Duration

Description start finish Duration


Delay
A Design Drawing plan/contract 9-Aug-23 9-Aug-23 0
15
actual 9-Aug-23 24-Aug-23 15
B Shopdrawing plan/contract 16-Sep-23 15-Oct-23 29
72
actual 16-Sep-23 26-Dec-23 101
C Fabrication plan/contract 22-Sep-23 10-Nov-23 49
80
actual 10-Oct-23 16-Feb-24 129
D Painting plan/contract 10-Oct-23 20-Nov-23 41
78
actual 22-Oct-23 18-Feb-24 119
E Delivery plan/contract 6-Nov-23 26-Nov-23 20
78
actual 13-Nov-23 19-Feb-24 98
2023 2024
August Sep Oct Nov Dec Jan Feb
W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29

Contract duration

EXTENTION OF TIME
(11 WEEKS)

Feedback RFI Delay 11 Days (RFI-016)


Actual duration

Received final Design Feedback RFI Delay 17 Days Feedback Shopdrawing Design change (Modification
(RFI-042) Delay 14 Days (SS.39-44) Column ) 37 days