S.

No Pilot plant name Core cutting dates


by Kewuanee
1 Personal care 17-Mar-24

2 Home care 17-Mar-24


3 Candy 17-Mar-24
4 Beverages 17-Mar-24
5 Ice cream & chocolate 17-Mar-24

6 Processed foods- Biscuits &snacks 17-Mar-24

7 Packaging room and slicer-peeler 17-Mar-24


8 Pantry NA
Trenches completion Equipment installation Power supply date
date from R&D team by Kewaunee
21-Mar-24 23-Mar-24 24-Mar-24

21-Mar-24 23-Mar-24 24-Mar-24


26-Mar-24 2-Apr-24 3-Apr-24
26-Mar-24 2-Apr-24 3-Apr-24
26-Mar-24 2-Apr-24 6-Apr-24

26-Mar-24 2-Apr-24 10-Apr-24

26-Mar-24 2-Apr-24 12-Apr-24


26-Mar-24 15-May-24 19-May-24
Utilities tie-in date from Kewaunee
(RO+CA+Chiller+HW+SG)
7-Apr-24

7-Apr-24
17-Apr-24
17-Apr-24
17-Apr-24

17-Apr-24

17-Apr-24
30-May-24
Remarks

Core cutting has dependency on builder- Applicable to all below


points
Utilities tie in date are not applicable for the HWG and SB- as
procurement team needs to share the HWG and SB equipment and
piping work completion date - This is applicable to all below points-
Need R&D team support on this

Ice cream m/c skid power source to be confrimed by R&D team,


therefater 15 days are required by Kewaunee to arrange matyerial
for termination

2nos m/c (noodle and snacks line) are supposed to be received by


10th June and 10th Aug'24 . After that 15 days required to complete
the termination

Planetary mixture and frier are supposed to be received 10th Apr


and 10th May 24.
S. No Areas

1 CIC area - Step down tiles in home care

2 Power Augmentation

3 Basement storage work

4 3rd floor terrace


5 HWG and SB equipment and pipeline
commissioning
Readiness date

4-Apr-24

30-Apr-24

21-Mar-24

30-Apr-24
15-May-24
Remarks

Kewaunee will not be having permission to enter inside the home


care area as CIC team is arranginmg training session. This training
session will be completed by 27th Mar'24

This will have dependency on the


SCO-Government liasioning
Procurement team- DG and Transformer supply-8-12 weeks
Developer - For concurrence for the design and panel modification.
This has to be routed through R&D team

Design finalization date is mentioned. After design finalization R&D


team needs to take confirmation from developer for the storage
execution work.
After developer approval this will take 60 day for the execution
considering the delivery of clean room panels

Need support from R&D team for the IT work


Consultant PO/WO is pending to be released