Substructure Acceleration: Additional Team no.

Background of Submission

1. Baseline Schedule
The contractual baseline schedule planned completion, for the substructure subcontract
scope of work is 23 months. An average productivity of 4.35% is required with 4 teams executing
simultaneously at different work fronts for Balagtas, Guiguinto, Malolos GBA and in Malolos Old
Station to complete the works. Substructure execution commences on the completion of Bored piling
works for each scheduled pier/substructure.

Baseline Start Baseline Finish Duration Required


Productivity
September 2019 July 2021 23Mos 4.35%

2. Mobilization of Team 5
Execution of the subcontract: On 16 March 2020 until 31 May 2020, NSCR project was
suspended by the government due to COVID-19 pandemic. Upon partial resumption in June 2020,
substructure works were limited to cleaning of rebars, safekeeping of materials and equipment
preparatory to the full works resumption. At this point, the project milestones dependent on the the
substructure completion, in full or in part, were compromised.

Meetings between SMCC & SCIC: From June 2020, NSCR was allowed to resume works
subject to government imposed restrictions ans protocols amid the COVID 19 pandemic. During the
gradual works resumption and re-mobilization of resources, SMCC and SCIC held series of meetings
and discussions requiring SCIC to provide an additional substructure working team (team no. 5) to
counter the effects of COVID -19 pandemic that severely impacted the continuity and progress of
subcontract works. Manpower and equipment are provided on 1 August 2020 aligned to SMCC
provided revised schedule.

Minutes of Meeting Date Remarks


20200625 June 25,2020 1. SMCC informed SCIC that the revised schedule of
permanent works to consider Guiguinto station.
2. SMCC required SCIC to provide additional Manpower
and equipment (Carpenter & Scaffolder)
20200702 July 02,2020 1. SMCC queried SCIC regarding the status of mobilization
of miners.
20200806 August 06,2020 1.SMCC informed SCIC to start substructure works for
Guiguinto station to be able to reach the project key
dates.
20200820 August 20,2020 1. SMCC informed SCIC about the sent e-mail regarding
the required number of machines needed. SMCC
requested SCIC to mobilize additional tools and machines.

3. September 1, 2021 Updated Schedule


SMCC issued an updated and revised schedule in September 1,2021 reflecting the starting
dates of the piers/substructures construction (inclusive of the variation order quantities). Derivation of
substructure subcontract including variation using the contractual baseline cycle time and
productivity, and following the sequence of piling works, completion of the substructure subcontract
falls on May 16,2023, deploying 5 working teams. The revised schedule required an average monthly
productivity of 2.75%
Bored Pile Finish Date Substructure Finish Date Plan Productivity Critial Path
May 7,2022 May 16,2023 2.75% PR6-33 to PR6-7

3.1 Variation Order


SMCC issued a variation order for the construction of piers at PR5 59-60 Bocaue Area. The
additional substructure works resulted to changes in the sequence of works. The mobilization of Team
No.5 will ensure and sustain the required productivity rates for the timely completion of the works.
The variation order pier construction schedule is listed below.

Pier No. No. Of Piers Plan Start Plan Finish


PR5-59-PR5-60 12 Janaury 2022 June 2022

4. As-Built Schedule (Plan vs Actual)


Based on the comparative schedule showing SMCC’s issued Sept 1 2021 revised schedule, the
actual completion of Substructure works was March 27,2023, therefore, the substructure subcontract
completed 50 days ahead on time against plan/schedule with an actual monthly productivity of 3.10%
vs plan of 2.75%, thereby demonstrating an acceleration of the substructure works scope attributable
to the mobilization of additional team no 5 resources.

Plan Finish Actual Finish Days Ahead Plan Actual


Productivity Productivity
May 16,2023 March 27,2023 50 days 2.75% 3.10%

Pursuant to Sub clause 17.4 of the Subcontract Agreement the Subcontractor is entitled to
claim for acceleration.

We submit herewith the total cost incurred relative to the provision of the additional team no.
5 as part of the acceleration claim.
1. September 1, 2021 Bored Pile Schedule Reflecting Pier Construction Date (Equivalent P6 Schedule in separate
sheet)

Pier No. Bored Pile Finish Date Substructure Starting Date

PR6-7 December 11,2021 April 2023


PR6-8 December 14,2021 April 2023
PR6-9 January 18,2022 April 2023
PR6-10 January 19,2022 March 2023
PR6-11 January 26,2022 February 2023
PR6-12 October 29,2021 February 2023
PR6-13 October 30,2021 February 2023
PR6-14 February 7,2022 February 2023
PR6-15 February 11,2022 February 2023
PR6-16 February 27,2022 January 2023
PR6-17 March 1,2022 January 2023
PR6-18 March 15,2022 January 2023
PR6-19 March 19,2022 December 2022
PR6-20 April 2,2022 December 2022
PR6-21 April 17,2022 December 2022
PR6-22 April 30,2022 November 2022
PR6-23 May 7,2022 November 2022
PR6-28 October 9,2021 September 2022
PR6-29 September 30,2021 September 2022
PR6-30 September 29,2021 September 2022
PR6-31 September 2,2021 August 2022
PR6-32 September 12,2021 August 2022
PR6-33 September 15,2021 August 2022

2. As-Built Schedule (Plan vs Actual)