Initial JDL

Week No. 38
DAILY ACTIVITY REPORT Date Cut-In 18-Sep-23

WEEK 38 - 2023 Date Cut-Off 24-Sep-23


Date Prepared 23-Sep-23
ENGINEERING DEPARTMENT JHUN MICHAEL D. LOCUS Checked by ASS
CAVITE PHILIPPINES OFFICE PROJECT ENGINEER Submitted To RDE

Date Project Specific Job Worked Time Notes & Remarks

18-Sep-23 22024 PM4 Building Equipment Layout with Load update 8:00 AM - 5:00 PM Finished

19-Sep-23 22024 PM4 Building Equipment Layout with Load Finalizing 8:00 AM - 5:00 PM Finished

20-Sep-23 22024 PM4 Building Equipment Foundation Civil Guide Layout Update 8:00 AM - 5:00 PM Finished

21-Sep-23 22024 PM4 Building Equipment Foundation Civil Guide Layout Finalizing 8:00 AM - 5:00 PM Finished

22-Sep-23 22024 PM4 Stock Prep Sewer Layout Update 8:00 AM - 5:00 PM Continue

- NBI claiming 1:00 AM - 2:00 PM Done

23-Sep-23 22024 PM4 Stock Prep. Sewer Layout Finalizing 8:00 AM - 5:00 PM Finished

PM4 Stock Prep. Floor Slab Hole

24-Sep-23 - Rest Day

Prepared By: Jhun Michael D. Locus Submitted To: PPI Office


Date: September 23, 2023 Date: September 23, 2023

Evaluation and Remarks:


Checked By: Arnold S. Sapanta 1-
Date: September 23, 2023 2-
3-

Week 38-2023 JDL Activity Report .xlsx Page 1 of 1