Activity Name Duration Start Finish

Submittals General, Material & Procurement


Civil
Pavement 365
Aggregates Source - Quality check 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
CTB Mix Design 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
PCC Mix Design 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
Blinding Concrete Mix Design 22
Purchase and Procurement Process 6 1-May-15 14-May-15
Structural Concrete Mix Design 22
Purchase and Procurement Process 6 1-May-15 14-May-15
Plain Dowel 100
Purchase and Procurement Process 6 9-Mar-15 23-Mar-15
JOINT SEALANT FOR CONCRETE & ASPHALT PAVEMENT 96
Purchase and Procurement Process 6 28-Feb-15 13-Mar-15
Subbase 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
CABC 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
Asphalt Base Course Mix Design 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
Bitumen 60/70 22
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15
Tack Coat 19
Purchase and Procurement Process 2 11-Apr-15 16-Apr-15
Asphalt Crack Relief Layer Mix Design 22
Purchase and Procurement Process 6 5-May-15 19-May-15
Prime Coat 19
Purchase and Procurement Process 2 23-May-15 29-May-15
Asphalt Surface Course Mix Design 22
Purchase and Procurement Process 6 15-May-15 29-May-15
Pavement Sealant 22
Purchase and Procurement Process 6 20-May-15 3-Jun-15
Curing Compound 29
Purchase and Procurement Process 12 4-May-15 3-Jun-15
Joint Filler Boards 29
Purchase and Procurement Process 12 9-May-15 8-Jun-15
Pavement marking 35
Purchase and Procurement Process 18 9-Jul-16 23-Aug-16
Fencing 37
Purchase and Procurement Process 20 26-Nov-16 15-Jan-17
Structure 242
Waterproofing 53
Purchase and Procurement Process 36 14-Jun-15 11-Sep-15
Damproofing 124
Purchase and Procurement Process 36 14-Jun-15 11-Sep-15
Steel Reinforcement 130
Purchase and Procurement Process 36 20-Nov-14 11-Sep-15
Sealants 35
Purchase and Procurement Process 18 29-Jul-15 11-Sep-15
MASTERFLEX 477 ELASTOMERIC POLYURETHANE JOINT SEALANT 139
Purchase and Procurement Process 18 10-Feb-14 26-Mr-14
Storm Drainage 132
RC Pipes 65
Purchase and Procurement Process 48 1-Nov-14 11-Mar-15
Manholes Covers & Frames / Gratings 129
Purchase and Procurement Process 48 22-Sep-14 27-Jun-15
GRP - Slot Drains 93
Purchase and Procurement Process 48 1-Sep-14 23-Mar-15
Architechural 89
CMU 89
Purchase and Procurement Process 72 3-Aug-15 29-Jan-16
Paint 53
Purchase and Procurement Process 36 3-Aug-15 31-Oct-15
Doors 89
Purchase and Procurement Process 72 3-Aug-15 29-Jan-16
Windows 89
Purchase and Procurement Process 72 3-Aug-15 29-Jan-16
Flooring 89
Purchase and Procurement Process 72 3-Aug-15 29-Jan-16
Mechanical
FHS - (Pressure Transmitter) 89
Purchase and Procurement Process 72 11-Apr-15 7-Oct-15
FHS - (Welding Material) 149
Purchase and Procurement Process 24 22-Jun-14 13-Apr-15
FHS - (Coating and Wrapping material) 153
Purchase and Procurement Process 72 22-Jun-14 28-May-15
FHS - (Temperature Transmitter) 89
Purchase and Procurement Process 72 11-Apr-15 7-Oct-15
FHS - Pipes Fittings 97
Purchase and Procurement Process 48 28-Jul-14 26-Mar-15
FHS - Pipes 97
Purchase and Procurement Process 48 28-Jul-14 26-Mar-15
FHS - Pits 153
Purchase and Procurement Process 72 22-Jun-14 28-May-15
FHS - High Points & Low Points Assembly 185
Purchase and Procurement Process 72 28-Feb-15 26-Aug-15
FHS - Hydrant Pit Valves Assembly 155
Purchase and Procurement Process 72 22-Jun-14 13-Jun-15
FHS - DBB Valves (Double Block & Bleed Valves) 141
Purchase and Procurement Process 82 26-Jul-14 29-May-15
FHS - Shock Absorber Accumulator 89
Purchase and Procurement Process 72 11-Apr-15 7-Oct-15
FHS - Pressure Reducing Valves 89
Purchase and Procurement Process 72 11-Apr-15 7-Oct-15
FHS - Pressure Releif Valves 53
Purchase and Procurement Process 36 11-Apr-15 9-Jul-15
FHS - Hydrocarbon Detector 89
Purchase and Procurement Process 72 11-Apr-15 7-Oct-15
FHS - Cathodic Protection 65
Purchase and Procurement Process 48 1-May-15 28-Aug-15
HVAC - Split / AHU's / FCU 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
PVC Pipes and Fittings 73
Purchase and Procurement Process 8 28-Aug-15 17-Sep-15
GRP Pipes and Fittings 29
Purchase and Procurement Process 12 18-Aug-15 17-Sep-15
Pre-insulated Pipes and Fittings 53
Purchase and Procurement Process 36 19-Jun-15 17-Sep-15
Insulation material 41
Purchase and Procurement Process 24 19-Jul-15 17-Sep-15
Pumps 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Plumbing Accessories 29
Purchase and Procurement Process 12 18-Aug-15 17-Sep-15
Electrical and Communication
Medium Voltage Cables 53
Purchase and Procurement Process 36 1-May-15 29-Jul-15
Substations 65
Purchase and Procurement Process 48 1-May-15 28-Aug-15
Transformers 65
Purchase and Procurement Process 48 1-May-15 28-Aug-15
Airfield Ground Lighting / Guidance Signs/AFL cable 77
Purchase and Procurement Process 60 1-May-15 27-Sep-15
400 Hz Converters/PITS/Cables 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
ALCMS 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Flood Lights 65
Purchase and Procurement Process 48 1-May-15 28-Aug-15
Switch Boards 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Panel boards 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Automatic transfer Switch 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
MCC's 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
LV Generator 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
MV Switch Gears 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Lighting Fixtures 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
Receptacles / Switches 89
Purchase and Procurement Process 72 1-May-15 27-Oct-15
LV Cables 53
Purchase and Procurement Process 36 1-May-15 29-Jul-15
Grounding Pits and accessories 53
Purchase and Procurement Process 36 1-May-15 29-Jul-15
PVC Conduits 33
Purchase and Procurement Process 16 1-May-15 9-Jun-15
Rigid Conduits 33
Purchase and Procurement Process 16 1-May-15 9-Jun-15
Special Systems 78
Summary Of Special System (Submittals & Procurement ) Part 78
(VDGS) Units 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
I.P Telephony sets 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
PAS Equipment 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
(FAS) Units 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
FIDS Work station 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
Digital Control and Monitoring Units & Cabling 65
Purchase and Procurement Process 48 3-Aug-15 30-Nov-15
I/O BACKBONE FIBER OPTIC CABLING 65
Purchase and Procurement Process 48 6-Aug-15 4-Dec-15
AVIATION FUEL MONITORING & CONTROL SYSTEM Units 65
Purchase and Procurement Process 48 16-Aug-15 14-Dec-15
(UPS) 65
Purchase and Procurement Process 48 26-Aug-15 24-Dec-15
BUILDING MANAGEMENT SYSTEM Units & Cabling 65
Purchase and Procurement Process 48 5-Sep-15 3-Jan-16