery to Site
Delivery 58 02-Jun-24 30-Jul-24 30 30-Jul-24, Delivery
DEL-1430 Delivery Skeleton steel to Site By IBSF - Zone 1 14 02-Jun-24 16-Jun-24 53 Delivery Skeleton steel to Site By IBSF - Zone 1
DEL-1440 Delivery Wall Sandwich Panel to Site By IBSF - Zone 1 21 09-Jul-24 30-Jul-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 1
Construction 71 05-Jun-24 01-Sep-24 0 01-Sep-24, Construction
CON-170 Erection at Site By IBSF Skeleton steel - Zone 1 32 05-Jun-24 17-Jul-24 14 Erection at Site By IBSF Skeleton steel - Zone 1
CON-180 Erection at Site By IBSF Wall Sandwich Panel - Zone 1 24 04-Aug-24 01-Sep-24 0 Erection at Site By IBSF Wall Sandwich Panel - Zone 1
Zone No. 02. 209 03-Mar-24 28-Sep-24 0 28-Sep-24, Zone No. 02.
Engineering 114 03-Mar-24 24-Jun-24 0 24-Jun-24, Engineering
ENG-1692 Prepare and Submit Approval Drawings 49 03-Mar-24 20-Apr-24 10 Prepare and Submit Approval Drawings
ENG-1702 Review & Approval of the Approval Drawings by Customer 21 01-May-24 21-May-24 0 Review & Approval of the Approval Drawings by Customer
ENG-1712 Prepare and Release of Fabrication Drawings 34 22-May-24 24-Jun-24 0 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 57 24-Jun-24 20-Aug-24 35 20-Aug-24, Fabrication and Delivery
Fabrication 15 24-Jun-24 11-Jul-24 0 11-Jul-24, Fabrication
FAB-1200 Fabrication of Structural Steel, Delivery to Site 15 24-Jun-24 11-Jul-24 0 Fabrication of Structural Steel, Delivery to Site
Delivery 57 25-Jun-24 20-Aug-24 35 20-Aug-24, Delivery
DEL-1410 Delivery Skeleton steel to Site By IBSF - Zone 2 14 25-Jun-24 08-Jul-24 77 Delivery Skeleton steel to Site By IBSF - Zone 2
DEL-1420 Delivery Wall Sandwich Panel to Site By IBSF - Zone 2 21 30-Jul-24 20-Aug-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 2
Construction 66 11-Jul-24 28-Sep-24 0 28-Sep-24, Construction
CON-550 Erection at Site By IBSF Skeleton steel - Zone 2 32 11-Jul-24 18-Aug-24 0 Erection at Site By IBSF Skeleton steel - Zone 2
CON-660 Erection at Site By IBSF Wall Sandwich Panel - Zone 2 22 01-Sep-24 28-Sep-24 0 Erection at Site By IBSF Wall Sandwich Panel - Zone 2
Zone No. 03 235 03-Mar-24 23-Oct-24 0 23-Oct-24, Zone No. 03
Engineering 135 03-Mar-24 15-Jul-24 18 15-Jul-24, Engineering
ENG-1722 Prepare and Submit Approval Drawings 49 03-Mar-24 20-Apr-24 49 Prepare and Submit Approval Drawings
ENG-1732 Review & Approval of the Approval Drawings by Customer 21 22-May-24 11-Jun-24 18 Review & Approval of the Approval Drawings by Customer
ENG-1742 Prepare and Release of Fabrication Drawings 34 12-Jun-24 15-Jul-24 18 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 57 15-Jul-24 10-Sep-24 30 10-Sep-24, Fabrication and Delivery
Fabrication 15 15-Jul-24 01-Aug-24 16 01-Aug-24, Fabrication
FAB-1220 Fabrication of Structural Steel, Delivery to Site 15 15-Jul-24 01-Aug-24 16 Fabrication of Structural Steel, Delivery to Site
Delivery 57 16-Jul-24 10-Sep-24 30 10-Sep-24, Delivery
DEL-1390 Delivery Skeleton steel to Site By IBSF - Zone 3 14 16-Jul-24 29-Jul-24 70 Delivery Skeleton steel to Site By IBSF - Zone 3
DEL-1400 Delivery Wall Sandwich Panel to Site By IBSF - Zone 3 21 20-Aug-24 10-Sep-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 3
Construction 44 01-Aug-24 23-Oct-24 0 23-Oct-24, Construction
CON-560 Erection at Site By IBSF Skeleton steel - Zone 3 20 01-Aug-24 08-Sep-24 10 Erection at Site By IBSF Skeleton steel - Zone 3
CON-650 Erection at Site By IBSF Wall Sandwich Panel - Zone 3 14 28-Sep-24 23-Oct-24 0 Erection at Site By IBSF Wall Sandwich Panel - Zone 3

Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Phase 2 - Albawani GAQ Building Draft Baseline Schedule 10-Mar-24 12:04
Activity ID Activity Name Original Start Finish Total Qtr
Float
1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Zone No. 04 259 03-Mar-24 16-Nov-24 0 16-Nov-24, Zone No. 04
Engineering 163 03-Mar-24 12-Aug-24 50 12-Aug-24, Engineering
ENG-1752 Prepare and Submit Approval Drawings 49 03-Mar-24 14-May-24 50 Prepare and Submit Approval Drawings
ENG-1762 Review & Approval of the Approval Drawings by Customer 21 12-Jun-24 02-Jul-24 34 Review & Approval of the Approval Drawings by Customer
ENG-1772 Prepare and Release of Fabrication Drawings 35 02-Jul-24 12-Aug-24 42 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 70 23-Jul-24 01-Oct-24 30 01-Oct-24, Fabrication and Delivery
Fabrication 15 23-Jul-24 10-Aug-24 41 10-Aug-24, Fabrication
FAB-1240 Fabrication of Structural Steel, Delivery to Site 15 23-Jul-24 10-Aug-24 41 Fabrication of Structural Steel, Delivery to Site
Delivery 64 30-Jul-24 01-Oct-24 30 01-Oct-24, Delivery
DEL-1370 Delivery Skeleton steel to Site By IBSF - Zone 4 14 30-Jul-24 12-Aug-24 70 Delivery Skeleton steel to Site By IBSF - Zone 4
DEL-1380 Delivery Wall Sandwich Panel to Site By IBSF - Zone 4 21 10-Sep-24 01-Oct-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 4
Construction 50 13-Aug-24 16-Nov-24 0 16-Nov-24, Construction
CON-570 Erection at Site By IBSF Skeleton steel - Zone 4 20 13-Aug-24 19-Sep-24 24 Erection at Site By IBSF Skeleton steel - Zone 4
CON-640 Erection at Site By IBSF Wall Sandwich Panel - Zone 4 13 23-Oct-24 16-Nov-24 0 Erection at Site By IBSF Wall Sandwich Panel - Zone 4
Zone No. 05 282 03-Mar-24 09-Dec-24 0 09-Dec-24, Zone No. 05
Engineering 178 03-Mar-24 27-Aug-24 35 27-Aug-24, Engineering
ENG-1782 Prepare and Submit Approval Drawings 49 03-Mar-24 14-May-24 63 Prepare and Submit Approval Drawings
ENG-1792 Review & Approval of the Approval Drawings by Customer 21 27-Jun-24 17-Jul-24 34 Review & Approval of the Approval Drawings by Customer
ENG-1802 Prepare and Release of Fabrication Drawings 35 17-Jul-24 27-Aug-24 29 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 71 13-Aug-24 22-Oct-24 30 22-Oct-24, Fabrication and Delivery
Fabrication 7 27-Aug-24 04-Sep-24 29 04-Sep-24, Fabrication
FAB-1260 Fabrication of Structural Steel, Delivery to Site 7 27-Aug-24 04-Sep-24 29 Fabrication of Structural Steel, Delivery to Site
Delivery 71 13-Aug-24 22-Oct-24 30 22-Oct-24, Delivery
DEL-1350 Delivery Skeleton steel to Site By IBSF - Zone 5 14 13-Aug-24 26-Aug-24 70 Delivery Skeleton steel to Site By IBSF - Zone 5
DEL-1360 Delivery Wall Sandwich Panel to Site By IBSF - Zone 5 21 01-Oct-24 22-Oct-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 5
Construction 81 04-Sep-24 09-Dec-24 0 09-Dec-24, Construction
CON-580 Erection at Site By IBSF Skeleton steel - Zone 5 32 04-Sep-24 13-Oct-24 29 Erection at Site By IBSF Skeleton steel - Zone 5
CON-630 Erection at Site By IBSF Wall Sandwich Panel - Zone 5 20 16-Nov-24 09-Dec-24 0 Erection at Site By IBSF Wall Sandwich Panel - Zone 5
Zone No. 06 305 03-Mar-24 01-Jan-25 0 01-Jan-25, Zone No. 06
Engineering 172 03-Mar-24 21-Aug-24 54 21-Aug-24, Engineering
ENG-1812 Prepare and Submit Approval Drawings 49 03-Mar-24 20-Apr-24 121 Prepare and Submit Approval Drawings
ENG-1822 Review & Approval of the Approval Drawings by Customer 21 21-Apr-24 11-May-24 121 Review & Approval of the Approval Drawings by Customer
ENG-1832 Prepare and Release of Fabrication Drawings 35 18-Jul-24 21-Aug-24 54 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 69 04-Sep-24 12-Nov-24 30 12-Nov-24, Fabrication and Delivery
Fabrication 15 04-Sep-24 22-Sep-24 50 22-Sep-24, Fabrication
FAB-1280 Fabrication of Structural Steel, Delivery to Site 15 04-Sep-24 22-Sep-24 50 Fabrication of Structural Steel, Delivery to Site
Delivery 69 05-Sep-24 12-Nov-24 30 12-Nov-24, Delivery
DEL-1330 Delivery Skeleton steel to Site By IBSF - Zone 6 14 05-Sep-24 18-Sep-24 61 Delivery Skeleton steel to Site By IBSF - Zone 6
DEL-1340 Delivery Wall Sandwich Panel to Site By IBSF - Zone 6 21 22-Oct-24 12-Nov-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 6
Construction 86 22-Sep-24 01-Jan-25 0 01-Jan-25, Construction
CON-590 Erection at Site By IBSF Skeleton steel - Zone 6 32 22-Sep-24 30-Oct-24 51 Erection at Site By IBSF Skeleton steel - Zone 6
CON-620 Erection at Site By IBSF Wall Sandwich Panel - - Zone 6 20 09-Dec-24 01-Jan-25 0 Erection at Site By IBSF Wall Sandwich Panel - -
Zone No. 07 331 03-Mar-24 28-Jan-25 0 28-Jan-25, Zone No. 07
Engineering 214 03-Mar-24 02-Oct-24 53 02-Oct-24, Engineering
ENG-1842 Prepare and Submit Approval Drawings 49 03-Mar-24 14-May-24 109 Prepare and Submit Approval Drawings
ENG-1852 Review & Approval of the Approval Drawings by Customer 21 14-May-24 03-Jun-24 133 Review & Approval of the Approval Drawings by Customer
ENG-1862 Prepare and Release of Fabrication Drawings 35 21-Aug-24 02-Oct-24 45 Prepare and Release of Fabrication Drawings
Fabrication and Delivery 76 19-Sep-24 03-Dec-24 30 03-Dec-24, Fabrication and Delivery
Fabrication 15 02-Oct-24 20-Oct-24 45 20-Oct-24, Fabrication
FAB-1300 Fabrication of Structural Steel 15 02-Oct-24 20-Oct-24 45 Fabrication of Structural Steel
Delivery 76 19-Sep-24 03-Dec-24 30 03-Dec-24, Delivery
DEL-1310 Delivery Skeleton steel to Site By IBSF - Zone 7 14 19-Sep-24 02-Oct-24 61 Delivery Skeleton steel to Site By IBSF - Zone 7
DEL-1320 Delivery Wall Sandwich Panel to Site By IBSF - Zone 7 21 12-Nov-24 03-Dec-24 30 Delivery Wall Sandwich Panel to Site By IBSF - Zone 7

Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Phase 2 - Albawani GAQ Building Draft Baseline Schedule 10-Mar-24 12:04
Activity ID Activity Name Original Start Finish Total Qtr
Float
1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Construction 94 09-Oct-24 28-Jan-25 0 28-Jan-25, Construction
CON-600 Erection at Site By IBSF Skeleton steel - Zone 7 32 09-Oct-24 16-Nov-24 46 Erection at Site By IBSF Skeleton steel - Zone 7
CON-610 Erection at Site By IBSF Wall Sandwich Panel - Zone 7 22 01-Jan-25 28-Jan-25 0 Erection at Site By IBSF Wall Sandwich

Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation