SUPPLY AND INSTALLATION OF 01 HEAVY FUEL Classic Schedule Layout 17-Jan-24 16:07

TANK AT TOBRUK REFINERY

Activity ID Activity Name Original Start Finish Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
435 30-Oct-25, Q-43 PROJECT SUPPLY A
Q-43 PROJECT SUPPLY AND INSTALLATION OF 01 NEW HEAVY FUEL OIL TANK AT01-Mar-24
TOBRUK30-Oct-25
REFINERY
Q-43 PROJECT.2 PROJECT MILESTONES 435 01-Mar-24 30-Oct-25 30-Oct-25, Q-43 PROJECT.2 PROJEC

A1180 Project Start 0 01-Mar-24 Project Start, 01-Mar-24


A1190 Project Finish 0 30-Oct-25 Project Finish,
180
Q-43 PROJECT.1 PROJECT MANAGEMENT, HSSE , PROCUREMENT, ENGINEERING 01-Mar-24 07-Nov-24 07-Nov-24, Q-43 PROJECT.1 PROJECT MANAGEMENT, HSSE , PROCUREMENT, ENGINEERING

A1000 Site Visit/Site Survey/Collect data/Geotechnical Report 25 01-Mar-24 04-Apr-24 Site Visit/Site Survey/Collect data/Geotechnical Report
A1001 Detailed Engineering 97 22-Mar-24 05-Aug-24 Detailed Engineering
A1002 Procurement 150 12-Apr-24 07-Nov-24 Procurement
A1010 Project Execution Plan and Project Management 30 12-Apr-24 23-May-24 Project Execution Plan and Project Management
A1020 Project Communication Plan 30 12-Apr-24 23-May-24 Project Communication Plan
A1030 Project HSSE Plan & Case Studies 30 12-Apr-24 23-May-24 Project HSSE Plan & Case Studies
A1040 Project Method Statement Report 30 12-Apr-24 23-May-24 Project Method Statement Report

Q-43 PROJECT.9 150.000 BBL TANK FABRICATION WORK (Fabrication in workshop75)-122-Mar-24 04-Jul-24 04-Jul-24, Q-43 PROJECT.9 150.000 BBL TANK FABRICATION WORK (Fabrication in workshop )-1

A1200 Tank Prefabrication 75 22-Mar-24 04-Jul-24 Tank Prefabrication

Q-43 PROJECT.3 CONSTRUCTION WORKS 420 22-Mar-24 30-Oct-25 30-Oct-25, Q-43 PROJECT.3 CONSTR

Q-43 PROJECT.3.1 FOUNDATION WORKS 80 22-Mar-24 11-Jul-24 11-Jul-24, Q-43 PROJECT.3.1 FOUNDATION WORKS
A1069 Site installation 30 22-Mar-24 02-May-24 Site installation
A1070 Excavation Works 10 12-Apr-24 25-Apr-24 Excavation Works
A1080 Filling and compaction 20 26-Apr-24 23-May-24 Filling and compaction
A1090 Tank foundation works 35 24-May-24 11-Jul-24 Tank foundation works
Q-43 PROJECT.3.2 ERECTION OF 150.000 BBL TANK 230 12-Jul-24 29-May-25 29-May-25, Q-43 PROJECT.3.2 ERECTION OF 150.000 BBL TANK
A1100 Tank installation works 220 12-Jul-24 15-May-25 Tank installation works
A1210 NDT inspection 200 23-Aug-24 29-May-25 NDT inspection
Q-43 PROJECT.3.3 TANK HYDROTEST 30 16-May-25 26-Jun-25 26-Jun-25, Q-43 PROJECT.3.3 TANK HYDROTEST
A1110 Hydrotest works 30 16-May-25 26-Jun-25 Hydrotest works
Q-43 PROJECT.3.4 TANK COATING 45 27-Jun-25 28-Aug-25 28-Aug-25, Q-43 PROJECT.3.4 TANK COATING

A1120 Coating works 45 27-Jun-25 28-Aug-25 Coating works


Q-43 PROJECT.3.5 MECHANICAL/PIPING TIE-INS 30 11-Jul-25 21-Aug-25 21-Aug-25, Q-43 PROJECT.3.5 MECHANICAL/PIPING TIE-INS
A1130 Installation of Pipe supports/valves/Tie-ins . 30 11-Jul-25 21-Aug-25 Installation of Pipe supports/valves/Tie-ins .
Q-43 PROJECT.3.6 FIRE FIGHTING SYSTEM OF THE TANKS 30 22-Aug-25 02-Oct-25 02-Oct-25, Q-43 PROJECT.3.6 FIRE FIGHTING S
A1140 Firefighting works/Foam system/Cooling system etc. 30 22-Aug-25 02-Oct-25 Firefighting works/Foam system/Cooling system etc.
Q-43 PROJECT.3.7 ELECTRICAL & INSTRUMENTATION FOR BOTH TANKS 60 11-Jul-25 02-Oct-25 02-Oct-25, Q-43 PROJECT.3.7 ELECTRICAL & IN
A1150 Installation of Cable tray, Hook-up etc. 60 11-Jul-25 02-Oct-25 Installation of Cable tray, Hook-up etc.
Q-43 PROJECT.3.8 COMISSIONING & START-UP 20 03-Oct-25 30-Oct-25 30-Oct-25, Q-43 PROJECT.3.8 COMIS
A1160 Comissioning 10 03-Oct-25 16-Oct-25 Comissioning
A1170 Start-up 10 17-Oct-25 30-Oct-25 Start-up

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 1
17/01/2024 01 I.E