AMK2 Levels 2 and 4 Interior Fit Out Master Programme

R6 updated on 19/12/2023
Months Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Weeks 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5
Stage/Phase Description Duration (Wks) Start Finish

1 Design 19
Project Kick Off 1-Dec-23 1-Dec-23
Appointment of Architect 8-Dec-23 8-Dec-23
Appointment of other Consultants (QS, GC&MEP, T&C) 3 8-Dec-23 29-Dec-23
Test Fit & Review 1 11-Dec-23 18-Dec-23

Concept Design 3 18-Dec-23 8-Jan-24 Apple Target Sign off on CD


Apple Review RE&D + BU W2 Jan 2024
Schematic Design 4 15-Jan-24 12-Feb-24 Apple Target Sign off on SD
Apple Review RE&D + BU W2 Feb 24
Detailed Design 3 12-Feb-24 4-Mar-24 Apple Target Sign off on DD
Apple Review RE&D + BU W1 Mar 2024
Development of
Cost Control & CAR Cost Plan
Cost Plan Finalisation 3 12-Feb-24 4-Mar-24 Target Final Cost Plan For Approval
Main CAR Prep 2 4-Mar-24 18-Mar-24
Main CAR Approval 4 18-Mar-24 15-Apr-24 Approval for Main CAR
Sufficient detail for
Tender and Construction Documentation 3 4-Mar-24 25-Mar-24 SCDF BP Submission
Target NOA from SCDF
Authority Submission (Kenyon) 6 26-Feb-24 8-Apr-24

2 Procurement 28
2A Design Services Procurement
Tender Preparation 2 4-Dec-23 18-Dec-23
Calling Tender 1 18-Dec-23 25-Dec-23 Award of Consultancy Contracts by Dec 2023
Tender Evaluation, Approval & Award 1 25-Dec-23 1-Jan-24

2B Apple Direct Procurement Items

2B-1 Main Contractor Tender Package 4 19-Feb-24 18-Mar-24


Apple Procurement Review 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation 1 1-Apr-24 8-Apr-24 Award of Work Package
Approval & Award of PO 1 8-Apr-24 15-Apr-24

2B-2 FFE / System Furniture


System Partition / Fabric Soft Cell Ceiling Panels / Carpet Tiles
Tender Preparation 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation, Approval & Award 1 1-Apr-24 8-Apr-24
Delivery Lead Time 12 8-Apr-24 1-Jul-24

Workstations / Manager Desks / Conference Tables / Loose Furniture


Tender Preparation 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation, Approval & Award 1 1-Apr-24 8-Apr-24
Delivery Lead Time 12 8-Apr-24 1-Jul-24

2C Long Lead Equipment & Items


IS&T Equipment Lead Time 14 12-Feb-24 20-May-24
WAP & Server Installation & Cabling 7 17-Jun-24 5-Aug-24

AV Equipment Lead Time (procured by IS&T) 8 12-Feb-24 8-Apr-24


AV Equipment Installation (by AV Vendor) 3 1-Jul-24 22-Jul-24 Installation of AV equipment + T&C

GS Equipment Lead Time 14 12-Feb-24 20-May-24 WAP Instllation to


Card Reader & CCTV & Server Installation & Cabling 6 24-Jun-24 5-Aug-24 follow ceiling closure
Handover of LAN room to GS & IST
3A Construction 17 for rack install
Early Works (such as demolition, 6
Mobilisation 2 8-Apr-24 22-Apr-24 RI Inspection
Fit Out Works 14 15-Apr-24 22-Jul-24 FSC Approval
RI Inspection and FSC Approval 2 22-Jul-24 5-Aug-24
Stage 1 Sever Room Inspections (Room Readiness) 17-Jun-24 Stage 1 Server Room Handover
Stage 2 Sever Room Inspections (Final Cleaning & Server Rack Install) 15-Jul-24 Stage 2 Server Room Handover
RI Inspection
L4 Main Fit Out Works 16 15-Apr-24 5-Aug-24 FSC Approval
RI Inspection and FSC Approval 2 5-Aug-24 19-Aug-24
Stage 1 Sever Room Inspections (Room Readiness) 17-Jun-24 Stage 1 Server Room Handover
Stage 2 Sever Room Inspections (Final Cleaning & Server Rack Install) 15-Jul-24 Stage 2 Server Room Handover

3B Testing & Commisioning, Tests & Defects Rectification 7


T&C 2 22-Jul-24 5-Aug-24
Tests (IAQ & Portable Water) 2 22-Jul-24 5-Aug-24
Level 2
Early User Inspections 4 8-Jul-24 5-Aug-24
Defects Retifications 4 15-Jul-24 12-Aug-24 Major Defects Rectification

Additional 2 weeks for L4 T&C and Defects Retifications 2


4 Completion, Handover & Closeout 5 `
L2 Final Handover Inspection 2 22-Jul-24 5-Aug-24 L2 Final Handover
L2 Handover 1 5-Aug-24 12-Aug-24
L4 Final Handover Inspection 2 5-Aug-24 19-Aug-24 L4 Final Handover
L4 Handover 1 19-Aug-24 26-Aug-24