26-Mar-24 15-May-24 19-May-24 Utilities tie-in date from Kewaunee (RO+CA+Chiller+HW+SG) 7-Apr-24
7-Apr-24 17-Apr-24 17-Apr-24 17-Apr-24
17-Apr-24
17-Apr-24 30-May-24 Remarks
Core cutting has dependency on builder- Applicable to all below
points Utilities tie in date are not applicable for the HWG and SB- as procurement team needs to share the HWG and SB equipment and piping work completion date - This is applicable to all below points- Need R&D team support on this
Ice cream m/c skid power source to be confrimed by R&D team,
therefater 15 days are required by Kewaunee to arrange matyerial for termination
2nos m/c (noodle and snacks line) are supposed to be received by
10th June and 10th Aug'24 . After that 15 days required to complete the termination
Planetary mixture and frier are supposed to be received 10th Apr
and 10th May 24. S. No Areas
1 CIC area - Step down tiles in home care
2 Power Augmentation
3 Basement storage work
4 3rd floor terrace
5 HWG and SB equipment and pipeline commissioning Readiness date
4-Apr-24
30-Apr-24
21-Mar-24
30-Apr-24 15-May-24 Remarks
Kewaunee will not be having permission to enter inside the home
care area as CIC team is arranginmg training session. This training session will be completed by 27th Mar'24
This will have dependency on the
SCO-Government liasioning Procurement team- DG and Transformer supply-8-12 weeks Developer - For concurrence for the design and panel modification. This has to be routed through R&D team
Design finalization date is mentioned. After design finalization R&D
team needs to take confirmation from developer for the storage execution work. After developer approval this will take 60 day for the execution considering the delivery of clean room panels