Professional Documents
Culture Documents
Expansion Project
Monthly
Progress Report
February 2023 (35th Month)
- Data cut-off date: 28 February 2023
Monthly Report (Feb 2023)
Contents
1. Project Summary
1.1 Outline of the Project
1.2 Executive Summary of Status of Works to date
5. Procurement Progress
5.1 Subcontractors Status
6. Construction Progress
9. Financial Status
[Attachment ]
1. Project Summary
Project Brief
Earthwork,
Key Construction Airside &
Elevated Drive Way installation,
Landside Earthwork
Pavement (Asphalt & Concrete)
Special Events
- VVIP Movement in the Site : All type of site works and movement were suspended
Time
No. Date Remarks
Start Finish Hours
1 04 Feb 2020 07 : 00 10 : 30 03 : 30
2 08 Feb 2020 07 : 00 13 : 30 06 : 30
3 25 Feb 2020 23 : 00 03 : 00 04 : 00
VVIP movement
4 07 Mar 2020 14 : 00 17 : 00 03 : 00
5 14 Oct 2020 12 : 25 19 : 30 07: 05
6 27 Oct 2020 07: 00 08 : 30 01: 30
President of the Republic of
7 17 Mar 2021 03 : 00 10 : 00 07 : 00 Maldives’s arrived
President of the Republic of
8 19 Mar 2021 20 : 00 03 : 00 07 : 00 Maldives’s departed
PM of Democratic Socialist
9 19 Mar 2021 05 : 00 12 : 00 07 : 00 Republic Sri Lanka arrived
PM of Democratic Socialist
10 20 Mar 2021 13 : 00 20 : 00 07 : 00 Republic Sri Lanka departed
President of the Republic of Nepal
11 22 Mar 2021 06 : 00 13 : 00 07 : 00 arrived
President of the Republic of Nepal
12 23 Mar 2021 13 : 00 17 : 00 04 : 00 arrived
PM of the Kingdom of Bhutan
13 23 Mar 2021 06 : 00 13 : 00 07 : 00 arrived
Time
No. Date Remarks
Start Finish Hours
PM of the Kingdom of Bhutan
14 25 Mar 2021 04 : 00 11 : 00 07 : 00 departed
PM of People Republic of India
15 26 Mar 2021 06 : 00 13 : 00 07 : 00
arrived
PM of People Republic of India
16 27 Mar 2021 14 : 00 21 : 00 08 : 30
departed
PM of People Republic of
17 17 Sep 2021 07 : 30 10 : 00 02 :30
Bangladesh
President of People Republic of
18 1 Oct 2021 06 : 00 10 : 30 04 :30
Bangladesh departed
Prime Minister of People Republic
19 8 Oct 2021 06 : 00 10 : 30 04 :30
of Bangladesh Arrived
President of People Republic of
20 26 Oct 2021 04 :00 09 :30 05 :30
Bangladesh Arrived
Prime Minister of People Republic
21 31 Oct 2021 06:00 09: 30 03 :30
of Bangladesh departed
Prime Minister of People Republic
22 14 Nov 2021 02:00 03:00 01:00
of Mozambique Transit
Prime Minister of People Republic
23 14 Nov 2021 04:30 08:30 04.00
of Bangladesh Arrived
President of People Republic of
24 15 Dec 2021 07:30 11:30 04:00
India arrived
President of People Republic of
25 17 Dec 2021 09:30 02:00 04:30
India departed
Prime Minister of People Republic
26 22 Dec 2021 08:30 12:30 04:00
of Bangladesh departed
Prime Minister of People Republic
27 27 Dec 2021 13:45 17:45 04:00
of Bangladesh arrived
Prime Minister of People Republic
28 07 Mar.2022 11:30 16:30 05:00
of Bangladesh departed
Prime Minister of People Republic
29 12 Mar.2022 19:30 00:30 05:00
of Bangladesh arrived
Crown Princes of Denmark
30 25 Apr.2022 8:00 11:00 03:00
arrived
Crown Princes of Denmark
31 25 Apr.2022 14:00 17:00 03:00
Departed to Cox’s Bazar
Crown Princes of Denmark
32 27 Apr.2022 21:00 00:00 03:00
Departed
Prime Minister of People Republic
33 5 Sep.2022 8:00 11:00 03:00
of Bangladesh departed
Prime Minister of People Republic
34 8 Sep. 2022 17:00 20:30 03:30
of Bangladesh arrived
Prime Minister of People Republic
35 15 Sep.2022 8:00 12:00 04:00
of Bangladesh departed
Prime Minister of People Republic
36 3 Oct. 2022 18:00 22:00 04:00
of Bangladesh arrived
37 15 Oct. 2022 10:30 15:30 05:00 Brunei Sultan arrived
38 17 Oct. 2022 06:00 10:00 4 Brunei Sultan Departed
President of people republic of
39 29 Oct. 2022 23:30 3:30 4
Bangladesh departed
President of people republic of
40 17 Nov. 2022 6:30 11:30 5
Bangladesh Arrived.
Aviation Dhaka Consortium (ADC) 5 / 146
Monthly Report (Feb 2023)
-
- Government Authority or Other Authority’s visit
① JICA’s visit : 13 Dec. 2020, from 13:30 to 15:00, they stopped by center area of
Terminal 3 accompanied by CAAB Chairman and CE, and the other 3 officials visited
Airside (Area 2-1 and 6-2)
② Army Officers’ visit : 17 Jan. 2021 (12:30~13:30) Army officer (14person) visited the
Site with CAAB Chairman
③ MOCAT Secretary’s visit : 21 Jan. 2021 (12:10 ~ 13:10) MOCAT Secretary visited the
Site with CAAB Chairman
④ Japan Ambassador’s visit : 15 Feb. 2021 (16:00 ~ 17:30)
⑤ Deputy Secretary of IMED – Planning Ministry’s visit : 24 Apr. 2021 (10:30 ~ 12:20)
⑥ Additional Secretary of MOCAT : 28 Apr. 2021 (10:00 ~ 14:20)
⑦ JICA’s visit : 22 Jun. 2021, from 14:00 to 16:00 JICA visited the Site for checking
Safety Management status
⑧ Government VVIP Visit : 5 Jun. 2021, 12:20 p.m, State Minister with 4 nos. of Officials
visited to site.
⑨ Korea Ambassador’s Visit : 30 Aug. 2021 (11:30 ~ 12:30)
⑩ Additional Secretary of MOCAT Visit : 18 Sep.2021 (11:00~ 15:00)
⑪ Deputy Police commissioner (Labor Ministry) : 13 Nov.2021(10:30~12:30)
⑫ Parliamentary Accounts committee visited: 29 Dec.2021 (11:00~14:00)
⑬ Planning Ministry Official visit : 6 Jan. 2022(13:30~16:00)
⑭ Ministry of MOCAT & CAAB Official Visit : 11 Apr.2022(11:00~13:30)
⑮ Additional Secretary of MOCAT & CAAB Official Visit : 21 May 2022 (11:00~16:00)
○
16 PDW Department Official Visit : 27 August 2022(10:30~14:30)
○
17 Ministry of MOCAT & CAAB Official Visit : 12 Sep.2022(10:00~14:30)
○
18 Airport Security System Team (USA) Visit: 25 Oct.2022(10:00~13:00)
ICT 29-1-2024 10-3-2024 -41 Delay in RC Structure work due to 63.82% 56.31% -7.5%
delayed Site Hand-over and COVID-19
ECT 02-1-2024 25-2-2024 -54 Pandemic, IP delay 64.18% 62.69% -1.5%
Delay in Pile & RC Structure work due to
Tunnel 30-4-2023 13-5-2023 -13 delayed Site Hand-over and COVID-19 97.49% 98.31% 0.8%
Pandemic
MLCP 27-3-2024 08-12-2023 110 (ADC's earlier start of works) 75.48% 78.99% 3.5%
Project Overall
Completion 06-4-2024 17-8-2024 -132 64.55% 62.99% -1.6%
(T&C)
(* Details: Please refer to attached updated programme)
▷ Current Main Slippage & Critical Paths in Progress
No. Delayed Works Time Variance Impact Remarks
3 Party’s work - BTCL cable, drainage
rd
EDW South & EDW south & north
1 - 133 days re-location work delay. For mitigating
North work structure
delay, work sequence was changed
Seating Sub-con Engineering ,Mock-up
2 - 100 days Sub-con selection & confirmation delay.
selection installation
CHS installation
3 -87 days CHS installation, T&C Steel Rack installation delay
at ICT, ECT
TE3 VIP & VVIP VIP & VVIP facilities Delay in Subcontractor contracting for
4 -74 days
facilities internal Fit-out works VIP & VVIP facilities
TE3 Center Steel Internal Finishing
5 -62 days Material delivery delay
Structure works & MEP works
TE3 BHS BHS Steel Structure, Encoding Station
6 - 57 days BHS installation, T&C
installation Platform installation delay
TE3 internal Internal Finishing
MEP & Finishing Material Procurement
7 Finishing, MEP - 54days work, MEP 1st & 2nd
delay (IP delay, LC open delay)
work fix
VVIP Terminal Demolition, Utility &
8 - 5 days VVIP Terminal movement delay
Hand-over Drainage works
- 87 ~ - 250 TE3 door installation
9 Door Procurement days Material approval delay
& final finishing works
2.4 Others - Sand delivery (Dec. 2022) / Cumulative total : 92,900 m3 / 4,229,400 m3
2.5 Safety(Incident free) Man-hour (monthly / cumulative) : 2,944,650 / 10,998,080 hours.
99.7%100.0%100.0%
6.0% 97.6%
98.7% 100.0%
96.1%
93.8%
85.0%
4.5% 72.7%
69.0% 70.0%
4.0% 64.3%
59.6%
60.0%
3.5%
54.6%
49.6%
3.0% 50.0%
45.0%
41.9%
2.5% 39.7%
37.8% 40.0%
36.7%
35.2%
33.7%
2.0% 32.3%
31.3%
29.3%
27.4%
30.0%
24.9%
1.5% 22.6%
20.8%
19.1%
20.0%
16.8% 17.5%
1.0% 14.0%
15.1%
12.4%
10.2%
8.5% 10.0%
0.5% 6.7%
5.4%
3.6%
2.3%
0.0% 0.0%
* From Mar. 2022, Planned Progress % based on Revised Baseline Programme was applied
Revised Plan (Monthly) Actual (Monthly) Revised Plan (Cumulative) Actual (Cumulative)
3. Contractor’s Organization PM Control Procure Planning HSE QA/QC Design Civil Building Logistic MEP Admin Sum
Foreigner 10 16 6 2 7 4 14 16 37 0 25 3 140
(as of 28 February 2023) Local 33 10 4 52 28 31 63 107 26 64 20 438
Total 10 49 16 6 59 32 45 79 144 26 89 23 578
Submitted Approved
Trade Total
Last This Last This
Balance Balance
Week Week Week Week
Structure 7 2 2 5 2 2 5
Architecture 112 72 75 37 61 63 49
Mechanical 27 27 27 0 5 7 20
Electrical 42 38 39 3 19 20 22
Civil 83 56 56 27 47 47 36
Electrical
1448 813 1200 248 844 874 574
DB Panel
4.3 Outstanding Submittals (Have not received reply for more than 14 days after submission)
Elapsed
Submissio Workfl Days
Submission No. Subject n Date ow No. (Up to
28-Feb-
2023)
Shop Drawing
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for ICT Ground,
21-0091-02 First, Second, Third Floor CCTV & SACS 23/Jan/23 026987 36
System Layout
ADC-NOCD-RFA-SD-ME- Shop Drawing Submittal for Underground
05/Feb/23 027664 23
22-0274-01 Piping Plan in ECT Out House
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 ELEC
22-0530-01 ROOM MDB PANEL CABLE DROP 07/Feb/23 027743 21
TYPICAL DETAIL
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
22-0496-01 STRUCTURAL STEEL CABLE TRAY 07/Feb/23 027744 21
INSTALLATION TYPICAL DETAIL
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
22-0184-01 GROUND FLOOR COMMS ROOM-1 07/Feb/23 027782 21
LAYOUT PLAN
ADC-NOCD-RFA-SD-ME- Shop Drawing Submittal for Secondary
22-0245-03 Electrical Power & Control for 07/Feb/23 027783 21
Mechanical in GH
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
21-0230-02 GROUND FLOOR POWER TOILET 07/Feb/23 027789 21
PLAN FOR TLG-10 System Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
23-0219-00 GROUND FLOOR POWER TOILET 07/Feb/23 027791 21
PLAN FOR TLG-07 System Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
23-0140-00 GROUND FLOOR LIGHTING
07/Feb/23 027807 21
LAYOUT PLAN TOILET (LTG-10 &
LTG-11)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 OFFICE
22-0542-01 AREA CABLE TRAY & CONDUIT
08/Feb/23 027840 20
TRAY INSTALLATION DETAIL FOR
RACK
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 MAIN
22-0508-01 ROOF CABLE TRAY ROUTE SYSTEM 08/Feb/23 027874 20
(ZONE-C1 GRID 26-34_B13-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 Main
22-0476-02 Roof CABLE TRAY ROUTE SYSTEM 09/Feb/23 027915 19
(ZONE B1 GRID 7-18_B13-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 MAIN
22-0477-01 ROOF CABLE TRAY ROUTE SYSTEM 09/Feb/23 027918 19
(ZONE-C2 GRID 34-45 _ B13-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 FIRST
22-0405-01 FLOOR CABLE TRAY ROUTE 09/Feb/23 027921 19
SYSTEM(ZONE-E GRID 12-40_B5-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 MAIN
22-0454-02 ROOF CABLE TRAY ROUTE SYSTEM 09/Feb/23 027925 19
(ZONE-A GRID 1-7_B16-B5)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 Ground
21-0229-02 Floor Power Toilet Plan for TLG-11 09/Feb/23 027928 19
System Plan
Aviation Dhaka Consortium (ADC) 14 / 146
Monthly Report (Feb 2023)
Elapsed
Submissio Workfl Days
Submission No. Subject n Date ow No. (Up to
28-Feb-
2023)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
22-0220-01 GROUND FLOOR TOILET POWER 09/Feb/23 027967 19
POINTS (TLG-08) System Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
22-0221-02 GROUND FLOOR TOILET POWER 09/Feb/23 027970 19
POINTS (TLG-09) System Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
23-0354-00 GROUND FLOOR TOILET LIGHTING 09/Feb/23 027974 19
System Plan
ADC-NOCD-RFA-SD-ME- Shop Drawing Submittal for Air
23-0312-00 Conditioning and Ventilation System in 11/Feb/23 028010 17
ICT 3F
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 2FP
23-0566-00 CABLE TRAY ROUTE SYSTEM 12/Feb/23 028023 16
(ZONE B GRIDLINE 7-26_B13-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 2FP
23-0567-00 CABLE TRAY ROUTE SYSTEM 12/Feb/23 028024 16
(ZONE C GRIDLINE 26-45_B13-A1)
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
22-0218-01 GROUND FLOOR TOILET POWER 12/Feb/23 028040 16
POINTS (TLG-06) System Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3
21-0138-02 BASEMENT FLOOR CABLE TRAY 12/Feb/23 028058 16
ROUTE SYSTEM
ADC-NOCD-RFA-SD-CC- Shop Drawing of Landside Traffic Sign
13/Feb/23 028086 15
22-0324-02 Plan (Display Information)
ADC-NOCD-RFA-SD-CC- Shop Drawing of Landside Traffic
23-0369-00 13/Feb/23 028090 15
Signboard Frame Details
ADC-NOCD-RFA-SD-ME- Shop Drawing Submittal for Secondary
22-0283-01 Electrical Power & Control for 13/Feb/23 028105 15
Mechanical in RFFS
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 2nd
13/Feb/23 028120 15
23-0583-00 Floor BCT System Layout Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for ECT Ground,
21-0043-03 First & Second Floor CCTV & SACS 14/Feb/23 028140 14
System Layout
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 Ground
14/Feb/23 028145 14
22-0521-01 Floor Fire Command Center Layout Plan
ADC-NOCD-RFA-SD-EL- Shop Drawing Submittal for TE3 FIRST
14/Feb/23 028172 14
22-0125-01 FLOOR LIGHTING (EXIT) System Plan
Method Statement
Method Statement of the Installation of
ADC-NOCD-RFA-MS-
Signage (Aluminum, Stainless Steel & 08/Feb/23 027831 20
BC1-23-0196-00
Galvanized Steel Metal), Terminal-3
Elapsed
Submissio Workfl Days
Submission No. Subject n Date ow No. (Up to
28-Feb-
2023)
Material
ADC-NOCD-RFA-MT-EL-
Material Submittal of RJ45 Connector 07/Feb/23 027811 21
23-0189-00
ADC-NOCD-RFA-MT-EL- Material Submittal for Lightning Pole
08/Feb/23 027847 20
23-0195-00 (Myoung Eun, Korea)
ADC-NOCD-RFA-MT-Q- Material Submittal of Steel (Fire,
BC1-22-0382-03 Acoustic & Timber) Door Hardware 08/Feb/23 027850 20
(Part-1) for T3 Building
ADC-NOCD-RFA-MT-EL-
Material Submittal for AC-DC Meter 11/Feb/23 028013 17
23-0196-00
ADC-NOCD-RFA-MT-EL- Material Submittal for Pin Type Lug &
11/Feb/23 028014 17
23-0197-00 Ferrules
ADC-NOCD-RFA-MT-Q- Material Submittal of Acoustic doors and
BC1-22-0448-01 sound control door assemblies at T3 12/Feb/23 028060 16
building
ADC-NOCD-RFA-MT-ME- Material Submittal of Non Return Valve
12/Feb/23 028062 16
23-0269-00 for MCP Basement UWR
Request For Information
ADC-NOCD-RFI-ME-23- Clarification for the sprinkler type in ICT
07/Feb/23 027802 21
1733-00 radio active room
ADC-NOCD-RFI-ME-23- Clarification for the sprinkler system on
13/Feb/23 028098 15
1786-00 the cold room in ICT and ECT
ADC-NOCD-RFI-ME-23- Clarification for the M&E design for Fuel
13/Feb/23 028100 15
1787-00 Stand
ADC-NOCD-RFI-CC-22- Clarification for Landside Road 1, 3-3
14/Feb/23 028173 14
1486-01 sidewalk
5. Procurement Progress
Preliminaries 9 9
Civil 23 23
M&E 14 14
Total 75 74 1
- Pending Subcontractors
"MATPLAZA" or
1 Building Seating Works 20-Feb-22 6-Mar-22
"CCM" for VO
6. Construction Progress
- Total earthwork quantity is expected 6.5 mil.㎥ approximately, and the detailed quantities
of each area are as follows. This earthwork consists of swamp soil removal, excavation,
soil embankment, sand embankment which are going to be carried out in 5 phases (Ph.1 :
Apr ’20 ~ May ’20 / Ph.2 : Sep ’20 ~ Apr ’21 / Ph.3 : Sep ’21 ~ Apr ’22 / Ph.4 : Sep ’22 ~
Apr ’23 / Ph.5 : Sep ’23 ~ Apr ’24). Current work quantities will be re measured after
finishing of each trade of work.
- Excavation & embankment work has been progressed at the following in Landside and
Airside zone
→ Airside : Area 3-1, Area 6-1, 6-2, 7-1
→ Landside : Pond 21, Road A-1, 3, Existing VVIP Road , Car Park Access and T3 front,
North and right side etc.
700,000 7,000,000
600,000 6,000,000
500,000 5,000,000
200,000 2,000,000
100,000 1,000,000
0 0
Actual
Total Plan
~Jan. 2023 Feb. 2023 Cum.
Excavation 1,947,000 1,668,300 2,248,500 30,400 2,278,900
Embankment 4,503,000 4,125,900 3,939,300 45,700 3,985,000
Total 6,450,000 5,794,200 6,187,800 76,100 6,263,900
Progress (%) 89.8% 95.9% 1.2% 97.1%
- ST2-ST6 Asphalt work is ongoing. Additional Service Road 11 & 12 Sub grade work is
ongoing.
- Taxiway Closure Ph.6 commenced on 18th Dec. ‘22 and completed end of Mar ‘23.
Actual
Total Plan
~Jan. 2023 Feb. 2023 Cum.
Con’c Duct Bank 4,953 3,102 3,036 670 3,706
Ceramic Duct Bank 10,506 7,794 6,777 634 7,411
Fuel Hydrant Pipe 7,438 5,292 4,836 205 5,041
External Hydrant Pipe 6,414 4,554 2,896 222 3,118
Water Supply System 10,125 6,097 2,317 630 2,947
Sewer Pipe 5,018 4,183 1,982 230 2,212
44,454 31,022 21,844 2,591 24,435
Total
69.7% 49.1% 5.8% 54.9%
[EDW South]
[EDW North]
6.2.1 Pile work Progress – Bored Pile & PHC Pile Test Status
Total
Description Item Make Baseline Location 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th Status Remark
Qty's
22-05-25 ~ 22-10-31 22-12-05 22-12-29 2023-03-06 2023-03-20
1st on-site Port 3rd : 34
LG 22-07-23 (DKAC-499) (DKAC-546) (DKAC-620) (DKAC-773) (DKAC-795) 3rd : Duty payment delaying
AHU 157 no. 4th : 34
(KOR) 22-09-22 ~ CAAB Received : 7-FEB
Installation On site 23-01-10 23-01-25 23-03-02 23-03-30 23-04-20 5th : 34
23-05-10
Port 22-06-10 22-07-05 22-08-02 22-11-19 4th : on site unloading
21-07-27 ~ (Steel) (DKAC-246) (DKAC-303) (DKAC-382) (DKAC-548)
4 Lot 1st on-site Total : 12 container
21-11-09
On site 22-07-22 22-08-03 22-09-16 23-02-20 Done : 11container
Dimark
BHS 22-02-12
(POL) Port 22-06-10 22-08-09 22-12-19 22-12-30 23-01-15 23-02-01 23-03-10
(DKAC-192, TBD TBD
22-07-30 ~ (Conveyor) 219) (DKAC-258) (DKAC-338,391) (DKAC-552) (DKAC-565) (DKAC-566) (DKAC-668) (DKAC-669) 6th : Duty payment delaying
TE3 10 Lot Installation
24-02-24 CAAB Received : 15-FEB.
On site 2022-06-01 2022-06-30 2022-09-28 2023-01-19 2023-01-19 2023-03-02 2023-02-20 2023-04-12
(6th Batch) (6th Batch)
(Contract Batch) (1st Batch) (2nd Batch) (3rd Batch) (4th Batch) (4th Batch) (4th Batch) (5th Batch) (5th Batch)
22-07-03 ~ 23-03-03
1st on-site Port
Firefighting SPP 22-09-05 (DKAC-528)
6 no. 1st : on port 23.03.03 1st : 6
Pump (USA) 23-04-10 ~
Installation On site 23-03-30
23-07-23
22-07-03 ~ 23-01-10
1st on-site Port 23-04-07 23-04-07 1st :33
Taejin 22-09-05 (DKAC-642) 1st : IP issue
P&S Pump 65 no. 2rd : 2
(KOREA) 23-04-10 ~ (Sump pump, Booster pump)
Installation On site 23-03-10 23-05-02 23-05-02 3th : 6
23-07-23
21-11-21 ~ 22-10-15 22-12-16 23-01-13 23-01-21 23-01-21 23-02-18 23-02-18 23-03-18 23-03-19 23-04-10
HYUNDA 1st on-site Port
22-08-25 (DKAC-395) (DKAC-530) (DKAC-614) (DKAC-645) (DKAC-646) (DKAC-743) (DKAC-744) (DKAC-758) (DKAC-770) (DKAC-800)
CHS I MOVEX 9 Lot 6th : On site 23.03.19
22-11-05 ~
(KOR) Installation On site 22-12-18 23-01-27 23-02-09 23-02-10 23-02-25 23-03-19 23-03-19 23-04-21 23-04-21 23-05-11
23-12-07
22-07-03 ~
1st on-site Port 23-03-30
Frudent 22-09-05 1st on port : 23.03.30
Fan 38 no. 1st : 38
(Mal) 23-04-10 ~ (Roof fan)
Installation On site 23-04-18
23-07-23
22-07-03 ~ 23-03-03
1st on-site Port 23-04-14
22-09-05 (DKAC-528)
Firefighting SPP 23-04-10 ~ 1st : 3
26 no. Installation On site 23-03-30 23-05-10 1st : on port 23.03.03
Pump (USA) 23-07-23 2nd : 23
Other
ICT(8), ECT(8)
Building Location(no.) MLCP(3)
RFFS(4), MLCP(3)
22-07-03 ~ 23-03-02 23-03-17
1st on-site Port 23-03-31 23-04-14
22-09-05 (DKAC-766) (DKAC-788) 1st : 2
23-04-10 ~ 2nd : 4
Taejin Installation On site 23-03-30 23-04-15 23-04-21 23-05-10
P&S Pump 55 no. 23-07-23 1st : on port 23.03.02 3rd : 6
(KOREA)
ICT(6), ECT(6) 4th : 33
MLCP(4),
Location(no.) Tunnel(2) WSS(6) RFFS(3),STP(6) 5th : 10
RFFS(6)
MLCP(3), WSS(13)
Water 22-04-02 ~ 22-12-12 23-01-29 2023-03-21
1st on-site Port 23-04-15 23-04-25 23-05-30 23-06-25
treatment Yooduck 22-05-31 (DKAC-555) (DKAC-680) (DKAC-791) 3rd : preparing for shipment
7 Lot
system & (KOR) 22-09-28 ~ 4th : preparing for shipment
STP
Installation On site 22-12-29 23-02-12 23-04-05 23-05-02 23-05-15 23-06-20 23-07-10
23-08-05
22-07-29 ~ 22-08-27 22-12-13
1st on-site Port
Cooling Baltimore 22-09-26 (DKAC-423) (DKAC-573) 1st : 6
12 no. Full Completed
Tower (CHN) 22-09-27 ~ 2nd : 6
Installation On site 22-10-05 23-01-26
23-07-10
22-05-25 ~ 22-08-27 22-10-06
1st on-site Port
ACMV Grundfos 22-08-16 (DKAC-423) (DKAC-440) 1st : 6
24 no. Full Completed
Pump (KOR) 22-01-05 ~ 2nd : 6
Installation On site 22-10-05 22-11-04
23-07-23
DONE 22-07-03 ~ 23-01-01
1st on-site Port
Frudent 22-09-05 (DKAC-661)
Fan 40 no. Full Completed 1st : 40
(China) 23-04-10 ~
Installation On site 23-02-08
23-07-23
22-05-21 ~ 22-04-30 22-09-18
1st on-site Port
LG 22-07-19 (DKAC-218) (DKAC-421)
Chiller 12 no. Full Completed 1st : 24
(KOR) 22-01-05 ~
Installation On site 22-07-03 22-10-14
23-07-23
Progress
Location Material Total Q'ty Remark
Last month This month Cumulative
Basement UPVC 1,824 - - 1,758 96.4%
Ground Floor UPVC 8,962 51 49 8,773 97.9% +0.6%
1st Floor UPVC 8,459 146 186 8,048 95.1% +2.2%
2nd Floor UPVC 3,591 323 202 1,406 39.2% +5.7%
Sum total 22,836 520 437 19,985 87.5% +1.9%
Basement PPR 1,875 94 - 1,597 85.2% +5.0%
Ground Floor PPR 10,719 818 695 7,778 72.6% +11.1%
1st Floor PPR 5,055 284 517 1,135 22.5% +10.3%
2nd Floor PPR 3,560 - - - -
Sum total 21,209 1,196 1,212 10,510 49.6% +5.8%
Basement Floor HDPE 3,742 79 - 1,742 46.6% +2.2%
Ground Floor HDPE 284 - - - -
Sum total 4,026 79 - 1,742 43.3% +2.0%
Total 48,071 1,795 1,649 32,237 67.1% +3.5%
This month
Location Total Q'ty Last month Remark
Done Cumulative
Basement 17,184m 15,796m 226m 16,022m (93.2%) +1.3%
Ground Floor 64,417m 49,145m 1,733m 50,878m (79.0%) +3.7%
1st Floor 41,310m 18,089m 1,669m 19,758(47.8%) +4.0%
Roof 86,536m 16,254m 8,695m 24,949(28.8%) +10.0%
This month
Location Total Q'ty Last month Remark
Done Cumulative
Basement 3,901 m 2,936 m 284 m 3,220m (82.6%) +9.0%
This month
Location Total Q'ty Last month Remark
Done Cumulative
Basement 36,250 m2 13,931 m2 226 m2 14,157 m2 (39.1%) +0.7%
Ground Floor 120,710 m2 71,510 m2 2,944 m2 74,454 m2 (61.7%) +2.5%
1st Floor 63,124 m2 30,211 m2 3,069 m2 33,280 m2 (52.7%) +4.8%
- AHU installation
This month
Location Total Q'ty Last month Remark
Done Cumulative
Basement 6 no. - - -
[Ground Floor]
This month
Location Total Q'ty Last month Remark
Done Cumulative
Cooling tower
zone 12 no. 6. 1 7(58.3%) +8.3%
- Cable installation
Q’ty Installation
- Activity Remark
(%) Last month This Month Cumulative
Baggage Break down 100 - 35.9 35.9
Baggage Claim Hall 100 32.9 2.5 35.4
Reclaim Carousel 100 - -
BHS Make-up(Left) 100 66.4 7.2 73.6
HBS(EDS) 100 15.0 10.1 25.1
BHS Make-up(Right) 100 19.4 2.1 21.5
Electrical Work 100 0.8 4.3 5.1
SAT/T&C 100 - - -
Total progress 100 26.0 5.7 31.7
* Total progress: Calculated by applying weight factor by item
- AGLS
This month
Item Total Quantity Remark
Done Cumulative
Hand hole 350ea 2ea 320ea(91.4%) +0.5%
Primary HDPE 57,968m 1,774m 55987m(93.5%) +3.1%
Primary Cable 216,976m 5,350m 103,640m(47.8%) +2.6%
Secondary Cable 26,300m 210m 23,435m(89.1%) +2.2%
- FHS
This month
Total Length Last month Remark
Done Cumulative
7,440m 4,808m 192 5,000m (67.2%) +2.6%
ICT
40,000m 3,047m (7.6%) 1,973m 6993m (17.5%) +4.9%
GI Conduit
MLCP
2,775m 1,741m (62.7%) 101m 1,943m (70%) +7.3%
Cable Tray
This month
Total Length Last month Remark
Done Cumulative
5,655 m 2,886 m 200 m 3,086 m (54.6%) +3.5%
19 May.2021 for
Imported Aggregate United Quarries 2nd Jun 2021 Completed:
2-2 (ADC-NOCD-RFA-PL-Q-
(Asphalt) (UAE) (EAC-21-0741) (23 ~ 30 Oct, 2021)
21-0012-01)
TBD
3 Dowel bar, Admixture - - TBD
(Bangladesh)
9 Feb. 2022
15th Feb 2022 Completed:
4 Steel Girder bridge Samil, Korea (ADC-NOCD-RFA-PL-Q-
(EAC-22-0188) (25 ~ 31 May, 2022)
CC-22-0023)
Precast Concrete Sinohydro Factory
5 - - TBD
Girder (Bangladesh)
Aeronautical Ground
Lighting System
(AGLS) and
6th June 2021 14th July 2021
Aeronautical Lighting OCEM For AGLS Completed
6 (a)~(f) (ADC-NOCD-LTR-G-21- (L-CLEN-21-
control and monitoring (Italy) (21 ~ 27 Feb 2022)
0041) 0399)
systems (ALCMS)
(a) AGL Lighting
Fixture
Screwed steel pile
7 Fujita - - -
(Cancelled)
Completed:
st Korea Factory: (28
1 Jun.2021 for
Steel Structure DSHI 2nd Jun 2021 June ~ 2 July, 2021)
8-1 (ADC-NOCD-RFA-PL-Q-
(ECT/ICT) (Korea, Bangladesh) (EAC-21-0740) Bangladesh Factory:
21-0015-03)
(17 Aug. ~ 7 Sep
2021)
22 Apr. 2021
Façade Performance Jangho 17 May 2021 Completed:
9 (ADC-NOCD-RFA-PL-Q-
Mock-up (PMU) (China) (EAC-21-0667) (15 ~ 21 June, 2021)
21-0012)
TBD
14 Louvers, screen - - TBD
(Malaysia, China)
Lounge Furniture,
15 Check-in counters, - - - -
etc.
Aviation Dhaka Consortium (ADC) 47 / 146
Monthly Report (Feb 2023)
Table # 1
Date of submission of Date of Date of test
in Chapter Item Name Factory Name
test plan and schedule approval (estimate)
10160
16 Signage - - - -
22 Apr. 2021
Façade, Glazing Jangho 17 May 2021 Completed:
18 (ADC-NOCD-RFA-PL-Q-
system (China) (EAC-21-0667) (15 ~ 21 June, 2021)
21-0012)
Special Operating
19 - - - -
Door (30930CFGS)
23 Apr.2021
Sinohydro 25 Apr. 2021
20 Roof Cladding (ADC-NOCD-RFA-PL-Q- TBD
(China) (EAC-21-0574)
21-0013)
Metal Sandwich Wall
TBD
21 Panel (30700CF- - - TBD
China
Cladding)(ECT/ICT)
Uninterrupted Power SOCOMEC Asia 2th August 2022 #Factory visit planned
12 Sep. 2022
32 Supply (UPS) Pacific Pte. Ltd, (ADC-NOCD-LTR-ME-22- from 21st Oct. to 27th
(EAC-22-1192)
equipment France 0083) Oct. 2022
10th May 2022
16 Nov.2021 (ADC-NOCD-LTR-G-
LG Electronics, 24 Nov. 2021
33 Chiller (HSIA-ADC-PL-ME-21- 22-0054)
Korea (EAC-21-0330)
0006) #Factory visit from 15
May 2022 done
#Factory visit planned
34 Cooling Tower - - -
TBD
Chilled water & 16 Jan. 2022
22 Mar. 2021 Completed:
35 Condenser water Korea (HSIA-ADC-PL-ME-22-
(EAC-22-350) (10 ~ 18 June, 2022)
pump 0008)
Prudent Aire 8th June 2022
VAV box and
36 Engineering Sdn - - (ADC-NOCD-LTR-G-
controller assembly
Bhd, Malaysia 22-0064)
Aviation Dhaka Consortium (ADC) 48 / 146
Monthly Report (Feb 2023)
Table # 1
Date of submission of Date of Date of test
in Chapter Item Name Factory Name
test plan and schedule approval (estimate)
10160
HVAC MCC Main
37 - - - -
switch board
8 Mar. 2022
LG Electronics, 16 Mar. 2021 Completed:
38 Air handling unit (ADC-NOCD-RFA-PR-ME-
Korea (EAC-22-338) (10 ~ 18 June, 2022)
22-0012-01)
10 May 2021
Steel pipe for fuel 14 May 2021
39 Korea (HSIA-ADC-PL-ME-21- TBD
supply (EAC-21-0654)
0003)
ADC-NOCD-LTR-ME-
Fire pump 6 Jan. 2022 22-0048
SPP Pump, 22 Mar. 2021
40 sets(Electric (HSIA-ADC-PL-ME-22- #Factory visit planned
USA (EAC-22-349)
motor/engine driven) 0007) from 16thAug to 22nd
Aug 2022
ADC-NOCD-LTR-ME-
22-0050
Water treatment
41 Korea - - #Factory visit planned
equipment
from 12th Aug to 18th
Aug 2022
ADC-NOCD-LTR-ME-
Sewage treatment Yooduck 27 Jan. 2022 22-0050
42 plant equipment & Environment Co., (HSIA-ADC-PL-ME-22- - #Factory visit planned
vehicle Korea 0009) from 12th Aug to 18th
Aug 2022
8th September 2022 #Factory visit planned
16 Oct. 2022
43 Fire Alarm system Portugal (ADC-NOCD-LTR-ME-22- from 19st Oct. to 25th
(EAC-22-1434)
0092) Oct. 2022
23rd October 2022 #Factory visit planned
Security screening 3 Oct. 2022
44 Germany (ADC-NOCD-LTR-PR-22- from 08th to 14th Jan.
equipment (EAC-22-1346)
0827) 2023
25th September 2022 #Factory visit planned
Facial recognition 16 Oct. 2022
45 Germany (ADC-NOCD-LTR-PR-22- from 21th to 27th Jan.
system (FRS) (EAC-22-1430)
0755) 2023
Annunciator and
46 - - - -
Monitoring
Fire fighting System
47 - - - -
Equipment
TBD : To be dated
Note :
The Row filled with the color ( ) stands for the completed Factory Witness Test item.
The Row filled with the color ( ) stands for the schedule of Factory Witness Test up-to next 3 months (Oct.)
7.
Alternator issue for Emergency Generator(4000KVA) from Kohler (Minutes in this meeting)
- NOCD issued EI-22-0005 on 13 Feb 2022 regarding Kohler Generator confirmation after In regards with FAT report between submission
various discussion eventually. in Dec. 23 and revised submission in Feb, 23,
- ADC had got material approval through EAC-22-0812 on 22 Jun 2022.(Engine&Alternator: NOCD highlighted the discrepancy of both
Kohler/France)
documents.
- NOCD issued that Alternator Brand and COO(LEROY-SOMER/Czech Republic) is different
1) ADC clarified this issue with Kohler letter that
from MFA approved COO and Brand
4200 & 4000 KVA is only meaning of head title
- ADC provides Kohler's letters to NOCD which declared "We, LEROY-SOMER and
without any confusion of test report
KOHLER, declare that, between Kohler and Leroy-Somer, Alternator model No : KH
09720T(Alternator) made by Leroy-Somer is product under the brand Kohler." 2) CAAB requested ADC to submit the 3rd party
2 TE3 New NOCD ADC ASAP
- In addition, LEROY-SOMER declared that "LSA 54 frame" Alternator, which is same frame audit report about discrepancy only for
with HSIA PJT's one, is only manufactured in the factory from Czech Republic. alternator accordingly.
- In spite of those declaration, ADC has proposed its discount(50,000EUR) and In regards with Alternator issue of Kohler
additional 2 year warranty(Total 7years) requests for approval revised MFA and FAT generator such as COO & manufacturer
reports to resolve the issue to avoid further delay for the PJT schedule and conformity, Chairman agreed to close out this
Ceremony . subject with below condition.(ADC-NOCD-LTR-
though the letter ref. ADC-NOCD-LTR-ME-23-0063 on 27 Feb 2023 ME-23-0063 on 27 Feb 2023)
- Kindly request for prompt approval for Material and FAT report of Emergency 1) Discount(50,000EUR) and additional 2 year
Generator(4000KVA) warranty(Total 7years)
Requesting Variation Order(VO) for the H-Pile Earthnig Works for Pier Extension
- NOCD issued EI(EI-22-0161) on 23 Jun 2022 regarding H-Pile Earting Installation Layout
Plan for (update as of 2nd Mar.)
6 TE3 Pier Extension Building New NOCD Under review by NOCD, so the agenda will be
- ADC has raised RFA (ADC-NOCD-RFA-EL3-0578) on 08 Jan 2023 skipped.
- ADC issued on VO (ADC-NOCD-LTR-C-23-0071 on 01 Feb 2023
- Kindly request for VO approval.
Withdraw material maker change of BHS drum motor (Ref. L-ADC-23-0027-01) (update as of 2nd Mar.)
- The additional material list for drum motor of Italy "Rulmeca" approved by EAC-22-1848 Time impact and the comparison of the
dated on 21th December 2022. BHS with drum motor was ordered and fabricating already. materials to be explained by ADC in the
CAAB
Hence, it is not possible withdraw. meeting. Immidiatel
8 TE3 New NOCD NOCD
- ADC issued a letter(ADC-NOCD-LTR-ME-23-0052) on 19 Feb 2023 regarding cost and y
ADC
time impact resulting from the cancellation of Rulmeca drive motors and to use Interroll brand (Minutes in this meeting)
instead for the BHS conveyors Meeting among CAAB, ADC and Dimark to be
- Kindly request for NOCD's reply. ararnged ASAP
- 05 Jan, NOCD issued a letter to CAAB, L-CLEN-23-0061, for submitting Technical Documents to RHD. - CAAB needs to submit Technical
RHD: Highway New
12-1 - 07 Feb, NOCD issued a reminder letter to CAAB, L-CLEN-23-0336, for submitting Technical Documents to RHD. Documents to RHD for RHD's evaluation 05 Mar.
Pedestrian Bridge
- 28 Feb, NOCD issued a reminder letter to CAAB, L-CLEN-23-0484, for submitting Technical Documents to RHD. as per MoM with on 05 jul. 2022.
- 11 Feb. 2023, ADC issued a letter, ADC-NOCD-LTR-G-23-0062, "Request for relocation or demolition of elecric poles for stee bridge
erection".
- 22 Feb. 2023, CAAB advised NOCD to instruct ADC to inform the exact date of the latest for the relocation, so that CAAB can negotiate
with the concerned Authority.
RHD: Highway Electric - CAAB needs to arrange a Coordination
12-2 - 23 Feb., Traffic Police & RHD & CAAB (with NOCD & ADC) Joint Meeting was held. RHD agreed to have a further discussion with ADC 07 Mar.
Pole etc.' relocation meeting with RHD and get a permission by
to help.
10 Mar.
- 28 Feb, ADC submitted a updated letter, ADC-NOCD-LTR-G-23-0062-01, stated deadline date with 10 Mar. for getting a permission
from RHD.
- 01 Mar, NOCD issued a letter to CAAB, L-CLEN-23-0487, for requesting a meeting with RHD.
- 01 Feb. RAB requested CAAB to complete Road Pavement work by Mid. Mar. before VVIP visits RAB HQ.
=> This is not ADC's original schedule.
- ADC should submit a Pavement work
- 21 Feb. CAAB reminded NOCD & ADC to complete Pavement work as requested by RAB HQ.
RAB HQ: Pavement schedule and complete the Pavement work
14 - 23 Feb. CAAB & NOCD & ADC discussed and agreed to complete Pavement work "in front of RAB HQ area only" by 07 Mar. 07 Mar.
Work in front of RAB HQ by 07 March.
- 26 Feb., NOCD issued EI to ADC and also a letter to CAAB.
- 28 Feb, CAAB (with NOCD) has had a meeting with RAB and received a permission of Time Extension until 07 March. NOCD informed
it to ADC.
<Terminal-3>
Request final confirmation whether temporary slab cover with finish at tunnel opening is installed
9 TE3 Design NOCD
or not
Request to revise and issue Pier extension connection area design and work scope as per L-
10 TE3 Design ADC-23-0055 on 22-Jan-2023. NOCD
- EI-23-0001-06 was issued. But, still not finalize.
<Other Building>
Serial
Area Item Issues Action By By when Final Status
No
Diagonal steel members are exposed under ceiling.
10 O/B ICT & ECT NOCD
- Submitted ADC-NOCD-RFI-BC2-23-1823
<Electrical 1>
Serial
Area Item Issues Action By By when Final Status
No
<Electrical 2>
Serial
Area Item Issues Action By By when Final Status
No
Waiting confirmation Toilet DB location
- Toilet DB location had been issued by shop drawing comment from Dec-2021.
- Finally ADC received all DB locations by ERRI-23-0017.
- ADC is struggling with one agenda to change more than 6 times for more than 1 year.
- This is impact Toilet Finishing and DB Cable ternimation Work
14 Electrical Toilet DB location - ADC issued of Delay notice to NOCD - ADC-NOCD-LTR-ME-23-0028 on 04 Feb 2023 NOCD
- ADC submitted rev02 RFI(ADC-NOCD-RFI-EL-22-1583) regarding Final Confirmation on 20
Feb 2023
- Request for approval 9nos Toilet DB Approval
· 6nos Toilet DB Shop drawing submitted and Need to get Approval asap
· 3nos RFI submitted regarding Final Location of Toilet DB Confirmation
<Electrical 3>
Serial
Area Item Issues Action By By when Final Status
No
Integration of FACP to mechanical Fire fighting system in Other building same as
Terminal-3
- ADC recieved an initial EI for the integration between FACP and FF systme in other buildings
as T3 on
28 Sep 22. (EI-22-0252)
- ADC reminded 3 times NOCD to provide detailed drawings for Integration of FACP to FF
system but
again received similar EI without details on 22 Jan 23. (L-ADC -23-0053)
- ADC submitted to request EI Issue (ADC-NOCD-LTR-ME-23-0045 : Increase Fiber Optic
46 Electrical Design Cable for Fire NOCD
Alarm as future provision to connect T3 and other building ) by 16th of Feb 2023.
- If no issue EI by 16th of Feb 2023, ADC will proceed with the purchase of Fiber Optic cable
based on
original contract that does not include Fiber Optic cable for Fire Alarm System
- ADC requested issue an EI for additional FO cable by 16 Feb
- NOCD issued EI(EI-23-0060) on 26 Fen 2023 regarding Interface between FACP and
Mechanical Fire
Fighting System in Other Buildings
- ADC still needs Detail Design after then ADC will discuss with NOCD
PBB (Glass)
- Glass material was confirmed by L-ADC-23-0067 on 29 Jan 2023
57 Electrical PBB NOCD
- ADC submitted Modified RFA and awaiting approval
- ADC submitted rev01 ADC-NOCD-RFA-MT-EL-22-0134 on 9 Feb 2023
PBB (Floor)
- Floor material was confirmed by L-ADC-23-0067 on 29 Jan 2023
- The vendor confirmed that they no longer manufacture confirmed material (3.5mm rubber
sheet)
- The contractor strongly recommended to use PBB manufacture's proposed floor material for
58 Electrical PBB their NOCD
guarantee and keep the work schedule
- ADC submitted rev01 ADC-NOCD-RFA-MT-EL-22-0135 on 22 Jan 2023
- NOCD apporved as noted rev01 ADC-NOCD-RFA-MT-EL-22-0135 on 20 Feb 2023
· Comment : Follow L-ADC-23-0067 on 29 Jan 2023
- ADC to submit rev02 MFA with NOCD Comments reply
Pending Technical Report approval for AODB and other system interface data
confirmation
- ADC submitted Interface Control Documents for exchanging data between AOCD and VDGS
59 Electrical Technical Report NOCD
∙ ADC-NOCD-RFA-TR-EL-22-0028-02 on 22 Jan 2023
(ICD for exchanging data between AOCD and VDGS)
- Kindly requests for NOCD's prompt review and approval.
- ADC noticed the price of Diesel and Kerosene is revised effective from 3rd Nov 2021 with unreasonable increase acc to the Bangladesh
Gazette dated 3rd Nov 2021 and is considered to be changes in legislation / 10th Nov 2021
- ADC noticed for additional fuel price increase(80->114 BDT/liter) acc to Government Circulation dated 5th Aug 2022 on 6th Aug
- ADC submitted estimated cost impact on the balance activities of the work in amounting to BDT 2bil on 24th Aug
- ADC noticed for additional fuel price adjustment(80->109 BDT/liter, diesel) acc to Government Circulation (dated 29th Aug 2022) on 30th Aug
- NOCD approved that the Gazette notice can be defined as change of government regulations under GC13.7 and the specific application of
Government's Circulation for Fuel the additional cost shall be limited only to fuel prices which are directly incurred by the consumption of the fuel (indirect effect of this fuel price
4
Price Increase increase shall be deemed to be separately adjusted under GC 13.8) on 15th Sep
- ADC requested for approval of indirect cost Impact due to Government Circulation for the Fuel Price Increase on 18th Oct
- NOCD disapprove previous certificate so ADC submitted the details/breakdown of quantity in tender stage and waiting for NOCD's decision
- ADC agreed the evaluated amount of NOCD which is based on equipment efficiency and excluding O&P 25.8%, and waiting for approval of
cumulative impact, claimed up to Dec 2022 as of BDT 221.6mil. for ADC's equipment, sand delivery and Bus/Car on 23rd Jan, 2023
- ADC submitted the cost proposal (upto Sep 2023) applying the caculation method which was discussed with NOCD on 19th Feb, 2023
- ADC submitted cumulative impact up to Jan 2023 as BDT 263.3mil for ADC's equipment, sand delivery and Bus/Car on 22nd Feb, 2023
- ADC requested the Employer to issue a support letter in L/C Opening which has been delayed due to USD shortage in the bank (of Finish
Non-availability to open L/C due to work Subcon, AMFL) in order to avoid further delays on 30th Oct (ADC-NOCD-LTR-G-22-0308)
5 USD Shortage in Major Commercial - ADC requested the Employer to issue a request letter to Bangladesh Central Bank to supply USD to the bank for opening L/C exclusively for
Banks of Bangladesh the Project in order to avoid further delays on 3rd Nov (ADC-NOCD-LTR-G-22-0313)
- ADC noticed the delay caused by Non-availability to open L/C due to USD Shortage in Major Commercial Banks of Bangladesh on 4th Dec
- ADC noticed massive fluctuation of JPY currency (expected fluctuation of JPY:USD upto 2%/year in average as per the 4 years record of
Unreasonable Currency Fluctuation of
6 currency fluctuation prior to Feb 2019 → more than 27% annual percentage currently) and impacted on the Contractor/Subcontractors' price
the Japanese Yen (JPY) and BDT
so requested adjustment of the Contract Price on 18 Jul
- ADC noticed steep rise in Shipping Cost for procurement of imported materials by 540% as per the data from SCFI(Shanghai Containerized
Freight Index) from overseas (ocean freight) due to Shortage of Containers and additional COVID-19(Omicron) quarantine guideline for ships
Steep Rise in Shipping Cost and
7 departing from the port around the world on 4th Jan
Delay in Import Process
- Notified steep rise of ocean freight which is causing extra cost burden and requested support the Engineer/Employer to allow ADC to obtain
necessary permits, approval required for importation process in timely manner to avoid further delay/cost impact on 28 Feb
- ADC requested adjustment of price escalation considering not reflecting the actual market condtion and mis-matching with the official inflation
rate of the Country ("The Business Standard") on 27 Mar 2022
- NOCD requested the detailed official indices or alternatives to CPI for each individual items for evaluations and for approvals by the CAAB
on 30 Mar and ADC submitted the comparison between actual market price which colllected from relevant suppliers and cost index of BBS
on 11 Apr 2022
- ADC requested adjustment of price escalation (ohshore) with the analysis of newly published PWD schedule of Rates 2022 which is 26%
increase in the cost and in average 6.5%/year from last version (RWDP 2018) on 31 Jul 2022
- NOCD recommended the adjustments of BDT index(23.4% esc from base date) to CAAB which's raised by the Contractor on 23 Aug 2022
- ADC requested NOCD/CAAB to apply the revised cost escalation factor effective form 21 June 2022
- ADC transmitted newspaper article pointing out the current situation of BBS of being delayed application of inflation data acc to Executive
Request for Clarification of Cost Index Director of the Policy Research Institute of Bangladesh on 28th Sep 2022
8
in the table of adjustment data - CAAB officially requested to MOCAT to decide on whether to update BBS Index or use PWD Index on 27th Oct 2022
- ADC requested NOCD to make fair determination as soon as applicable but not later than 28 days from the date of 15th Nov 2022
- ADC submitted legal memorandum for the interpretation of Sub-Clause 13.8 of FIDIC Pink Book on 14th Dec 2022
- ADC requested for the Engineer’s determination on the issue of Price Escalation Adjustment as soon as applicable but not
later than 28 days from the date of previous letter (ADC-NOCD-LTR-C-22-0539, dated 14th Dec 2022) considering hardships
and problems which have deteriorated the productivity and cash flow of the Contractor on 27th Dec 2022
- NOCD notified that he cannot set by determination the change of Price Adjustment Index from BBS to PWD and will continue to his utmost to
convince the Employer on the matter on 3rd Jan 2023
- ADC notified that he shall not be held responsible for any delay and disruption which may cause adverse implications such as reduced
resources, lowerd morale, out of control on Subcontractor's performance considering the Engineer's lack of fair determination and
Contractor's position not to bear any further financial loss on 15th Jan. 2023
- ADC suggested NOCD to evaluate variation in fair and reasonable unit rate as price escalation mechanism has not been properly operated
due to the deviation between the actual price in the market and the price set by the bureau of statistics of various Authorities on 7th Aug. 2022
- ADC suggested NOCD that fair and reasonable unit rate should be applied to the evaluation of the variation ① No cost revision for the
completed/on-going Variation works ② Variation not been started shall be re-submitted based on the reasonable cost in the maket ③ If
Variation work contains item whose rate or price is specified in the Contract, such rate or pice shall be adjusted on a pro-rata basis between
PWD 2018 and PWD 2022 (As of Aug 2022, 22.7%) ④ If Variation work contains item whose rate or price is not specified in the Contract,
such rate or pice shall be derived from the reasonable cost which is available in the market at the month of receiving an EI for the Variation on
9 Evaluation of Variation works 9 Aug. 2022
- ADC notified that he shall not be bound to proceed with any variation work which has not been confIrmed in terms of cost till 5th Dec. 2022
- ADC notified his suffer on delay and disruption due to internal hindrances (new works not required for the Permanent works, continuous
changes, uncoordinated drawings delayed response to clarifications to resolve deviations i.e> WSS) and his opinion to decline the EI to
conduct any new works not required for the Permanent Works considering utmost priority for the Project (Pre-Opening ceremony and
successful completion of the Project) on 15th Dec. 2022
- ADC requested NOCD to issue the official approval to VO cost proposals which are already evaluated by the Engineer and
accepted by the Contractor (17 nos of VOs) on 9th Jan 2023
- ADC submitted 'List of missining items (Civil, Building and M&E) including introduction of related Contract Condition on 31 Aug and had
clarification meeting on 15 Sep, 18 Sep and 19 Sep
Missing Items in Bill of Quantities
11 - ADC submitted the revised BOQ of IPP/IPR reflecting missing items acc to NOCD's instruction on 2nd Oct
(BOQ)
- NOCD requested ADC to revise not only the addition of Missing Items, but also the quantity and Contract Amount for all items
to understand the approximate amount of Overall Variation on 24th Nov but it shall be discussed with ADC
- ADC proposed to approve 50% of saving amount (JPY 62,579,406 & BDT 184,972,466) in line with approval of shop and mock-up test on 16
Nov
- NOCD notified to proceed apron lean concrete work as technically concurred by BUET, CAAB and the Consultant. However, commented that
VE cost saving amount shall be considered for decreasing durability of pavement due to change of the thickness on 25th Nov
VE_Design Change of Airside Apron
12 - ADC replied that calculated PCC design life of 20.1 years satisfies Engineer's PCC design life requirement and FAA design requirement of
Pavement
20 years, so no decreas in durability of the pavement and waiting for approval from CAAB
- ADC submitted revised VE fee for Type-1 & Type-1' pavement which is 50% of saving in amount to JPY 64,717,849 & BDT 190,357,086 on
27 Jul
- ADC requested NOCD to approve VE fees pertaining to the airside apron con'c pavement works on 15th Nov
- NOCD instructed ADC to suspend all activities concerning the Engineer's Accommodation and make the site safe and secure for retuning
the site to CAAB on 16th Oct
- ADC applied Taking Over Certificate for the Engineer's Accommodation with the consideration of the scope omission on 13th Nov
13 TOC for Engineer's Accommodation
- NOCD issued Taking Over Certificate on Engineer's Accommodation Area as of 14th Nov 2022
- ADC submitted Final Account of Engineer’s Accommodation (Design, Site Preparation and Earthworks) in amount of
JPY 13,904 and BDT 41,305,484 on 1st Dec
- NOCD indroduced "TCL-TP-UP JV" as Nominated Subcontractor for Provisional Sum of VVIP Lounge work in T3 with the cost amount BDT
641,151,054 on 27th Feb 2023 (L-ADC-23-0134)
Nominated Subcontractor for
- ADC notified to NOCD that NSC ("TCL-TP-UP JV") has not allowed enough consideration for the conditions of the actual execution for the
14 Provisional Sum of VVIP Lounge work
Project as they were not properly aware of working process for the apparoval of Shop Drawing, Material, Mock-up, FWT etc. and being not able
in T3.
to check essential terms and conditions such as payment terms, bonds, warranties, indemnity, LD etc. So ADC requested NOCD to provide
fruther information which is prerequisite to review the capability and capacity of the NSC on 2nd Mar 2023 (ADC-NOCD-LTR-G-23-0084)
- ADC noticed the change in the Laws for VAT provision of Ready Mixed Concrete (HS Code 68.10) on 27th Jul.
- VAT exempted on Ready Mixed Concrete acc to the SRO No.144/2020/105-VAT → Payment 15% VAT and withdrawn Ready Mixed Concrete
Government’s Circulation for Change
from the VAT exemption list acc to new SRO No.1163/Law/2022/176-VAT dated 1st Jun 2022
in VAT
- ADC noticed the change in the Laws for VAT provision(2000 BDT/ton -> 2200 BDT/ton) of Rebar (HS Code 72.13~72.16) on 10 Aug
- ADC included 1st claimable amount in IP#26 for compensation and have been approved
Disruptions to Site Operations due to - ADC noticed the interruption of works at site due to frequent power cuts on 4th Aug
Intermittent Power Cuts - NOCD replied not to agree on ADC's assertion that power cuts are unforeseeable events on 10 Aug
- ADC submitted revised baseline schedule reflecting 'Acceleration plan' on 24th Sep → Briefing session to NOCD held on 29th Sep
- NOCD request for further information (list of any concerns on "specific probable future events or circumstances which may adversely affect
the
work, increase the Contract Price or delay the execution of the Works" refering GC 8.4) and proposals to mitigate such delays, etc., if they
were
to occur on 17th Oct
Revision of baseline schedule - ADC submitted 'List of delay events issued from March 2022 to September 2022' as a reply of NOCD letter on 20th Oct
- NOCD requested ADC to submit detailed schedule which reflect the depletion of float and mitigation method to prevent delay events (44 nos)
that reflected in ADC submitted list on 26th Oct
- ADC replied that ① the documents to claim EOT to be compliance with the critical path methodology applied to the P6 Programme, ②
methods to mitigate delays to be applicable on 31st Oct
- NOCD consented on the revised Baseline Schedule on 2nd Nov
- ADC reported Force Majeure Event (Lightning strike on N1 Rapid Taxiway for Demolition & Repair of Existing Pipe Culvert Headwall Besides
Airside Service Road 2) on 3rd Aug.
Pavement repair at Taxiway N1 - NOCD instructed ADC to submit incident report/ remove the affected area/ submt Method Statement for repair work on 5th Sep.
- ADC submitted cost for Force Majeure event (JPY 3,115 and BDT 35,887) and for demolition & repair (JPY 10,361 and BDT 53,029) on 11th
Oct.
- NOCD shared drawings of Architectural, Electrical and Structural Dwgs for New CAAB office Bldg and requested necessary actions on 5th
Oct.
- Requested NOCD to issue additional information for the New CAAB office Building (Full set of drawings/ Sepcification/ BOQ) and noticed
12 New CAAB Office Building proposal for additional works shall be based on new rate/price prevailing in the current market on 9th Oct.
- NOCD issued EI (drawing list of column and anchor bolt layout and base plate) to prepare additional CAAB office
- NOCD instructed the columns above the roof of the WSS issued through previous EI's to be omitted on 26th Dec. (EI-22-0354)
- NOCD instructed ADC to take action as per EI on 27th Dec
8.2 Materials
8.3 Equipment
8.4
Aviation Dhaka Consortium (ADC) 63 / 146
Monthly Report (Feb 2023)
Temperature(˚C) Relative
Date Sky Rainfall (mm) Wind(kph)
Humidity(%)
Max Min
< Weather Data from : Bangladesh Meteorological Department, http://www.bmd.gov.bd and Site Laboratory >
9.Financial Status
9.1 Payment status
Work A. Submission B. Certification C. Payment D. Outstanding (=B-C)
S/N Combined Combined Due Actual Combined Combined
Period Date JPY BDT Date JPY BDT JPY BDT JPY BDT
USD USD Date Date USD USD
10-Mar-20 18,731,363,901 8,844,855,799 271,181,955 254,836,728
IPA-30
30 22-Jan-23 2,565,644,665 1,449,937,228 39,991,810 20-Feb-23 1,920,757,544 1,055,325,563 29,579,436 2-Apr-23
(Dec '22)
IPA-31
31 21-Feb-23 3,102,648,867 1,168,037,642 41,371,047 2-May-23
(Jan '23)
IPA-32
32
(Feb '23)
Total (including AP) 52,909,460,415 41,264,536,542 960,438,758 49,806,811,548 40,096,498,900 919,066,321 47,885,942,965 39,041,136,866 889,486,858 0 0
34,178,096,514 32,164,844,015 686,213,250 31,075,447,647 30,996,806,373 644,840,812 29,154,579,064 29,941,444,339 615,261,350 0 0
Total (excluding AP)
54.0% 42.7% 49.7% 40.1% 38.2%
before retent/AP amor after retent/AP amor before retent/AP amor after retent/AP amor after retention [SUM of Outstanding Payment & Financing Charge]
Note ; Item Amount (BDT) Remarks
1) Above amount is exclusive of AIT & VAT and after 10% retention and exchange rate is 1 USD=83.73 BDT, 1JPY=0.74BDT. 1) Advance Payment
2) Outstanding amount of BDT portion has been caused by CAAB’s payment process, converting currencies from BDT & JPY to BDT before being paid to ADC. 2) Interim Payment 0 pending
3) ADC-CAAB-LTR-G20-0079 dated on 15 Sep 2020 : Requested CAAB to establish a payment scheme to resolve outstanding amount. 3) Financing Charge 146,496,344 for 1)+2)
- Financing charge : 3%(annual rate) + discount rate of central bank in the country of the currency of payment. If not available, the interbank offered rate shall be paid according to G.C. 14.8. 4) Custom Duty/Tax 366,570,153
4) "Flow chart of inspection for bored pile", WIR to be signed by inspector within 24 hours from inspection and feedbacked by RE within 3 working days after completion of WIR 5) Financing Charge 33,228,443 for 4)
10.1 Engineer’s Instruction & Confirmation (Closed items removed and outstanding items only listed here)
No. Category Reference No. Instruction Date Description Remarks
EI-20-0035 - ADC requested EI for site clearance of obstruction and complete handover and NOCD clarified that
EI-20-0061 Location of ICT was confirmed in weekly ADC install fence around ICT and backfill the existing canal in ICT area and do removal/relocation of
84 Civil 27-Aug-20
ADC-NOCD-LTR-C-21-0040 meeting by CAAB and NOCD / 12 Aug lighting, waste, brick wall, other existing structures and debris and re-submitted cost proposal of JPY
ADC-NOCD-LTR-C-21-0056 10,173,409 and BDT 38,169,731 for the site preparation of ICT area on 11th Mar according to EI
ADC-NOCD-LTR-G-20-0249 8-Dec-20 - Requested EI for additional road maintenance works (additional road for VVIP movement, pavement
EI-20-010, EI-21-0032 13-Dec-20 of existing unpaved road & additional maintenance road)/ 9th Dec 2020 and submitted technical
85 Civil ADC-NOCD-LTR-C-20-0060 15-Dec-20 Additional airside road works proposal & initial estimated cost quotation
L-ADC-20-0240 22-Dec-20 - Detail design is under preparation and revised cost proposal is after approval of detail design
ADC-NOCD-LTR-G-21-0254 2-Nov-21 ADC submitted the Cost proposal or an amount of JPY 53,572,741 and BDT 51,297,873.
ADC-NOCD-LTR-C-21-0009 Tree removal along the verge on the - NOCD issued EI to carry out the tree removal and relocation prior to the temp fencing work along
86 Civil 3-Feb-21
EI-21-0033 expressway the verge of the highway on 4th Feb 2021
ADC-NOCD-LTR-C-20-0065 - NOCD issued the EI and request to submit cost proposal for approval / 5 Jan 2021
87 Civil EI-21-0004 23-Dec-20 Cement Stabilization Work at Box Culvert - ADC submitted revised cost proposal considering the mixing ratio of cement as 60kg per cubic
ADC-NOCD-LTR-C-21-0007, 0095 meter (Case#1) on 20th Apr (JPY 439.0 and BDT 8,329 per cubic meter)
- NOCD issued EI to revise shop drawing and submit cost for "Change of CT water supply and make-
88 M&E EI-21-0107 8-Jun-21 Airport's HVAC system
up water system" and "Change or reduce CT storage space, secure relocation location"
- NOCD issued EI for submission of technical and cost proposals for site preparation of Ansar
Accoridng to handover inspection, there
89 Civil L-ADC-21-0117 14-Jun-21 Barrack Area
are lots of garbage to remove
- Based on work done cost proposal will be prepared
EI-20-0035, 0061, 21-0023
90 Civil 27-Aug-20 Site preparation of ICT area - ADC Submitted Cost Proposal on 11 Mar 2021(JPY 10,173,409 BDT 38,169,731)
ADC-NOCD-LTR-C-21-0056
Design change apron storm water
EI-21-0047
01-Mar-21 drainage system vertical shaft with -ADC confirms and is in agreement with the Engineer's assessment the revised Cost K220(JPY
91 Civil ADC-NOCD-LTR-C-21-0130
15-Nov-21 maintenance covers at TA2-E-03 & TA4-E- 43,556,855 BDT 304,334)
ADC-NOCD-LTR-C-21-279
03
Design change of Concrete Kerb on EDW - NOCD issued EI and requested ADC to submit cost proposal (Variation Order) on 24th Oct 2021
105 Civil EI-21-0200 24-Oct-21
Curbside Bridge (Height and shape of Concrete Kerb)
Aviation Dhaka Consortium (ADC) 68 / 146
Monthly Report (Feb 2023)
No. Category Reference No. Instruction Date Description Remarks
Additional road works of Airside VVIP Road
EI-21-0032 2-Feb-21
106 Civil in Area 6-1 and VVIP Service Road no.8 to - Submitted cost proposal in the amount of JPY 52,572,741 and BDT 51,297,873 on 2nd Nov 2021
ADC-NOCD-LTR-C-21-0254 2-Nov-21
13 Parallel Taxiway
- EI was issued to add DESCO Jashimuddin grid substation to backup line and request to submit
EI-21-0021 10-Mar-21
cost estimate including arch/strl impact on 10 Mar 2021
EI-21-0055 Modification of DESCO incoming power
- Requested VO for the modification of IPR with the submission of cost breakdown on 11th Jul 2021
107 M&E ADC-NOCD-LTR-ME-21-0042 11-Jul-21 supply in Intake Power Plant for Receiving
- NOCD requested total Increase-Decrease Summary and Cost calculation for VO on 13th Sep 2021
L-ADC-21-0193 13-Sep-21 (IPR)
- Requested VO in amount of JPY 164,324,493 and BDT 1,241,471 for the modification of IPR with
ADC-NOCD-LTR-C-21-0263 31-Oct-21
the submission of cost breakdown on 31st Oct 2021
EI-20-0107 21-Dec-20 - EI to construct additional outlets for subdrain system and trapezodial channel at RET S1 and N1
ADC-NOCD-LTR-C-21-0015 20-Jan-21 - ADC noticed 95 days of delay for the completion of the Ph.2 Rapid Taxiway works due to the
New outlet and trapezoidal for RET S1 and
108 Civil ADC-NOCD-LTR-C-21-0004 23-Jan-21 additional works / 20th Jan and submitted cost proposal on 23rd Jan 2021
N1
ADC-NOCD-LTR-C-21-0004-01 01-Mar-21 - -ADC confirms his agreement with the Engineer's assessment and accordingly submits revised
ADC-NOCD-LTR-C-21-0261 02-Nov-21 cost proposal in the magnitude of JPY 10,066,064 and BDT 22,528,613
- Requested EI for the change of level of Airport Service Road-1 issued by verbal instruction of
ADC-NOCD-LTR-C-21-0090 18-Apr-21 members of the Airport Operation Team on 18th April 2021
EI-21-0078 20-Apr-21 - NOCD issued EI and requested submit shop dwgs & cost proposal on 20th April 2021
109 Civil Change the level of Airport Service Road-1
ADC-NOCD-LTR-C-21-0115 12-May-21 - Submitted revised cost proposal for abortive work and additional drainage work due to change in
ADC-NOCD-LTR-C-21-0255 2-Nov-21 Elevation of Airport Service Road-1 in the amount of JPY 949,452 and BDT 2,427,894 on 2nd Nov
2021
The Contractor requests the Engineer to confirm the ‘New Work’ in the Contractor’s Scope of Works
EI to Revision of Area-5 Domestic
EI-21-0198 19-Oct-21 and issue the necessary drawings and information
110 Civil Terminal Access Road and Car Park
ADC-NOCD-LTR-C-21-0244 21-Oct-21 so that the Contractor can proceed with the shop drawing preparation and site works
layouts Area-5
-Cost proposal to be submitted after shop drawing finalized.
Additional Demolition Work of Former
EI-21-0032 12-Oct-21 Drainage Structure in Area 5 and existing
111 Civil - Submitted cost proposal in the amount of JPY 15,733 and BDT 2,466,241 on 2nd Nov 2021
ADC-NOCD-LTR-C-21-0254 2-Nov-21 RCC works in different location of the
Project
- Issued EI for the confirmation of relocation and additional MV switch panel and request ADC to
112 M&E EI-21-0212 14-Nov-21 Relocation and additional MV switch panel
submit the related drawings/ technical & cost proposal on 14th Nov 2021
ERRI-20-0566, EI-21-0010,
2020-11-29, 2021-01-07
EI-21-0012, EADC-21-0129, - EI was issued for additional Underpass waterproofing works on 7th & 11th Feb 2021 and
113 Civil ADC-NOCD-LTR-C-21-0039(-01), 0277
2021-01-11, 2021-02-03 Waterproofing in road underpath
2021-02-23
ADC re-submitted cost proposal (JPY 13,463,934 and BDT 11,855,592) on 11th Nov 2021
ADC-NOCD-LTR-C-20-0066
EI-21-0151 6-Sep-21 - Issued EI of the airside drainage layout plan reflecting drainage modification on 6th Sep 2021
114 Civil ADC-NOCD-LTR-C-21-0213 26-Sep-21 Additional box culvert in Area 7-2 - ADC submitted revised cost(JPY 7,560,031 and BDT 25,521,176) for additional new pipe culvert
ADC-NOCD-LTR-C-21-0213-01, 0282 21-Oct-21, 15-Nov-21 and new headwalls to connect existing culverts on the basis of remeasurement on 15th Nov 2021
Landside sub-base crushed sand material - NOCD issued EI to carry out it and requested to submit revised MS & cost proposal on 18th Nov
115 Civil EI-21-0214 18-Nov-21
& Mixing proportion change 2021
- NOCD instructed to change of Water Over flow Level, There will be Insect Mesh at both END of
116 M&E EI-21-0216 21-Nov-21 Water Tank over flow pipe
Water Over flow Pipe on 21st Nov. 2021
- Issued EI to do Additional construction work of the new Bridge on VVIP Road-3. 1. A new bridge will
EDW Additional construction work of new
117 Civil EI-21-0218 22-Nov-21 be designed on VVIP Road-3 to balance water and drainage between ponds #2 & #6 as well as
Bridge on VVIP Road-3
ensure the aesthetics of the area.
- NOCD instructed to construct the alternative crossing duct(4 nos 75mm dia HDPE conduits) under
118 M&E EI-21-0223 29-Nov-21 Provision of Ducts under N2 Taxiway N2 taxiway of ADC working area as the demolition of the existing crossing duct of N2 taxiway on 29
Nov. 2021
EI-21-0023 Construction of the drainage pipe line at
- ADC re-submitted cost proposal for landside ICT area drainage pipe works in amount of JPY
119 Civil ADC-NOCD-LTR-C-21-0051 6-Mar-21 landside ICT area part A by changed
7,065,043 and BDT 15,913,873 on 14th Mar 2021
ADC-NOCD-LTR-C-21-0326 design
EI-21-0041
Design Change North Taxiway , instruction - ADC re-submitted Cost Proposal JPY 1,855,286 and BDT 3,230,712 on 13th Dec 2021
120 Civil ADC-NOCD-LTR-C-21-0124 24-Feb-21
to modify N2 & NE2 Taxiway - Other cost shall be claimed under remeasurement basis
ADC-NOCD-LTR-C-21-0322
Aviation Dhaka Consortium (ADC) 69 / 146
Monthly Report (Feb 2023)
No. Category Reference No. Instruction Date Description Remarks
- The Employer and the Engineer has given approval relocation of DESCO power line to start the
construction at EDW RAMP North & South side.In this regard, DESCO submitted the cost of
relocation work and necessary drawings. This relocation works should be immediately proceeded up
EI-21-0217 21-Nov-21 Relocation of DESCO Power Line at EDW
121 M&E through the coordination with DESCO
ADC-NOCD-LTR-ME-21-0084 12-Dec-21 RAMP (South/North) Area
- Requested to clarify and collect the permission for installation of underground cable laying and a
500kVA package type transformer (CIty Corporation/Road & Highwya/ Others) for installation of road
excavation transformer that requested to submit to DESCO on 12th Dec 2021
New Control Tower & Area 5 Domestic - NOCD issued EI for ADC to resubmit the revised drawing of New Control Tower & Area 5
122 Civil EI-22-0018 18-Jan-22
Terminal Access Road Lane Number Domestic Terminal Access Road Lane Number and submit cost proposal on 18th Jan 2022.
- Requested EI for the demolition of Existing Check Posts (Unused) Structures-3 nos. beside the
boundary wall on the VVIP road on 20th Jan 2022
ADC-NOCD-LTR-G-22-0020 Demolition of Existing Check Posts
123 Civil 20-Jan-22 - NOCD issued EI for the demolition of Existing Check Posts Structures with the requirement of
EI-22-0024 (Unused) Structures_3 nos.
submission of measured quantity and demarcation on 24th Jan 2022
- ADC submitted ICT area Guard House demolition plan on 25th Jan 2022
ADC-NOCD-LTR-C-21-0214, 0225 26-Sep-21, 18-Oct-21 - NOCD issued EI for VVIP Welcome road lighting at both side of the new VVIP road & requested to
124 M&E EI-21-0174 27-Sep-21 VVIP Welcome road lighting submit the detail cost proposal for installation of road light with electrical cables on 27th Sep 2021
ADC-NOCD-LTR-C-22-0045 02-Feb-22 - ADC re-submitted cost proposal in amount of JPY 1,303,381 and BDT 3,738,097 on 2nd Feb 2022
EI-21-0210 - NOCD instructed ADC to remove 14 no Trees and to relocate Street Light Post near Ansar Barak
ADC-NOCD-LTR-G-21-0129 with the request of cost proposal on 7th Nov 2021
ADC-NOCD-LTR-C-21-0235 Tree removal and Electric pole relocate at - Requested additional EI with the necessary information for stock pile location of the tree logs for
125 Civil 7-Nov-21
ADC-NOCD-LTR-C-21-0330 Area 3-1 near VVIP Road-3 convenience in taking over by the Employer on 19th Dec 2021
L-CLEN-21-1076 - NOCD request CAAB permission / necessary information on 21st Dec 2021
ADC-NOCD-LTR-C-22-0043 - Requested VO in amount of JPY 48,327 and BDT 770,744 on 2nd Feb 2022
- Requested EI for demolition of obstacles to construct the Road N and H in Area 5 on 29th Jan
① Electronic Display Boards on the Domestic Terminal Road("DTR"), ② Security wall on the DTR, ③ Parking lot
ADC-NOCD-LTR-C-22-0036 29-Jan-22 Demolition of existing facilities near BIMAN and building near the Biman, ④ Security wall & trees on T1 Road near Banga Bandhu Circle)
126 Civil
EI-22-0030 06-Feb-22 building
- NOCD issued EI to take necessary action to expedite the required consensus procedures with the
respective authorities on 6th Feb 2022
EI to additional demolition work of former - ADC submitted the cost proposal for Demolition Work of Former Drainage Structure and other
EI-21-0189 12-Oct-21
drainage structure and additional Demolition of existing RCC works approved through WIR.
127 Civil ADC-NOCD-LTR-C-21-0265 2-Nov-21
demolition work of existing RCC works - ADC submitted revised cost proposal in amount of JPY 15,773 and BDT 2,946,144 on 20th Feb
ADC-NOCD-LTR-C-22-0057 20-Feb-22
approved through WIR. 2022
- ADC submitted revised cost proposal for Pavement work at new Carpark in vicinity of Area 5 in
EI-21-0092 19-May-21
amount of JPY 3,665,763 and BDT 18,040,448 and noticed the cost proposal for drainage
ADC-NOCD-LTR-C-21-0199 8-Sep-21 Pavement Works and Curbstone for Road
128 Civil preparation in Area 5 and pavement works at new access road N to be submitted seperately
ADC-NOCD-LTR-C-22-0050 3-Feb-22 H, N and Carpark in Area 5
- ADC submitted revised cost proposal amounting to JPY 4,122,211 and BDT 20,967,053 on 23rd
ADC-NOCD-LTR-C-22-0069 23-Feb-22
Feb 2022
- NOCD requested ADC to submit MS with the schedule including Cost proposal for maintaining the
EI-22-0066 6-Mar-22 Method statement for maintaining the
129 Civil traffic in front of Domestic terminal building acc to handover the New Control Tower area including
EI-22-0066-01 9-Mar-22 traffic in front of Domestic terminal building
Domestic Terminal Car Parking on 6th Mar 2022
- NOCD requested ADC to submit for construction of 3 nos New Manhole and 100mm PVC Pipes for
New Manhole and PVC Pipes for Road
130 M&E EI-22-0088 23-Mar-22 use to LV cable for Road Lighting (New Manhole and pipe connect from Duct Bank Manhole Type-13-
Lighting Work at Biman’s Office, Area-5
1 to near Utility Building, Biman’s Office, Area-5) on 23rd Mar 2022
Suspend the pavement work in Zone3, - NOCD requested to suspend the pavement work in Zone3, Zone4 -Duct Bank as water supply pipe
141 Civil EI-22-0164 23-Jun-22
Zone4 - Duct Bank shall be installed into the Duct Bank excavation ditch on 23rd Jun 2022.
- Requested for EI & VO for cement stabilized sub-base course to avoid gap between the GSE
asphalt pavement and the concrete slab of T3 GSE entrance that NOCD commented through EDAC-
22-0828 (2nd Jun) on 7th Jun 2022
ADC-NOCD-LTR-C-22-0230 7-Jun-22 - NOCD requested to revise the relevant shop dwgs with the stabilization acc to attachment at the
142 Civil EI-22-0153 16-Jun-22 Cement Stabilized Subbase Course designated area in GSE road pavement area adjacent to the Apron concrete pavement area on 16th
EI-22-0171 5-Jul-22 Jun 2022
- NOCD instructed that compaction procedure of the sub-base course and base course shall be
carried out more carefully to avoid level difference at the junction of these pavement surfaces on 5th
Jul 2022
- NOCD requested to remove the special trees and plants from the existing site, then store them at
L-ADC-22-0267 26-Jun-22
the safe place after a joint site survey on 26th Jun and then NOCD requested to remove existing
ADC-NOCD-LTR-G-22-0198 20-Jul-22 Relocation of the special trees and plants
143 Civil trees subject to similar types of trees to be reinstated later stage by CAAB’s cost based on MOM
L-ADC-22-0301, L-ADC-22-0302 21-Jul-22, 21-Jul-22 along the Dhaka-Mymensingh highway
with RHD on 21st Jul 2022
ADC-NOCD-LTR-G-22-0220 2-Aug-22
- Requested to provide location for shifting of trees for EDW Works on 2nd Aug 2022
- NOCD requested to submit the cost reduction plan according to change of country of origin of
164 M&E EI-22-0280 26-Oct-22 Battery Issue for Rectifier-Inverter Panel
Battery for Rectifier-Inverter Panel (Europe/USA/Japan → Bangladesh) on 26th Oct 2022.
- NOCD requested for cost reduction for not supplying UL listed & FM approved GI pipe on 21st Sep
L-ADC-22-0428 21-Sep-22 Request for Cost Reduction for not
165 M&E 2022.
ADC-NOCD-LTR-C-22-0459 27-Oct-22 Supplying UL Listed/ FM approved GI Pipe
- Submitted cost reduction proposal amounting to JPY 1,453,247 on 27th Oct 2022.
- Submitted additional cost proposal amounting to JPY 271,174 and BDT 868,075 for a) Extension of
EI-22-0144 26-Aug-21 end diaphragm, b) Installation of temporary concrete barrier, c) Const. of temporary brick wall and d)
EI-21-0178 30-Sep-21 Const. of temporary drainage refering to issued EI's on 17th Jul 2022
ADC-NOCD-LTR-C-22-0265 17-Jul-22 Additional diaphragm and temporary - Submitted revised cost proposal for JPY 9,294,231 and BDT 15,141,130 with the confirmation of
166 Civil ADC-NOCD-LTR-C-22-0277 21-Jul-22 barrier at EDW (South) side agreement to NOCD's assessment on 26th Sep 2022
ADC-NOCD-LTR-C-22-0401 26-Sep-22 superstructure - NOCD issued VO for the additional diaphram and temporary barrier at EDW (South) side
L-ADC-22-0507 23-Oct-22 superstructure in amount of JPY 271,174 and BDT 868,075 on 23rd Oct 2022
L-ADC-22-0552 3-Nov-22 - NOCD instructed VO for additional diaphragm and temporary barrier at EDW (South) side
superstructure on 3rd Nov 2022
Request for Cost Reduction for Cooling - NOCD instructed cost reduction for not supplying cooling towers with direct driven fans on 3rd Nov
167 M&E EI-22-0286 3-Nov-22
Tower 2022
- ADC sent reminder for Removal of Trees and Bushes on 8th Mar and NOCD issued EI for ADC to
start the work on the removal of trees and bushes for drainage work and submit MS on 10th Mar
2022
ADC-NOCD-LTR-G-22-0007 9-Jan-22 - In line with NOCD's assesment, ADC submitted cost proposal amounting to JPY 2,182,511 and
ADC-NOCD-LTR-G-22-0085, 0185 8-Mar-22 BDT 8,685,098 on 2nd June 2022
EI-22-0072 10-Mar-22, 8-May-22 - NOCD issued EI for Construction of Road O-1 Area 5 on 3rd Aug 2022
Removal of trees and bushes for Drainage
168 Civil ADC-NOCD-LTR-C-22-0213 2-Jun-22 - NOCD issued variation order for the demolition works along the highway and removal of obstruction
Work from Foot bridge to Gate-5
EI-22-0198 3-Aug-22 at EDW(North) and from the bridge to Gate#5 in amount of JPY 2,182,511 and BDT 8,685,098 on
L-ADC-22-0504 23-Oct-22 23rd Oct 2022.
L-ADC-22-0561 6-Nov-22 - The variation for the Demolition Works along the Highway and Removal of Obstructions at EDW
(North) and from the Bridge to Gate 5 is 2,182,511 JPY and 8,685,098 BDT. Pursuant to G.C. 13.1
and 13.3, NOCD instruct Variation for the Demolition of the Existing Guard Room on VVIP Road 3
and informed that this letter supersedes L-ADC-22-0504 on 6th Nov 2022.
- NOCD requested ADC to submit cost proposal with the provision of detailed information of VVIP
Lounge Fitting design such as detailed drawings, specification and BOQ on 3rd Jul 2022
- Notified the Contractor's right for entitlement of additional time and cost owing to NOCD's 184 days
of delay for design issuance compared to baseline programme on 13th Jul 2022
- NOCD requested ADC to clarify the details why the fitting out work for VVIP/VIP lounge in T3 affects
the critical path in Master Schedule on 19th Jul 2022
- Clarified the criticality of VVIP/VIP lounge area showing that work is getting delayed and it will impact
the critical path based on the total float time, planned finish date, etc in the baseline schedule on 27th
L-ADC-22-0280 3-Jul-22
Jul 2022
ADC-NOCD-LTR-C-22-0257 13-Jul-22
- NOCD instructed ADC to submit an estimation based on this information and submit shop
L-ADC-22-0296 19-Jul-22
drawings and material approval on 6th Oct 2022
ADC-NOCD-LTR-C-22-0284 27-Jul-22
- Requested NOCD to provide the necessary info for ADC to conduct procurement process for
L-ADC-22-0332 7-Aug-22 Request Cost Proposal of VVIP Lounge
169 Building acquiring quotation from the Subcontractors and finzlaize the Subcontract engagement (Updated
L-ADC-22-0454 6-Oct-22 Fitting Design in T3
BOQ, Revised drawings/Specifications/ Any other missing/incomplted information & details) with the
ADC-NOCD-LTR-G-22-0286 13-Oct-22
'List of insufficient information' on 13th Oct 2022
L-ADC-22-0555 3-Nov-22
- NOCD issued revised documentation (BOQ/Spec/Drawings) with ambigious/insufficient info in
ADC-NOCD-LTR-G-22-0319 5-Nov-22
response to the missing items issued by ADC and requested ADC to submit estimated price on 3rd
ADC-NOCD-LTR-C-22-0538 13-Nov-22
Nov 2022
- Requested NOCD to issue the EI for the Contractor to engare the work for VVIP/VIP facilities
allcocated under Div.-80700 of Provisional Sum in the BOQ and several descriptions of General
Notes & Instruction included in the drawings for VVIP/VIP Lounge to be adjusted or removed in order
to reflect current situations at Site on 5th Nov 2022
- Submitted Tender Report of T3 VIP/VVIP Lounge work (3-bidder quotation) and requested NOCD to
issue an instruction to engage the works with conditions of subcontract, construction schedule,
updated latest drawings, Specification, BOQ nd relevant documents on 13th Nov 2022.
- NOCD instructed to relocate the BTCL cables at EDW south-east in the location for P-1 to P-4 and
EI-22-0322 1-Dec-22 prepare estimated cost for approval on 1st Dec 2022
ADC-NOCD-LTR-C-22-0526 4-Dec-22 Relocation of BTCL Cables found at P-1 to - Submitted cost proposal amounting to BDT 9,247,417 for cable relocation on 4th Dec 2022
179 M&E
ADC-NOCD-LTR-G-22-0374 12-Dec-22 P-4 location on south-east EDW. - Requested EI for the relocation of BTCL cable to avoid further delay of piling works and adverse
EI-22-0334 13-Dec-22 impact on the overall construction schedule of the Steel Box Girder Bridge on 12th Dec 2022
- NOCD issued EI on the BTCL cable to start inspection works in RHD South area on 13 Dec 2022
- NOCD instructed to remove tree prior to demolition of fence near existing VVIP terminal area on 4
Sep 2022.
- Submitted cost proposal for removal of trees amounting to BDT 3,273,435.00 on 19th Sep 2022
- Submitted cost proposal for demolition of existing fence after Installation of new fence and
EI-22-0227 4-Sep-22 demolition of existing boundary wall in the amount of JPY 3,518,312 and BDT 433,196 on 11th Oct
ADC-NOCD-LTR-C-22-0389 19-Sep-22 2022 (including 22.7% adjustment)
ADC-NOCD-LTR-C-22-0411 11-Oct-22 EI for Removal of Tree, Fence Installation - Accepted NOCD assessment and submitted revised Cost proposal amounting to JPY 2,831,860
180 Civil ADC-NOCD-LTR-C-22-0451 24-Oct-22 and Demolition of Boundary Wall at Area 5 and BDT 239,360 on 24th Oct 2022.
L-ADC-22-0571 8-Nov-22 Pond 21 - NOCD approved the variation for Removal of Trees at Area-5, Pond-21 near the VVIP Terminal for
L-ADC-22-0579 8-Nov-22 amount of BDT 3,273,435 on 8th Nov 2022.
ADC-NOCD-LTR-G-22-0383 19-Dec-22 - NOCD approved the variation for the Fence Installation and Demolition of the Boundary Wall at
Area 5 Pond 21 is 2,831,860 JPY and 239,360 BDT on 8th Nov 2022.
- Requested the Engineer's comments on the removal of logs and barks of cut down trees around
the existing VVIP terminal to a seperate location in order to avoid any safety hazard at Site and the
smooth progress of works on 19th Dec 2022
- NOCD instructed to provide Electric Room Heater and Automatic Air Freshener for CAAB on 3rd
EI-23-0004 3-Jan-23 Electric Room Heater and Jan 2023
190 General
ADC-NOCD-LTR-C-23-0013 9-Jan-23 Automatic Air Freshener for CAAB - Submitted cost(BDT 9,636) on 9th Jan 2023, which had been handed over to the Engineer on 5th
Jan 2023
Demolishing existing Sewer pipe and - NOCD instructed to demolish existing RCC pipe culvert and constructe new box culvert and
191 Civil EI-23-0009 10-Jan-23
construct new box culvert, Area-5 prepare const. drawing and BOQ data for the same on 10th Jan 2023
EI-22-0310 21-Nov-22 Cost Proposal for Additional Drainage at - NOCD provided EI for additional drainage for Pier Extension (North) on 21st Nov 2022
192 Civil
ADC-NOCD-LTR-C-23-0018 11-Jan-23 T3 Pier Extension (North) - Submitted cost proposal of JPY 18,720,098 and BDT 45,795,975 on 11th Jan 2023
- NOCD requested for consumables for PD's office on 19th Dec. 2022
EI-22-0342 19-Dec-22
Engineer’s instructions to provide - Submitted cost proposal with quotations amounting to BDT 265,043 on 15th Jan. 2023
ADC-NOCD-LTR-C-23-0023 15-Jan-23
193 General consumable items for Project Director's - Submitted cost proposal for Computer, which was omitted in the previous quotation on 18th
ADC-NOCD-LTR-C-23-0033 18-Jan-23
Office Jan. 2023
L-ADC-23-0049 19-Jan-23
- NOCD approved items except for Computer on 19th Jan 2023
- NOCD issued drawings of doors and windows for RFFS main on 13th Dec 2022
EI-22-0337 13-Dec-22 Cost Proposal for Additional Aluminum
194 Building - Submitted cost proposal for additional aluminium windows, louvers and doors for other buildings
ADC-NOCD-LTR-C-23-0036 21-Jan-23 Windows and Doors for Other Buildings
amounting to JPY 11,096,441 and BDT 1,610,906 on 21st Jan 2023
- NOCD notified that LPS is required for Cooling Tower and water tank and instructed to submit
EI-22-0307 17-Nov-22 Lightning Protection Works for Water Tank details layout drawing on 17th Nov 2022 and ADC submitted cost proposal based on approved
195 M&E
ADC-NOCD-LTR-C-23-0040 24-Jan-23 and Cooling Tower design for lightning protection works amounting to JPY 7,490,410 and BDT 1,391,524 on 24th Jan
2023
- NOCD issued EI to resubmit of the revised shop drawing and cost proposal
EI-22-0011 11-Jan-22 - ADC submitted Cost Proposal in the amount of JPY 1,711,160 and BDT 1,894,417 on 6th Jun
ADC-NOCD-LTR-C-22-0226 6-Jun-22 Revision of VVIP Road-3 Vertical 2022.
196 Civil
ADC-NOCD-LTR-C-22-0283 25-Jul-22 Alignment and Additional Sidewalk Design - Confirmed agreement with the NOCD's assessment and submitted revised cost proposal for the
L-ADC-23-0074 31-Jan-23 amount of JPY 1,786,725 and BDT 1,977,697 on 25th Jul 2022.
- Approved the VO of JPY 1,786,725 and BDT 1,977,697 on 31st Jan 2023 (Closed)
- NOCD issued VO to ADC on the additional work of New Bridge on VIP Road 3 on 2nd Jan 2022
- ADC submitted cost proposal for the BP and Others of the Cable Stayed Bridge on 17th Apr 2022
- NOCD instructed to cancel cable stayed bridge and to construct the PSC slab girder
EI-22-0002 2-Jan-22
bridge on 31st May and requested to submit shop drawing on 7th June and submitted cost proposal
EI-22-0016 17-Jan-22
for decoration cable stayed bridge excluding bored pile works amounting JPY 17,165,925 and BDT
EI-22-0058 27-Feb-22
134,811,466 on 4th Jul 2022
ADC-NOCD-LTR-C-22-0094 4-Apr-22
- Based on subcontractor's revised quotation submitted revised Cost proposal amounting to
ADC-NOCD-LTR-C-22-0145 17-Apr-22
JPY 17,549,507 and BDT 170,116,910 and notified that offer is valid upto end of Oct 2022
ADC-NOCD-LTR-C-22-0094-01 17-Apr-22, 31-May-22
- Notified that the Contractor is unable to executethe it considering the prolonged delay in finalization
EI-22-0131, EI-22-0139 7-Jun-22
Additional work of New Bridge on VVIP of Subcontractor (135 days delay as of 14th Nov) and uncertainty of new quotation to be within the
197 Civil ADC-NOCD-LTR-C-22-0255 4-Jul-22
Road 3 expected limits of the Employer on 14th Nov 2022. Chairman instructed to do the work based on
ADC-NOCD-LTR-C-22-0326 17-Aug-22
ADC's proposed amount after discussion with NOCD
ADC-NOCD-LTR-C-22-0381 14-Sep-22
- Forwarded CRBC's (subcon) letter and informed to NOCD that ADC cannot execute decoration
ADC-NOCD-LTR-C-22-0487 14-Nov-22
cable stay bridge works and requested EI for going back to original design of drainage box culvert on
ADC-NOCD-LTR-C-22-0506 24-Nov-22
24th Nov 2022
ADC-NOCD-LTR-C-23-0022 15-Jan-23
- Submitted cost proposal amounting to BDT 198,432,970 (excluding sheet piling) based on
ADC-NOCD-LTR-C-23-0053 29-Jan-23
quotation of Subcon which was confirmed by Chairman meeting on 15th Jan. 2023
L-ADC-23-0077 31-Jan-23
- Submitted revised cost proposal based on meeting with CAAB, BUET & NOCD amounting to BDT
208,385,400 on 29th Jan 2023.
- Approved VO for amount of BDT 208,385,400 on 31st Jan 2023.
- Instructed to cooperate with DESCO and deploy sufficient trained manpower for temporary cable
EI-23-0022 24-Jan-23 Temporary Relocation of DESCO cables
200 Civil relocation and asked to submit Cost proposal for Variation work on 24th Jan 2023
ADC-NOCD-LTR-C-23-0070 1-Feb-23 at FDEE Exit Ramp area
- Submitted cost proposal for an amount of BDT 1,907,574 on 1st Feb
- NOCD instructed to install Temporary Barrier Wall between T3 and Pier Extension on 24th Oct
EI-22-0051-12 24-Oct-22 Temporary Barrier Wall between T3 and
201 Building 2022.
ADC-NOCD-LTR-C-23-0072 2-Feb-23 Pier Extension
- Submitted cost proposal smounting to JPY 49,128,418 and BDT 26,838,969 on 2nd Feb
- NOCD innstructed ADC to remove the cantilever slab on 2nd floor and submit VO proposal on 20
Nov
EI-22-0309 20-Nov-22 - Submitted VO cost for demolishing the 2nd floor cantilever slab for an amount of BDT 83,479 on 9
ADC-NOCD-LTR-C-23-0015 9-Jan-23 Jan
Cancellation of extended 2nd floor
202 Building-1 L-ADC-23-0039 15-Jan-23 - NOCD declined cost proposal and advised to use VO-35 rate on 15th Jan
cantilever slab
ADC-NOCD-LTR-C-23-0060 30-Jan-23 - Submitted revised cost considering rates of labour from BOQ for an amount of BDT 71,336 on 30th
L-ADC-23-0080 1-Feb-23 Jan
- NOCD approved VO amount of BDT 71,336 and stated that this approval is an execptional case
and should not be considered as an exmple in other places on 1st Feb 2023 (Closed)
- NOCD issued EI for ADC to proceed the demolition work of the Guard House in ICT area and to
EI-22-0014 13-Jan-22 submit demolition plan and cost estimation on 13th Jan 2022.
ADC-NOCD-LTR-C-22-0020 25-Jan-22 - NOCD reviewed ADC demolition plan and forwarded it to CAAB on 30th Jan 2022
L-ADC-22-0037 30-Jan-22 - Submitted cost proposal for demolition of ICT guard house and adjacent fence installation in
203 Building-2 Demolition of Guard House in ICT area
ADC-NOCD-LTR-C-22-0253 3-Jul-22 amount of JPY 18,990 and BDT 748,400 on 3rd Jul 2022.
L-ADC-22-0544 1-Nov-22 - NOCD reviewd that unit rate is as per approved rate, but the WIR of the quantity mentioned in cost
L-ADC-23-0085 2-Feb-23 proposal has no approval and requested to re-submit with proper documents on 1st Nov 2022
- As per mutual discussion NOCD approved the proposed cost variation on 2nd Feb 2023 (Closed)
EI-22-0161 23-Jun-22 H-Pile Earthing installation layout plan for - NOCD istructed to install H-pile for pier extension building on 22nd Jun 2022
204 M&E
ADC-NOCD-LTR-C-23-0071 1-Feb-23 Pier Extension Building - Submitted cost proposal smounting to JPY 8,456,794 and BDT 3,127,254 on 1st Feb 2023
1 0 .2 Contractor's Variation Request (Closed items removed and outstanding items only listed here)
No. Reference No. Issue Date Description Remarks
ADC-CAAB-CVI-BC-20-0001
Request for EI and approval of cost
57 Civil L-ADC-20-0037/20-0053/ 0057 8-Jun-20 - ADC sunmitted cost proposal JPY 4,676,450 BDT 20,359,382 on 29th Mar 2021
ADC-NOCD-LTR-21-CC-0074 proposal for site preparation of ECT area
RFI-BC2-21-0639 - NOCD required the demolition and rebuilding of fence and open drain in ICT
Demolition and rebuilding of fence and
58 Civil ERRl-21-0024 19-Jan-21 area as ERRI-21-0024 on 17th Jan 2021
open drain in ICT area
ADC-NOCD-LTR-C-21-0014 - Requested to issue VO instruction on 19 Jan 2021
ADC-CAAB-LTR-ME-21-0005 17-Feb-21 New item cost info for AGL system (HDPE
59 M&E - NOCD commented that the amount of some items needs to be adjusted on 7th Mar 2021
L-ADC-21-0059 7-Mar-21 secondary cable)
ADC-CAAB-LTR-ME-20-0006 24-Sep-20 - Requested EI and VO for the relocation of cable for GA hangars as the Employers MT substation
ADC-NOCD-LTR-ME-21-0009 9-Mar-21 Relocation of cable for General Aviation demolished and re-submitted cost proposal of JPY 230,500 and BDT 8,272,580 for the installation of
60 M&E
ADC-NOCD-LTR-ME-21-0016 23-Mar-21 Hangars a new electrical cable route. NOCD replied not to issue VO as the provision of power supply to GA
L-ADC-21-0077 29-Mar-21 until handover is Contractor's responsibiity
- Requested EI for demolition of existing box culvert (Apprx. 40m x 10 m x 6m size) in the Area 5 not
ADC-NOCD-LTR-C-21-0081 7-Apr-21
available in the BOQ on 7th April 2021
61 Civil ADC-NOCD-LTR-C-21-0161 4-Aug-21 Demolition of existing Box Culvert in Area 5
-Cost proposal submitted JPY 30,668 BDT 2,199,025 on 4 August 2021
ADC-NOCD-LTR-C-21-0161-1 9-Sep-21
-Revised Cost proposal submitted JPY 30,668 BDT 1,472,241 on 9 Sept. 2021.
- NOCD agreed ADC proposal in RFI-CC-21-0730 and requested to submit cost proposal
Cost Proposal for FHS Pit Base Materials
62 Civil ADC-NOCD-LTR-C-21-0086 10-Apr-21 - Submitted cost proposal of JPY 29,616 and BDT 127,635 for new FHS pit base materials
(from crushed stone to sand)
(compacted sand THK200 + polythene sheet 1000g)
Removal and reinstatement of the existing - Requested EI for removal and reinstatement of the existing asphalt pavement at North Landside
63 Civil ADC-NOCD-LTR-C-21-0082 18-Apr-21 Asphalt pavement at North Landside for due to the change of duct bank location from footpath area to the paved road which is different from
duct bank tender drawing on 18th April 2021
Rebuilding retaining wall at the former - Requested EI to rebuild the existing retaining wall in order to permanently close Ansar pocket gate
64 Civil ADC-NOCD-LTR-G-21-0037 4-May-21
Ansar camp so that it ensurie safe & secure site conditions on 4th May
Demolition of Consultant’s Airside office - Requested EI to demolish existing Consultant's airside office which is provisional sum items in the
65 Civil ADC-NOCD-LTR-C-21-0118 23-May-21
(PS) Contract
Additional Steel Column for Facade
66 Building-1 ADC-NOCD-LTR-C-21-0129 10-Jun-21 - Requested EI to install additional steel column for façade support at 1st floor in TE3
Support
- ADC Submitted cost proposal (JPY 15,096,767 BDT 1,190,434) on 20th June 2021 regarding
Additional Security fence and Gate Works
67 Civil ADC-NOCD-LTR-C-21-0135 20-Jun-21 additional security fence installation for new access road beside biman and new car park and
at gate 5
drainage preparation in vicinity of Area 5 and requested VO approval
Change of concrete grade from 25MPA to
68 Civil ADC-NOCD-LTR-C-21-0150 14-Jul-21 30MPA for main structure of Road - Requested VO with the cost breakdown reflecting new rates on 14th Jul 2021
Underpass Box Tunnel
- Requested VO as supply of Printer, Scanner is additional to the Contract in response to NOCD
L-ADC-21-0127 27-Jun-21 Providing Printer, Scanner and Desktop
letter (L-ADC-21-0127) on 19th July 2021
69 Common ADC-NOCD-LTR-C-21-0155 19-Jul-21 Computer to Chief Engineer's office for
- NOCD issued another letter requesting that Desktop Computer be added in addition to Printer and
L-ADC-21-0154 1-Aug-21 official use
Scanner to be supplied to CAAB on 1st Aug 2021
- Requested EI for it on 8th April 2021
ADC-NOCD-LTR-C-21-0084 8-Apr-21 Demolition of Existing Southern Service
70 Civil - Submitted cost proposal of JPY 218,197 and BDT 749,076 for the 'Demolition of Existing Pipe
ADC-NOCD-LTR-C-21-0178 22-Aug-21 Road and Pipe Culvert at N1 Taxiway
Culvert at N1 Taxiway' and demolition of road is remeasurable baed on BOQ on 22nd Aug 2021
- Requested VO for the relocation of HT Cable (from the Power House and Fire Station to the AGL
71 M&E ADC-NOCD-LTR-C-21-0180 23-Aug-21 Relocation of the HT Cable at Area 7-2 Substation) for new N1 Taxiway construction in Area 7-2 and submitted the cost proposal of JPY
1,697,836 and BDT 78,572,986 on 23rd Aug 2021
- Agreed with ADC to commence at the meeting on 8 Aug 2021 and request EI as follows.
1) for additional work (new fence installation-jet blast, decorative fence)
2) for activation of PS (demolition of monument wall, substation & floodlighting and installation of new Padma oil road
72 Civil ADC-NOCD-LTR-C-21-0177 17-Aug-21 Initial works for right side Pier extension 3) for the Engineer's coordination w/ CAAB for urgent commencement of works (CCTV, electric calbe & fence, lighting
pile, PD office and communication tower)
4) for early handover (for demolition of existing fence, apron & access, clearing & grubbing, soil investigation, soft soil
removal & embankment)
- Due to design change of piers, some girder's sapn lenght changed to 24.5m, 25.5m and 26.5m so
EI-21-0081 28-Apr-21
New rate for chagned PC girder span requested approval of new rate which is pro-rata of original BOQ rate
ADC-NOCD-LTR-C-21-0190 31-Aug-21
81 Civil length of EDW south side substructure - Requested VO with the unit rate agreed with Engineer(email dated 20th Sep) of changed PC girder
ADC-NOCD-LTR-C-21-0209 22-Sep-21
pier 14, 15, 16, 17, & 18 span length on 22nd Sep 2021
L-CLEN-21-0752 29-Sep-21
- NOCD requested CAAB to review & confirm ADC's proposed unit rate on 29th Sep 2021
- Requested VO for additional new Headwall-HW-NT2-NE1-05 at existing Box Culvert connected to
ADC-NOCD-LTR-C-21-0208 19-Sep-21 Existing Box Culvert connected to
82 Civil NT2/NE1-03 Trapezoidal Channel with the revised cost proposal of JPY 311,471 and BDT 800,128
ADC-NOCD-LTR-C-21-0226 30-Sep-21 NT2/NE1-03 Trapezoidal Channel
on 30th Sep 2021
- Requested NOCD to review and select the model for sanitary ware that previously confirmed to
Selection Model for Sanitary wares at
83 M&E ADC-NOCD-LTR-ME-21-0050 23-Sep-21 change TOTO for TE-3, American Standard for MCP & Other Buildings and than ADC will submit the
Terminal 3, MCP and Other Buildings
cost for VO on 23rd Sep 2021
-Request for Variation order Unit Rate of Concrete Kerb Type-CT-1 (Drainage Type) and Wire Net in
ERRI-21-0305 3-Aug-21.
BOQ
84 Civil ADC-NOCD-LTR-C-21-0224 29-Sep21 Concrete Kerb Type-CT-1 (Drainage type)
-ADC agreed NOCD Assessed rate for Concrete Kerb Type-CT-1 (Drainage Type) per meter -Yen
ADC-NOCD-LTR-C-21-0237 11-Oct-21
2,604 BDT 2,300 and Wire Net Yen 131 BDT 2,067 each.
Supply and installation of Con'c Kerb CT-1 - Requested VO for new rate of new Con'c Kerb CT-1 (Drainage Type) and wire net in different areas
85 Civil ADC-NOCD-LTR-C-21-0237 10-Oct-21
and Wire Net in different areas of the PJT of the Project according to Engineer's drawing (EDAC21-0974) and letter on 10th Oct 2021
Pile works of EDW interfered by trees
86 Civil ADC-NOCD-LTR-C-21-0235 18-Oct-21 - Requested EI for removing 19 numbers of trees obstructing piling works for EDW on 18th Oct 2021
along the highway
Demolition of existing underground Box - Requested EI for the demolition of the existing underground box culvert due to confliction of Box
87 Civil ADC-NOCD-LTR-C-21-0271 7-Nov-21
Culvert near South EDW Bridge Culvert and South EDW Bridge Abutment/Pier on 7th Nov 2021
Additional steel beam around the deck slab
88 Building ADC-NOCD-LTR-C-21-0269 9-Nov-21 - Requested EI for additional steel beam around the slab opening in ICT and ECT on 9th Nov 2021
opening in ICT and ECT
Aviation Dhaka Consortium (ADC) 85 / 146
Monthly Report (Feb 2023)
No. Reference No. Issue Date Description Remarks
89 Building ADC-NOCD-LTR-C-21-0284 17-Nov-21 PHC Test in IPP & IPR - Requested VO for PHC Test in IPP & IPR which missed in BOQ of IPP & IPR on 17th Nov 2021
- Requested proposed additional unit rate of BDT 715.00/㎥ in order to comply with Engineer's new
ADC-NOCD-LTR-C-21-0083 requirement and requested the Engineer to issue VO but rejected ADC's cost proposal as Revised
15-Apr-21
L-ADC-21-0230 Mix Design for Crushed Aggregate Base Course is within Specification’s requirement
90 Civil 31-Oct-21 Change of base course mix proportion
ADC-NOCD-LTR-C-21-0274 - Requested VO in amount of JPY 2,619 per Cum and BDT 8,178 per Cum on 10th Nov and noticed
10-Nov-21
ADC-NOCD-LTR-C-21-0286 that delayed confirmation incur adverse impact on progress of works and requested approval of cost
proposal by 30th Nov on 17th Nov 2021
Demolition of Monuments, Garden and
ADC-NOCD-LTR-C-21-0312 - Requested EI for demolition of Monuments, Garden and Light Poles on the north side of the EDW
91 Civil 2-Dec-21 Light Poles on the Dhaka-Mymensingh
ADC-NOCD-LTR-C-21-0331 on Dhaka-Mymensingh Highway at the earliest again on 19th Dec 2021
Highway
92 M&E ADC-NOCD-LTR-C-21-0313 6-Dec-21 Missing items are in respective M&E BOQ - ADC Request for Variation Order (VO) for additional Items at ECT, ICT IPP & IPR
Additional Temperature Sensors for roof - Requested VO for Additional Space Temperature Sensors for roof smoke fan at T3 issued thru
93 M&E ADC-NOCD-LTR-C-21-0320 13-Dec-21
smoke fan at Terminal-3 ERRI-21-0475 on 13th Dec 2021
- Requested EI for surge arrestor installation at 11KV Switchgear at T3 and other buildings acc to
Installation of Surge Arrester for 11KV
94 M&E ADC-NOCD-LTR-ME-21-0092 30-Dec-21 electrical specification, Section-I, Division-10104, sub-clause 1(n) “Lighting & Power line surge
Switchgear at T3 and other buildings
Protection shall be provided for all electrical system acc to the Engineer’s instruction”
IP rating of Test Link Box at Other - Requested EI spcifying IP rating of IP41/44 for the Test Link Box of Other Buildings which was not
95 M&E ADC-NOCD-LTR-ME-22-0001 3-Jan-22
Buildings mentioned in Specification on 3rd Jan 2022
19-Dec-21, 26-Dec-
ADC-NOCD-LTR-C-21-0328, 0338 - Requested VO for cost impact due to CAAB's requirement to reutilize the trees for T3 landscaping
21
ADC-NOCD-LTR-C-22-0011 Removal and replantation of trees in the works with cost proposal amounting to JPY 748,728 on 19th Dec 2021
96 Civil 10-Jan-22
EI-22-0024 VVIP Terminal Area - Submitted revised cost proposal in amount of BDT 348,008 reflecting NOCD-ADC meeting result
24-Jan-22
ADC-NOCD-LTR-C-22-0044 on 2nd Feb 2022
02-Feb-22
- Requested VO for Cable Tray and Trunking at other buildings which is not reflected in BOQ (except
Terminal-3) in amount of JPY 66,838,145 and BDT 11,928,538 on 13th Jan 2022
ADC-NOCD-LTR-C-22-0015 13-Jan-22
Cable Tray and Trunking at other buildings - NOCD issued recommendation letter to CAAB of issuing VO for the Cable Tray and Trunking at
97 Civil L-CLEN-22-0114 01-Feb-22
(ICT/ECT and MLCP) other buildings (ICT/ECT and MLCP) on 1st Feb 2022
ADC-NOCD-LTR-C-22-0391 02-Oct-22
- Submitted revised cost proposal in amount of BDT 48,779,967 for the change of quantities and
materials as per the site requirement of ICT/ ECT/ MLCP/ GH/ STP/ FFS/ AGLS on 2nd Oct 2022
EI-22-0017 17-Jan-22
98 M&E Additional PAC and Fans at MCP - Requested VO in amount of JPY 5,567,252 and BDT 1,202,032 on 9th Feb 2022
ADC-NOCD-LTR-C-22-0024 9-Feb-22
ADC-NOCD-LTR-C-22-0032 06-Feb-22 Relocation of DESCO Overhead line at - Requested in amount of BDT 10,378,969 on 6th Feb 2022
99 M&E
L-CLEN-22-0173 14-Feb-22 EDW area - NOCD submitted reviewed cost proposal to CAAB in amount of BDT 8,211,988.4 on 14th Feb 2022
EI-20-0093 03-Dec-20 - Requested VO regarding the addition of Lean Con'c and Polythene sheet under the footing con'c of
Additional works at Floodlighting
100 Civil ADC-NOCD-LTR-C-22-0030 27-Jan-22 Apron Floodlighting mast on 27th Jan and submitted revised cost proposal in amount of JPY 230,532
Foundation
ADC-NOCD-LTR-C-22-0070 27-Feb-22 and BDT 838,254 for additional works at floodlighting foundation on 27th Feb 2022
ADC-NOCD-LTR-C-21-0245 21-Oct-21 - Requested for VO due to change in U/R of rebar of Item No.1.2 from JPY 80 to JPY 80,000
Correction Request for U/R of rebar of
L-ADC-21-0227 28-Oct-21 considering PIT case which NOCD issued and Contractor agreed in good faith on 19th Oct 2021
101 Building-2 Item No.1.2 - Chapter 30420 Tunnel
ADC-NOCD-LTR-C-22-0063 22-Feb-22 - NOCD rejected ADC's new rate on 28th Oct and ADC claim in another way after the discussion
Structure Works
L-ADC-22-0086 3-Mar-22 with NOCD but NOCD rejected ADC request again on 3rd Mar 2022
ADC-NOCD-LTR-ME-22-0010 24-Feb-22 Relocation of existing cable route and hand - Requested Employer's immediate relocation of existing electical cable route & hand hole at
102 M&E
L-ADC-22-0082 2-Mar-22 hole at Area 6-1 (Existing south Taxiway) Area 6-1 or issuance of EI to relocate on 24th Feb 2022
- Request for VO for design change to larger 90kw motor from 45kw motor in amount of JPY
ADC-NOCD-LTR-C-22-0071 27-Feb-22 Change Design of external fire Hydrant
103 M&E 3,340,460 and BDT 2,568,064 on 27th Feb 2022
L-ADC-22-0091 7-Mar-22 pump
- NOCD replied additional requirement+G258:G259
Landside Drainage Modification Area 4 - Submitted cost proposal for Manhole, Concrete pipes Culvert installation in magnitude of JPY
104 Civil ADC-NOCD-LTR-C-22-0082 7-Mar-22
South Part-C 623,311 and BDT 1,747,082 (remeasurement basis) on 7th Mar 2022
Construction of Draignage at Existing - Requested VO for Construction of Draignage at Existing Apron Taxiway with cost proposal
113 M&E ADC-NOCD-LTR-C-22-0115 29-Mar-22
Apron Taxiway amounting to BDT 429,397,034 on 29th Mar 2022
ADC-NOCD-LTR-C-22-0033 06-Feb-22
- Requested VO in amount of BDT 9,799,796 on 6th Feb 2022
L-CLEN-22-0172 14-Feb-22 Relocation of DESCO Under ground HT
114 M&E - NOCD submitted reviewed cost proposal to CAAB in amount of BDT 7,753,737.2 on 14th Feb 2022
ADC-NOCD-LTR-G-22-0100 28-Mar-22 cable at EDW area
- Noticed the delay for relocation of DESCO Power Cable Line at EDW Area on 6th Apr 2022
ADC-NOCD-LTR-C-22-0131 06-Apr-22
3rd Party testing of cable conduit & Tray at - Requested VO for 3rd Party testing of cable conduit & Tray at BUET that verbally instructed by
118 M&E ADC-NOCD-LTR-C-22-0196 16-May-22
BUET NOCD regarding site sample with the cost proposal in amount of BDT 206,790 on 16th May 2022
ADC-NOCD-LTR-C-22-0199 23-May-22 Notification of Variation for Additional - Requested variation order for pressure tank(200 liters) at deep well 1 to 3 that were not included in
119 M&E
L-ADC-22-0217 25-May-22 Pressure Tank at Deep well 1 to 3 the Contract Drawings++
- Requested clarification of usage with dry mix mortar for Sidewalk base material as Specification
120 Civil ADC-NOCD-RFI-CC-22-1345 31-May-22 Clarification for Sidewalk base material mentioned (Tender drawing, BOQ mentioned "compacted sand") and noticed cost to be increase if
so on 31st May 2022.
- Requested variation order for overflow piping, bird nets and manholes that were not included in the
Notification of Variation for Additional
ADC-NOCD-LTR-C-22-0203 23-May-22 Contract Drawings but added in the shop drawing by the Engineer on 23rd May 2022
121 M&E Overflow Piping, Bird Nets and Manhole at
L-ADC-22-0240 8-Jun-22 - NOCD cancelled the additional overflow pipe and manhole and requested to submit final additional
LPS-1 & LPS-2
cost details except additional overflow pipes and manholes on 8th June 2022.
Building works regarding Transformer - Requested EI for building works for the fence of outdoor 33/1kv oil type transformer fixing on RCC
122 M&E ADC-NOCD-LTR-ME-22-0036 2-Jun-22
base and fencing base on 2nd June 2022
Application of TOC for the Part of Works - Requested NOCD to issue a TOC. However, the Engineer's comment to mitigate asphalt
123 Civil ADC-NOCD-LTR-G-22-0170 14-Jun-22 related to Airside VVIP Road and Airport pavement gap near BAF gate will be an additional work and require EI and VO as per Sub-Clause 3.3
Service Road-1 and Clause 13.
- Requested VO(BDT 46,897,029) which was confirmed by Chairman and NOCD recommneded
ADC's proposal on 15th Feb 2022and NOCD told ADC to commence it and evaluation of cost to be
L-CLEN-22-0134 08-Feb-22 informed later on 24th Mar 2022, and submitted revised cost proposal in amount of BDT 50,182,221
ADC-NOCD-LTR-C-22-0056 14-Feb-22 on 17th Apr 2022
L-CLEN-22-0177 15-Feb-22 - NOCD noticed to ADC that up escalators shall be installed on the Foot Over Bridge along with the
L-CLEN-22-0129 24-Mar-22 stairs and requested to re-submit revisions of the design and the cost proposal accordingly on 29th
124 Civil Relocation of pedestrian bridge works
ADC-NOCD-LTR-C-22-0056-01 17-Apr-22 May 2022
L-ADC-22-0223 29-May-22 - NOCD requested to submit revised drawings in consideration of the expanded walking path layout,
L-ADC-22-0256 19-Jun-22 revised cost proposal and other special notes and considerations on 19th Jun 2022.
ADC-NOCD-LTR-G-22-0177 23-Jun-22 - ADC informed that it is not in a position to take up the work since it is not in SOW or Instructed by
Engineer. However, it can cooperate if EI is issued stating a) Design is under NOCD, b) Work
executed by RHD nominated subcontractor, c) ADC will only be paymaster, on 23rd Jun 2022
- Requested VO for change from base to shallow and from hand hole type B&D to type A, where
have reseulted in higher length of cables as the transformers are re-located from directly under the
AGL fixtures to the side of the taxiway/runways. Proposal amounting JPY 141,233,341 and BDT
217,461,673
ADC-NOCD-LTR-C-22-0128 23-Apr-22 - NOCD cannot finalize evaluation without additional evidence and requested ADC to submit
Requesting Variation approval for the New I
125 M&E L-ADC-22-0243 9-Jun-22 breakdown of original contract of the following items, and manufacture’s quotation of handhole pit
tem cost as per change of AGL System
ADC-NOCD-LTR-ME-22-0044 21-Jun-22 cover on 9th Jun 22
- ADC informed main contract concept was based on deep-base box but at HSIA shallow bases are
used commonly; in BOQ Hand-hole items and pits are not considered as Class E600 pit covers as
they are far from runway. This is the main reason for price gap. ADC provided comparison review for
other CAAB project hand-hole subcontractor and requested to approve VO on 21st Jun 2022
- Informed locations for piling is not sufficient to continue the works after 15th Jun and requested
clearing the existing impediments for continuous piling works without any stoppages, while reserving
its rights under the Contract for additional cost and time on 12th Jun 2022
ADC-NOCD-LTR-G-22-0167 12-Jun-22
Request for Clearance for Hindrances in - NOCD requested ADC to submit the proposal for MS that describes ithe present schedule for
126 Civil L-ADC-22-0252 14-Jun-22
North Wing Pier Extension Works completion considering hindering third party works on 14th Jun 2022
ADC-NOCD-LTR-G-22-0175-01 20-Jun-22
- Informed that it is not in a position to submit completion schedule because, a) for apron demolition
fence installation is pending, b) relocation of Padma oil line is pending, c) Contract addendum is yet
to be signed on 20th Jun 2022
- Notified NOCD about the new requirement for air conditioning units and exhaust fan as per ERRI-22-
Revised M&E contract drawing for 2B1,
127 M&E ADC-NOCD-LTR-C-22-0272 16-Jul-22 0297 will be a Variation and the cost proposal will be submitted on approval of shop drawing on 16th
2B2 and 2C2 in T3
Jul 2022.
Notification of VO due to Change in Height - Submitted advance notice about the variation of work due to the change in ceiling height of RFFS
144 Building ADC-NOCD-LTR-C-22-0370 11-Sep-22
of Ceiling for RFFS Building building as per EI-21-0225 and ERRI-21-0254 on 11th Sep 2022
Notice of Delay and Cost caused by Re- - ADC referred to EI-22-0211 and EI-22-0160 that requested 3rd party testing whose result did not
145 Building ADC-NOCD-LTR-C-22-0374 12-Sep-22 tests for the Elongation Test by 3rd Party meet project requirement and notified that the Elongation Test was not in accordance to ASTM
Testing Agency instructed by the Engineer standards and thus ADC shall reserve rights to Claim additional cost and Time on 12th Sep 2022
- Submitted cost proposal for the non-BOQ items of the damp proof membrane of trapezoidal
channel and pipe culvert works considering the similar item in the BOQ (Division 30401IC – Item
No.15) amounting to BDT 10,494,341 on 21st Jul 2022
- NOCD rejected VO as per the General Spec' BASIS OF PAYMENT for the Trapezoidal Channel
ADC-NOCD-LTR-C-22-0276 21-Jul-22
and Pipe Culverts stating the prices shall fully compensate the Contractor for furnishing all materials
L-ADC-22-0328 4-Aug-22 Provision of damp proof membrane for
176 Civil on 4th Aug 2022
ADC-NOCD-LTR-C-22-0319 16-Aug-22 trapezoidal channel and pipe culvert works
- ADC Clarified ADC did not quote for damp proof membrane (polythene sheet) for it during the
L-ADC-22-0510 23-Oct-22
tender acc to its non-availablity in Contract Drawing of Trapezoidal Channel and Pipe Culvert and
requested NOCD to review and approve the cost proposal on 16th Aug 2022
- NOCD issued variation for the Provision of Damp Proof Membrane for Trapezoidal Channel and
Pipe Culvert Works of BDT 10,494,341 on 23rd Oct 2022.
EI-22-0042 13-Feb-22 - Request for VO for additonal Hoist Crane Runway at Generator House on 24th Feb 2022
ADC-NOCD-LTR-G-22-0060 21-Feb-22 - Submitted cost proposal in amount of JPY 5,060,874 (remeasurement basis) on 9th Mar 2022
ADC-NOCD-LTR-C-22-0077 9-Mar-22 Trial Excavation of Existing Sewer Pipe in - ADC confirmed its agreement with NOCD's assessment and submitted the revised cost proposal
177 Civil
ADC-NOCD-LTR-C-22-0358 4-Sep-22 Area 5 amounting to JPY 2,745 and BDT 51,767.
L-ADC-22-0516 24-Oct-22 - NOCD approved variation for the Trial Excavation of the Existing Sewer Pipe in Area 5 for an
L-ADC-22-0518 24-Oct-22 amount of JPY 2,745 and BDT 51,767 on 24th Oct 2022.
- Submitted cost proposal in amount of JPY 281,225 and BDT 974,646 on 4th Aug 2022.
ADC-NOCD-LTR-C-22-0302 4-Aug-22 - Submitted revised Cost proposal in agreement with Engineer's assessment amounting JPY
178 Civil ADC-NOCD-LTR-C-22-0365 8-Sep-22 Additional Pipe Culvert at Service Road 7 283,217 and BDT 974,646 on 8th Sep 2022
L-ADC-22-0511 23-Oct-22 - NOCD issued variation for the Additional Pipe Culvert at Service Road 7 amounting JPY 283,217
and BDT 974,646 on 23rd Oct 2022.
- Request for VO for additional milling work in different depth (0~240mm) of asphalt at N1 taxiway
connection area in amount of BDT 4,966,299 on 3rd Mar 2022
ADC-NOCD-LTR-C-22-0078 3-Mar-22
Additional Milling Work at N1 Taxiway - Submitted revised cost in agreement with the Engineer’s assessment in BDT 5,067,822 on 2 Oct
179 Civil ADC-NOCD-LTR-C-22-0409 2-Oct-22
Connection 2022
L-ADC-22-0512 23-Oct-22
- NOCD issued variation for the Additional Milling Work at N1 Taxiway Connection amounting
BDT 5,067,822 on 23rd Oct 2022.
- Noticed additional cost to be incurred to change the racks from standard racks to sesmic tracks for
other ELV system except for SCN system is amounting to approx. USD 1.4 Mil. on 18th Oct 2022.
ADC-NOCD-LTR-ME-22-0139 18-Oct-22
- NOCD requested ADC to use the seismic structured type for all typoe racks without any additional
180 M&E L-ADC-22-0495 20-Oct-22 Racks for ELV System
cost on 20th Oct 2022
ADC-NOCD-LTR-ME-22-0153 26-Oct-22
- Requested NOCD to issue the EI to change other system racks to seismic racks as ADC sugested
as previous letter on 26th Oct 2022
- Submitted cost proposal due to changes in VB-1 (Valve Box) location inside the POCL Tank Farm
EI-22-0257 2-Oct-22 amounting to JPY 2,857,492 and BDT 1,040,534 on 19th Oct 2022.
VB-1 (Valve Box) Location Change inside
181 M&E ADC-NOCD-LTR-C-22-0438 19-Oct-22 - NOCD rejected ADC's proposal of unit rate adjustment taking into account that it does not the
POCL Tank Farm
L-ADC-22-0503 23-Oct-22 matter of GCC 12.3 ('Evaluations') and cost adjustment proposal considering coefficient change
(BBS) is in discussion on 23rd Oct 2022.
- NOCD instructed changes on Mechanical System at IPP for Distribution (5th Apr 2021, 20th Mar
EI-21-0072 5-Apr-21
2022)
183 M&E EI-22-0082 20-Mar-22 Changes in Mechanical System at IPP
- Submitted variation cost proposal in amount of JPY 4,899,065 and BDT 1,023,414 on 27th Oct
ADC-NOCD-LTR-C-22-0452 27-Oct-22
2022.
Final Layout and Detail for Permanent - Requested EI regarding final layout for draignage along Road-1 and Road 3-3 along the
184 Civil ADC-NOCD-LTR-C-22-0462 2-Nov-22
Drainage of EDW (Highway Side) Mymensingh highway with official confiramation on 2nd Nov 2022.
- Submitted cost proposal for abortive work for Landside Drainage Manhole & Pipe Culvert in Area-4
Final Layout and Detail for Permanent
185 Civil ADC-NOCD-LTR-C-22-0465 3-Nov-22 in amount of JPY 179,611 and BDT 965,576 refered Engineer's response (ERRI-22-0365) on 3rd
Drainage of EDW (Highway Side)
Nov 2022
- Requested VO for the design of Decorated Screen in MLCP that not reflected in Contract BOQ
and approval of artist out of the submitted sample design on 13th Dec 2021
- Submitted VO amount (JPY 218,114,934 and BDT 23,199,237) on 22nd May
- Submitted cost proposal for 3 artists amounting JPY 11,791,140, JPY 14,292,291 and JPY
12,719,677 including cost of sample design for an amount of JPY 933,962 and requested for
ADC-NOCD-LTR-C-21-0318 13-Dec-21 approval on 17th Jul 2022
L-ADC-21-287 26-Dec-21 - Requested NOCD to review and approve the Contractor's cost proposal under the principle of
ADC-NOCD-LTR-C-22-0003 04-Jan-22 measurement from the FIDIC Contract Guide (Design Screen to be measured as Lump-sum / BOQ
L-ADC-22-0016 17-Jan-22 not contain this item) on 21st Jul 2022
ADC-NOCD-LTR-C-22-0202 22-May-22 - ADC informed that it cannot agree with NOCD's contention and clarified its stand and requested to
ADC-NOCD-LTR-C-22-0264 17-Jul-22 arrange dispute board if NOCD does not agree with the Contractor's clarification on 16th Aug 2022.
186 Building-2 L-ADC-22-0298 20-Jul-22 Design of Decorated Screen in MLCP - NOCD issued its interpretation and final determination as rejection of ADC's proposal considering
ADC-NOCD-LTR-C-22-0278 21-Jul-22 BOQ item is intended to include all related scope and the missing items should be distributed among
L-ADC-22-0348 10-Aug-22 the rates and prices entered for related Items, thus there is no conflict between General principles of
ADC-NOCD-LTR-C-22-0318 16-Aug-22 BOQ and Subclause 12.3 on 23rd Oct 2022.
L-ADC-22-0508 23-Oct-22 - Submitted cost proposal for missing scope of work deemed to be included in the BOQ and
ADC-NOCD-LTR-C-22-0454 25-Oct-22 Specification for “Expanded Mesh Screen with Powder Coating”; and Change in the method for the
L-ADC-22-0550 3-Nov-22 decorated screen’s design and painting in amount of JPY 263,175,704 and BDT 27,632,134 on 25th
Oct 2022.
- NOCD rejected proposal on following grounds: (1) it is irrational that expanded mesh with powder
coating is missed from BOQ considering that is main object, (2) other items in cost proposal like
signage, frame, etc. are miscellaneous accessories of decorated screen and clearly drawn in
contract drawings, (3) change in dimension of hole is normal on 3rd Nov 2022
- Recommends the conversion of the CATV system to the IPTV in light of the following particulars
ADC-NOCD-LTR-C-22-0164 24-Apr-22
and cost-saving benefits, VE of JPY 10,750,594 whereas the Employer will save JPY 5,375,297
L-ADC-22-0466 16-Oct-22 Value Engineering (VE) proposal for the
187 M&E - NOCD declared the closing of VO discussion as per its letter L-CLEN-22-1315 (18th Sep. 2022),
ADC-NOCD-LTR-ME-22-0137 20-Oct-22 IPTV
where it consented in favour of the proposal, without additional cost on 16th Oct 2022.
ADC-NOCD-LTR-ME-22-0168 7-Nov-22
- Requested NOCD to confirm to proceed with LSZH cable for Radio System on 7th Nov 2022
Aviation Dhaka Consortium (ADC) 95 / 146
Monthly Report (Feb 2023)
No. Reference No. Issue Date Description Remarks
- Based on Chairman's confirmation regarding cost escalation factor, ADC requested new cost
Request for Application of Revised Cost
ADC-NOCD-LTR-C-22-0390 21-Sep-22 escalation factor based on PWD’s cost data effective from 21st June 2022 on 21st Sep 2022.
188 Common Escalation Factor Effective from 21st Jun
ADC-NOCD-LTR-C-22-0479 15-Nov-22 - Requested NOCD to make fair determination within 28 days from the date of this letter on 15th Nov
2022
2022.
- ADC worked out the rates for the different types of Duct banks that are required to be installed in
the entire Project & the total expected Variation amount for the Duct bank Works of the Project as
ADC-NOCD-LTR-C-22-0219 1-Jun-22 compared to the original Contract amount is JPY -536,171,434 and BDT 952,118,817
EI-22-0193 31-Jul-22 - Notified NOCD the design changes of the utility duct bank of the Airside in Area 3-1 (EDAC-22-
EDAC-22-1194 7-Aug-22 Cost proposal of Changed Design for Duct 1194) is to cause additional duck bank works and requested to issue EI & VO on 14th Aug 2022.
189 Civil
ADC-NOCD-LTR-C-22-0312 14-Aug-22 Bank - Submitted revised cost proposal due to changes in status of drawings from previous submission
ADC-NOCD-LTR-C-22-0481 14-Nov-22 amounting to JPY (701,623,405) and BDT 1,496,296,040 on 14th Nov 2022.
L-ADC-22-0137 28-Feb-23 - NOCD requested ADC to reduce VE cost considering ADC didn not maintain the duct bank
proposed length and duct bank working layout plan according to VE proposal as a result increasing
the cost of Duct Bank Work on 28th Feb 2023.
- NOCD forwarded BUET opinion, wherein it is stated that the cost proposal regarding the material of
drainage layer of apron pavement to be included in the value engineering proposal of the Contractor
on 17th Oct 2022.
L-ADC-22-0479 17-Oct-22
- Notified disagreement with the BUET's opinion (the cost proposal regarding the material of drainage
190 Civil ADC-NOCD-LTR-G-22-0294 15-Nov-22 Drainage layer of Apron Pavement work
layer of Apron pavement to be included in the VE proposal of the Cotractor considering drainage
L-CLEN-22-1702 15-Nov-22
layer was not changed due to VE and requested NOCD's fair and reasonable action on 15th Nov
2022
- NOCD requested CAAB to take necessary actions on 15th Nov 2022
- Submitted New Rate for reinforcement bars in EDW Works considering increased qunatities (BOQ
7,174 tons → Projection 10,896.25 tons) in amount of JPY 158,230 and BDT 44,507 per Ton
(remeasurement basis) on 10th Mar 2022
- NOCD informed that the estimated quantities are not yet verified and final and hence, at this point,
the Engineer is not in a position to permit revising the unit rate of BOQ Item 20230/1.4 High Yield
ADC-NOCD-LTR-C-22-0083 10-Mar-22
L-ADC-22-0431 26-Sep-22 Reinforcement Bars on 26th Sep 2022 -> to be re-measured based on clear demarcation of EDW
191 Civil Reinforcement Bars in EDW Works area only
ADC-NOCD-LTR-C-22-0471 10-Nov-22
L-ADC-22-0591 15-Nov-22 - Pointwise clarified that qty is based on approved shop drawing (BOQ 7,174 tons → SD 11,265.08
tons) and provided breakdown of materials, cut bend installation which has a direct impact on
increase of rates and requested to approve new rate of JPY 158,230 and BDT 44,507 per Ton on
10th Nov 2022.
- NOCD rejected the ADC's cost proposal with the opinion of disagreement on 'Direct cost' increase
and 'cut, bend &installation' impact submitted in the previous letter on 15th Nov 2022.
- Requested to issue EI to start the construction of road A-4 and the draignage structure whose
Obstruction in Construction of Road A-4
192 Civil ADC-NOCD-LTR-G-22-0326 10-Nov-22 alignment overlaps existing Signboards with the clarification whether the sign boards shall be
and Drainage due to Biman Signboards
demolished as per the Contract drawing or relocated as per Biman's request on 10th Nov 2022.
- Referring to ERRI-22-0493, agreed to install granite bollard at "no additional cost " on 10th Nov
ADC-NOCD-LTR-C-22-0478 10-Nov-22
Change of Concrete Bollard to Granite 2022.
193 Building L-ADC-22-0586 13-Nov-22
Bollard in Terminal-3 - NOCD acknowledged the proposed payment calculation process for the Granite Bollards on 14th
L-ADC-22-0586-01 14-Nov-22
Nov 2022
- Submitted cost proposal in amount of JPY 2,987,981 and BDT 683,825 for changes in ACMV
ADC-NOCD-LTR-C-22-0446 23-Oct-22 system at IPR (based on ERRI-21-0410 and ERRI-21-0182) on 23rd Oct 2022
194 M&E Changes in ACMV System in IPR
EI-22-0305 17-Nov-22 - NOCD issued 6 conditions for the cost proposal on 17th Nov 2022
(i.e., Variation cost won’t it acceptable 22.7% higher BOQ unit rate, etc.)
Pavement Work of Road A-4 and Road-N - Based on EI-21-0095 & EI-22-0258 submitted cost proposal for pavement works of Road A-4 and
195 Civil ADC-NOCD-LTR-C-22-0494 17-Nov-22
Entrance in Area-5 Road-N entrance in Area5, amounting to JPY 23,700,320 and BDT 26,772,349 on 17th Nov 2022
- Submitted the cost proposal for executing the additional sewage line work for TE3 pier extension
(south and north) amounting to JPY 8,649,277 and BDT 23,710,348 including rate adjustment by
ADC-NOCD-LTR-C-22-0397 22-Sep-22 Additional Sewage Line for Pier Extension
196 Civil 22.7% on 22nd Sep 2022.
L-ADC-22-0610 22-Nov-22 (South & North)
- NOCD approved the tentative amount of JPY 8,649,277 and BDT 23,710,348 which shall be finally
approved after the confirmation of the Government’s Purchase Committee on 21st Nov 2022.
- Submitted cost proposal for IPP and IPR to cover Missing Items of BOQ amounting to JPY
199,686,132 and BDT 24,417,286 on 2nd Oct 2022
ADC-NOCD-LTR-C-22-0405 2-Oct-22
Revised BOQ for IPP and IPR to cover - NOCD requested ADC to revise the quantity in a provisional quantity considering not only the
198 Common L-ADC-22-0614 24-Nov-22
Missing Items of BOQ addition of Missing Items, but also the quantity and Contract Amount for all items to understand the
L-ADC-22-0614 (same) 27-Nov-22
approximate amount of Overall Variation on 24th Nov 2022
- NOCD issued a letter with same reference number on 27th Nov 2022.
- Based on EAC-22-1629, submitted Cost proposal for change in dimension of aluminium nosing at
MLCP amounting to BDT 602,586 on 28 Nov 2022
ADC-NOCD-LTR-C-22-0519 28-Nov-22 Change in dimension of Aluminium nosing
199 Building-2 - NOCD cancelled EAC-22-1629 and informed that original design shown in contract drawing shall
L-ADC-23-0081 1-Feb-23 of Staircase at MLCP
prevail and requested ADC to submit revised RFA for MLCP stair nosing and there shall be no
changes in cost on 1st Feb 2023.
- Requested EI to claim for additional cost implications according to new model for glass elevator
bollard on 20th Sep 2022.
- NOCD replied that the Contractor cannot claim either Variation cost or Expansion of Time due to no
ADC-NOCD-LTR-ME-22-0110 20-Sep-22 indication of different origin for bollard from elevator car origin in Bid documents specification
L-ADC-22-0440 28-Sep-22 (Section-IV, Division 40100, Chapter 5.3) on 28th Sep 2022.
Change in Bollard Design for Glass Lift,
200 M&E EI-22-0282 27-Oct-22 - NOCD approved the modified Bollard Design for Glass lift without VO and EOT on 27th Oct 2022.
Escalator and Moving walk
ADC-NOCD-LTR-ME-22-0160 1-Nov-22 - Requested NOCD's revision of EI for the design change of the Square plate shape Bollard,
ADC-NOCD-LTR-ME-22-0183 28-Nov-22 requested by the NOCD (EDAC-22-1019) on 1st Nov 2022.
- Requested NOCD's confirmation of COO of Raw material (Europe) and Fabrication (Bangladesh)
of TE3 Bollard design for Glass Lifts, Escalators, Moving walks and Wide Dooe jamb for Elevators
on 28th Nov 2022.
- Requested VO for drainage modification including additional Manhole, Con'c pipe & Uditch at Area-4
ADC-NOCD-LTR-C-21-0236 10-Oct-21
Additional Manhole, Con'c pipe & Uditch at North part-A in amount of JPY 521,138 and BDT 1,411,477 on 10th Oct 2021
203 Civil ADC-NOCD-LTR-C-21-0240 19-Oct-21
Area-4 North part-A - Submitted the revised cost proposal amounting to JPY 1,010,399 and BDT 2,639,319 with a net
ADC-NOCD-LTR-C-22-0529 5-Dec-22
Variation of JPY (225,427) and BDT (709,940) on 5th Dec 2022
- Requested NOCD to issue EI for
L-ADC-22-0632 30-Nov-22 Shifting communication cable from Securit
204 M&E shifting communication cable from Security wall near Export Cargo area for cost proposal on 4th
ADC-NOCD-LTR-C-22-0522 04-Dec-22 y wall near Export Cargo area
Dec 2022.
- Requested VO for additional Grease Trap for Kitchen Drainage at RFFS on 28th Mar 2022
ADC-NOCD-LTR-C-22-0112 28-Mar-22 - Submitted cost for non-BOQ item of grease trap in RFSS amounting JPY 8,602,047 & BDT
Additional Grease Trap for Kitchen
205 M&E ADC-NOCD-LTR-C-22-0303 3-Aug-22 2,205,549 on 3 Aug 2022
Drainage at RFFS
ADC-NOCD-LTR-C-22-0546 14-Dec-22 - Submitted revised cost as per NOCD comments amounting to JPY 282,464 and BDT 24,998 on
14th Dec 2022.
- ADC’s proposal to use the Prisma P model of Schneider LV Switchgear. NOCD recommended the
Schneider Blockset or Okken type as preferable. The manufacturer Schneider with COO was
proposed and in Contract Attachment # 8. Hence, ADC will claim for additional Cost and Time.
ADC-NOCD-LTR-ME-22-0038 3-Jun-22 Requested to expedite the confirmation process. NOCD stated EOT claim is not acceptable on 5th
L-ADC-22-0236 5-Jun-22 Jun 2022
206 M&E ADC-NOCD-LTR-ME-22-0058 30-Jul-22 Selection of LV Switchgear model - Noticed that ADC reserves right to claim for additional Cost and Time due to delay in approval on
ADC-NOCD-LTR-C-22-0537 15-Dec-22 30th Jul 2022
ADC-NOCD-LTR-C-23-0105 27-Feb-23 - Submitted variation Cost for LV Switchgear based on Manufacturing COO amounting to JPY
476,093,111 and BDT 2,147,275 on 15th Dec 2022
- Submitted revised variation cost proposal amounting JPY 455,413,113 and BDT 1,844,166 on 27th
Feb 2023.
- Requested NOCD to issue EI for the oil transformer installation (based on ERRI-21-0501-01) on
ADC-NOCD-LTR-ME-22-0120 26-Sep-22
26th Sep 2022.
207 M&E ADC-NOCD-LTR-ME-22-0159 31-Oct-22 Oil Transformer Installation
- Requested NOCD to issue EI again on 31st Oct 2022
EI-22-0333 12-Dec-22
- NOCD issued Oil Transformer base and trench plan (drawing) on 12th Dec 2022
- Requested to issue a Variation Order Instruction for additional rainwater gutter for E/J of MLCP roof
212 Building-2 ADC-NOCD-LTR-C-22-0530 18-Dec-22 Additional Gutter in MLCP and ECT slab and ECT balcony which was clarified by the Engineer but not reflected in the Contract
Drawings/BOQ on 18th Dec 2022.
- Requested NOCD to issue EI for the requirement of BMS in other buildings and necessary design
ADC-NOCD-LTR-ME-22-0114 29-Sep-22 BMS Monitoring for Switchgear in Other
213 M&E drawings on 29th Sep 2022
ADC-NOCD-LTR-ME-22-0201 18-Dec-22 Buildings
- Requested NOCD to issue EI once again on 18th Dec 2022
Additional electrical works for Exterior - Requested NOCD to issue EI for additional Electrical works for Exterior Signage of TE3, ECT, ICT
ADC-NOCD-LTR-ME-22-0128 10-Oct-22
214 M&E Signage for T3, ECT, ICT and MCP and MCP Buildings based on ERRI-22-0459 on 10th Oct 2022.
ADC-NOCD-LTR-ME-22-0201 18-Dec-22
Buildings - Requested NOCD to issue EI once again on 18th Dec 2022
- Submitted the MLCP XPM Lotus Screen lighting concept, simulation and cost proposal for an
estimated amount of USD 100,000 and requested EI according to the Chairman (CAAB) decision in
the metting (24th Feb 2022) on 2nd Jun 2022
ADC-NOCD-LTR-C-22-0222 2-Jun-22 - Requested EI again on 29th Oct 2022
ADC-NOCD-LTR-ME-22-0158 29-Oct-22 - NOCD issued instruction for XPM lotus Screen Lighting on 17th Nov 2022. :
215 M&E XPM Lotus Screen Lighting in MLCP
EI-22-0306 17-Nov-22 ① lights at 6m interval, ② light fixture details submission, ③ basket size and shape,
ADC-NOCD-LTR-ME-22-0204 20-Dec-22
④ cost breakdown for Engineer's evaluation
- Requested the Engineer to provide the drawings, design details (revised lighting layout,
specification etc.) of MLCP XPM Lotus Screen Lighting on 20th Dec
- NOCD requested ADC to submit the breakdowns of the original contract of the following items and
manufacture’s quotation of handhole pit cover for further evaluation on 9th June 2022
- NOCD issued VO for the new item cost as per the change of AGL system considering the aspect
of technical and AGL maintenance amounting JPY 117,291,602.68 and BDT 170,235,195.50 on 20th
Jul 2022
- Responded that NOCD to consider only 10% as the combined indirect cost and profit, instead of
06-Apr-22, 06-Apr-22
ADC-NOCD-LTR-C-22-0128 25.8% as per Att#20 of Contract and requested NOCD to re-evaluate the cost proposal on 21st Jul
10-Apr-22
L-ADC-22-0243 2022
09-Jun-22
L-ADC-22-0299 - NOCD clarified only the Contractor’s “overhead and profit” of 10% to be added due to indirect cost
20-Jul-22
ADC-NOCD-LTR-C-22-0275 in the Contractor's claim already included in the Subcontractor’s proposal on 29th Aug 2022.
21-Jul-22 Variation Order for the New Item cost as
L-ADC-22-0380 - Requested NOCD to revise evaluation for the variation cost for the changed AGL system as the
29-Aug-22 per change of AGL System
216 M&E ADC-NOCD-LTR-C-22-0346 Contractor is practically not allowed to use the Subcontractor’s Indirect Cost under the Subcontract
1-Sep-22
L-ADC-22-0394 or law on 1st Sep 2022
5-Sep-22
ADC-NOCD-LTR-C-22-0372 - NOCD clarified that ADC’s claim for the indirect cost related work has already been done in actual
15-Sep-22
ADC-NOCD-LTR-C-22-0472 field work, therefore, only the Contractor’s “overhead and profit of 10% was added on 5th Sep 2022
21-Nov-22
ADC-NOCD-LTR-C-22-0472-01 - ADC disagree with NOCD and requested to issue Engineer's determination within 28 days as per
4-Dec-22
L-ADC-22-0658 Sub-Clause 3.5 [Determination] on 15th Sep 2022.
19-Dec-22
- Reminded NOCD to approve revised Variation Cost of JPY (12,008,869) and BDT 156,039,086 on
21 Nov 2022
- Submitted revised cost of JPY (45,452,514) and BDT 152,547,579 and requested to approve on 4th
Dec 2022
- NOCD issued the Variation Order for the New Item revised cost of JPY (45,452,514) and BDT
152,547,579 and superseded letter no 0299 dtd 20th Jul, on 19th Dec 2022
- Submitted cost proposal for landside drainage modification at Airside drainage Area 3-1 Part C
EI-22-0133/0170/0186 10Jun~27-Jul-22
Landside Drainage Modification at Airside amounting (Cost Saving) to JPY (10,829,970) and BDT (16,377,180) on 21st Nov 2022
217 Civil ADC-NOCD-LTR-C-22-0498 21-Nov-22
Drainage Area 3-1 Part-C - Submitted cost proposal for pavement works in RFFS area and retention pond-6 in Area 3-1
ADC-NOCD-LTR-C-22-0569 28-Dec-22
amounting to JPY 32,732,667 and BDT 54,512,433 on 28th Dec 2022
- Submitted Cost proposal for: Force Majure event (lightning strike) amounting JPY 3,115 and BDT
Lightning Strike on N1 Rapid Taxiway and 35,887; Demolition & repair of existing pipe culvert amounting JPY 10,361 and BDT 53,029 on 11th
ADC-NOCD-LTR-C-22-0422 11-Oct-22 for Demolition & Repair of Existing Pipe Oct 2022
218 Civil - Agreed to NOCD's assessment & submitted revised Cost ① for FM event amounting JPY 2,539.40
ADC-NOCD-LTR-C-22-0559 28-Dec-22 Culvert Headwall Besides Airside Service
Road 2 and BDT 6,016.48, ② Demolition & repair of existing pipe culvert amounting JPY 8,444 & BDT
42,966 on 28 Dec 2022
- Submitted additional cost impact (BDT 557,941,935) due to the change in brand of Doors and
Windows to "Hormann-Germany" on 18th Apr 2022.
- NOCD informed that CAAB verbally approved Hormann with the conditions on 29th May. ADC
submitted revised Cost Impact of BDT 476,519,600 on 6th Jun 2022
- NOCD confirmed VO amount (BDT 476,519,600) for change to “Hormann” Brand on 15th Jun
- NOCD reuqested ADC to submit latest Hormann VO amount for T3 on 7th Dec 2022
ADC-NOCD-LTR-C-22-0146 18-Apr-22
- NOCD informed that, as per Technical meeting with Chairman, CAAB agreed to use China and
L-ADC-22-0188-05 29-May-22
Thailand Origin Doors and windows as per Attachment#8 for T3 and Other buildings on 11th Dec
ADC-NOCD-LTR-C-22-0228 6-Jun-22
2022
L-ADC-22-0188-06 15-Jun-22
- Informed NOCD about the delay in finalization of Door brand and that original supplier's price in
L-ADC-22-0188-07 11-Oct-22
Cost impact due to Hormann-Germany Contract vs new quotation difference can't be established due to validity lapse and market conditions
219 Building L-ADC-22-0422-02 7-Dec-22
brand of Doors and Windows on 13th Dec 2022
L-ADC-22-0422-03 11-Dec-22
- NOCD requested to: (1) Follow the original BOQ unit rate for China/Thailand origin Doors, (2) In
ADC-NOCD-LTR-C-22-0536 13-Dec-22
case of any additional work cost, submit officially; (3) Acknowledged “Claim for additional time" on
L-ADC-22-0422-04 14-Dec-22
14th Dec 2022
L-ADC-22-0422-05 21-Dec-22
- NOCD requested to use following manufacturers: Wooden Door, Fire Door from “Arctic Star”
ADC-NOCD-LTR-C-22-0572 29-Dec-22
(China), Rolling Shutter, Fire Door from “KSS” (Thailand), Steel Fire Door from “Classic Door”
(Thailand), and Aluminum Door Window from “ROPO” (China), “Tostem” (Thailand) and also
requested to submit Manufacturers’ experience on 21st Dec 2022
- ADC submitted brand and manufacturer information of steel door, timber door, rolling shutter,
aluminium door due to cancellation of confirmed variation for "Hormann" brand manufacturer on 29th
Dec 2022
- As per ERRI-22-0626 skim coat finishing under trench to be provided, hence requested EI on 28th
ADC-NOCD-LTR-C-22-0566 28-Dec-22
220 Building Skim Coat finishing of trench Dec 2022
EI-22-0361 29-Dec-22
- NOCD issued EI for the application of CSA finishing instead of SKM on 29th Dec 2022.
EI-22-0344 19-Oct-22 - NOCD issued EI for the change in type of ECT & ICT road boundary wall from wire to
Change in Type of Boundary Wall of ECT
240 Building-2 ADC-NOCD-LTR-C-22-0555 22-Dec-22 brick+RC on 19th Dec amd ADC notified additional cost and time impact on 22nd Dec 2022
& ICT
L-ADC-23-0051 19-Jan-23 - NOCD noticed to ADC that new rate & prevailing market rate is not acceptable on 19th Jan
Additional RC Kerb for ICT, IPP, IPR, WSS - Submitted cost proposal for additional RC Kerb for ICT, IPP, IPR, WSS and AGS as per approval of
241 Building-2 ADC-NOCD-LTR-C-23-0024 16-Jan-23 and AGS as per Approval of ECT on ECT (L-ADC-22-0657, 18th Dec. 2022) on Remeasurement basis in amount of BDT 1,369,052 on
Remeasurement Basis 16th Jan 2023.
Change in Country of Origin of Floor Paint - Noticed cost impact due to change in Country of Origin of P6b(UR810) for Other Buildings
242 Building-2 ADC-NOCD-LTR-G-23-0015 17-Jan-23
P6b for Other Buildings (Attachment#8 : Bangladesh → Actual : Greece(Top coat) & India(Antislip grain)) on 17th Jan
Additional Aluminum Windows and Doors - Submitted cost proposal for installation of additional aluminium windows, louvers and doors for
243 Building-2 ADC-NOCD-LTR-C-23-0036 17-Jan-23
for Other Buildings other buildings in amount of JPY 11,096,441 and BDT 1,610,906 on 21st Jan
- Requested NOCD to issue VO as 'Fire barrier in expansion joint' is not provided in the BOQ on 10th
Jan
ADC-NOCD-LTR-C-23-0014 10-Jan-23
- As per PC 13.1, only the item not shown in drawing nor specification, “Variations” will be
L-ADC-23-0063 25-Jan-23 Fire Barrier for EJ in Terminal 3, MLCP
252 Building considered, Therefore, the items cannot be considered as a Variation Item on 25th Jan
ADC-NOCD-LTR-C-23-0056 30-Jan-23 and ECT
- Notified NOCD for entitlement for missing item of fire barrier in BOQ as per the GC Sub-Clause
L-ADC-23-0109 13-Feb-23
20.1 while clarifying the terms and limit of the Variation clause under the contract on 30th Jan 2023
- Submit VO along with Shop Drawing of Fire Barrier detail on 13th Feb 2023.
- Requested VO for XPM ceiling and wall design change of T3 and MLCP by NOCD on 17th Jan
2022
- NOCD noticed to reject any additional cost and request alternative design change on 20th Jan 2022
- Submitted cost proposal for additional process and materials amounting to JPY 44,174,644 on 25th
ADC-NOCD-LTR-C-22-0017 17-Jan-22 Oct 2022.
L-ADC-22-0023 20-Jan-22 - NOCD asks for discount on additional cost amount of JPY 44,174,644 prior recommending to
ADC-NOCD-LTR-C-22-0453 25-Oct-22 CAAB on 1st Nov 2022.
L-ADC-22-0023-01 1-Nov-22 - Informed that the Contractor will proceed with the works complying with the comments according to
ADC-NOCD-LTR-G-22-0343 21-Nov-22 XPM ceiling and wall design change of T3 the approved shop drawings, material sample and colour sample once the Engineer will confirm the
253 Building-2
L-ADC-22-0611 23-Nov-22 and MLCP approval of VO amount previously (ADC-NOCD-LTR-C-22-0453, 25th Oct) on 21st Nov 2022
ADC-NOCD-LTR-C-22-0508 28-Nov-22 - NOCD acknowledged receipt of the letter on 23rd Nov 2022
EI-23-0002 4-Jan-23 - Submitted revised cost proposal with discount (4.71%) amounting to JPY 42,095,630 on 28th Nov
ADC-NOCD-LTR-C-23-0034 22-Jan-23 2022.
ADC-NOCD-LTR-C-23-0066 30-Jan-23 - NOCD issued revised design (with reference of EDAC-22-1564-04) and requested ADC to submit
revised VO for EDW XPM works on 4th Jan 2023
- Notified that cost for varied works including abortive materials will be submitted shortly on 22nd Jan
- Due to CAAB's requirement of lotus pattern screen submitted revised cost proposal amounting to
JPY 67,182,663 and BDT 79,010 on 30th Jan 2023
Cost Proposal for Safety Guard Rail and
- Submitted cost proposal for additional work of safety/protection guard rail at ECT & ICT coldrooms
254 Building-2 ADC-NOCD-LTR-C-23-0050 29-Jan-23 Protection Walls in Coldroom at ECT &
amounting to BDT 2,241,562 on 29th Jan 2023
ICT
- Submitted cost proposal for additional work of SS gutter at expansion joints of MLCP roof slab and
ADC-NOCD-LTR-C-23-0063 30-Jan-23 ECT balcony for an amount of BDT 2,408,262 on 30th Jan
255 Building-2 SS Gutter Works at EJ of MLCP & ECT
L-ADC-23-0151 2-Feb-23 - NOCD requested ADC to provide a comparison of cost variation between Tender drawing and
Shop drawing on 2nd Mar 2023
- Requested EI for the change in all PBB lengths as per the design development by the
Subcontractor (M/S CIMC TIANDA) on 16th Oct 2022.
- NOCD noticed the acceptance of the change of length of other 17 nos. PBB (except A16 and A24
FGW that were cancelled via EI-22-0051-11) and requested to submit a revised quotationon 18th Oct
2022.
- Submitted Cost proposal amounting to JPY 33,575,202 on 26th Oct 2022.
ADC-NOCD-LTR-ME-22-0126 16-Oct-22 - NOCD noticed ADC's submitted VO amount is not accepable noting that the difference between
L-ADC-22-0482 18-Oct-22 the VO applied unit price (4,000 USD/m) compared to the original unit price (1,395.8~1,620.93
ADC-NOCD-LTR-C-22-0460 26-Oct-22 USD/m) is excessive on 30th Oct 2022.
256 M&E L-ADC-22-0444-02 30-Oct-22 Changes in PBB Lengths - Submitted evaluation of cost/m based on avg. BOQ rate as per NOCD's advice, which was higher
ADC-NOCD-LTR-C-22-0466 7-Nov-22 ($9,499/m) than ADC's first submission of USD 5,391/m and requested NOCD to approve the ADC's
L-ADC-22-0444-03 27-Dec-22 first submission, as NOCD's evaluation is not acceptable on 7th Nov 2022.
ADC-NOCD-LTR-C-23-0057 29-Jan-23 - CAAB has rejected the TE3 PBB Length Change VO amount JPY 33,575,202 and NOCD
requested ADC to review the VO amount based findings shown in L-ADC-22-0444-02 on 27th Dec
2022.
- Engineer's calculation of 1,508 USD/m for additional length of PBB is not agreeable, as it does not
cover price of engineering, raw materials, fabrication, etc. whereas the Contractor's proposal of
5,391 USD/m is considering all relevant works needed to complete 1m of PBB turnel, however ADC
will try to offer discount within 15th Feb for NOCD's determination on 29th Jan 2023
- Submitted VO amount (JPY 285,658,688 and BDT 57,625,060) for Honeywell advanced system of
ALCMS in place of OCEM on 17th Jul 2022
- Provided reminder to approve VO and notified that ALCMS PO was scheduled on 14 Aug and
hence it is impacting the progress and ADC will inform actual impacts when materials are delivered
ADC-NOCD-LTR-C-22-0260 17-Jul-22 on 15th Sep 2022
ADC-NOCD-LTR-C-22-0377 15-Sep-22 - Reminder to issue EI and approve Variation Order proposal for ALCMS on 10th Oct 2022.
ADC-NOCD-LTR-C-22-0421 10-Oct-22 - NOCD requested ADC to demonstrate the impact of the delay on the related work’s Critical Path of
Airfield Lighting Control and Monitoring
257 M&E L-ADC-22-0468 13-Oct-22 the material approval of the ALCMS to the Programme for the Engineer's review on 13th Oct 2022.
System (ALCMS)
ADC-NOCD-LTR-C-22-0445 20-Oct-22 - Clarified NOCD that the existing AGL can work with new ALCMS system and informed that impact
ADC-NOCD-LTR-C-23-0044 23-Jan-23 of delay on critical path will be informed seperately once the consolidated impact is available on 20th
L-ADC-23-0076 31-Jan-23 Oct 2022.
- Submitted revised variation proposal for ALCMS amounting to JPY 174,126,732 and BDT
19,635,985 on 23rd Jan 2023.
- Requested to proceed with original OCEM and withdraw the variation proposal with honeywell on
31st Jan
- Submitted cost proposal for SCADA system for generator house as per EI-21-0240-02 for an
EI-21-0240 4-Jan-22
Request for VO – SCADA System for amount of JPY 22,026,958 on 29th Jan 2023.
258 M&E ADC-NOCD-LTR-C-23-0051 29-Jan-23
Generator House - NOCD rejected ADC's VO and requested the to follow the tender drawing and ADC to revise and
L-ADC-23-0128 26-Feb-23
resubmit cost proposal as VO on 26th Feb 2023.
- Based on NOCD's comment on EAC-23-0168 asking to submit Explosion proof type thermostat for
Explosion Proof Type Thermostat for
259 M&E ADC-NOCD-LTR-C-23-0064 30-Jan-23 generator house, requested for EI & Variation order, as this requirement is not as per Contract on
Generator House
30th Jan
Request for VO - Cable Tray Works at - Submitted cost proposal for additional works pf cable tray in IPP, IPR & generator house for an
260 M&E ADC-NOCD-LTR-C-23-0058 1-Feb-23
IPP, IPR & Generator House amount of JPY 35,875,448 and BDT 1,024,936 on 1st Feb
- NOCD confirmed to use WP-6 for MLCP inside of Retaining Wall and Water Tank and WP-5 for
MLCP outside of Retaining Wall instead of WP-3 as per manufacturer’s recommendation for benefit
of the project. ADC proposed rate(BDT 2,246.18) for WP-6 owing to no item in BOQ.
- NOCD instructed ADC to proceed with wp using unit rate of the original Contract Agreement on
28th Apr 2022.
ADC-NOCD-LTR-C-22-0154 27-Apr-22 - ADC proposed to apply the unit rate of WP of water tank as other area (Tunnel) BOQ rate for WP-5
L-ADC-22-0187 28-Apr-22 and new unit rate for WP-6 on 8th May 2022
ADC-NOCD-LTR-C-22-0182 8-May-22 - Informed NOCD that Epoxy waterproofing materials are suitable and recommended for water tank
ADC-NOCD-LTR-C-22-0437 30-Oct-22 rather than Urethane Waterproofing as per the Manufacturer’s recommendation on 30th Oct 2022
ADC-NOCD-LTR-C-22-0432/ 0432-01 30-Oct-22, 2-Nov-22 - Submitted cost propoasal of Epoxy waterproofing with cost impact when waterproofing type change
L-ADC-22-0585 13-Nov-22 Request of VO for Change in WP Materials (Urethane → Epoxy) of water/flush tank of MLCP in amount of BDT 5,400,838 on 2nd Nov 2022
266 Building
ADC-NOCD-LTR-C-22-0483 15-Nov-22 at MLCP - NOCD requested ADC to submit the evidence of Urethane waterproofing is unfit for waterproofing
ADC-NOCD-LTR-C-22-0432-02 20-Nov-22 on 13th Nov and re-submitted the previous letter (no. 0437) and requested NOCD to approve Cost
ADC-NOCD-LTR-G-22-0357 1-Dec-22 proposal within 28 days on 15th Nov 2022
ADC-NOCD-LTR-C-22-0556 27-Dec-22 - Found Epoxy waterproofing materials are suitable as per manufacturer's recommendation and
L-ADC-23-0072 31-Jan-23 submitted new rate of BDT 2,246.20/m2 for Epoxy waterproofing on 20th Nov 2022
ADC-NOCD-LTR-C-23-0083 14-Feb-23 - Determined that ADC should start the works for Water/Flush Tank in MLCP using Epoxy WP
material, provide 10 yr warranty and no VO will be issued and cost increase proposal is rejected on
31st Jan 2023
- Expressed disagreement with NOCD's determination and stated that, even after completion of 40%
work and providing technical clarifications from manufacturers, the Engineer has once again rejected
the claim and requested to reconsider and determine on 14th Feb 2023.
- Submitted Cost proposal for missing waterproofing cases from BOQ in other buildings amounting
to JPY 4,447,850 and BDT 24,174,073 on 29th May 2022
- Submitted revised cost proposal, amounting to JPY 9,507,572 and BDT 26,753,134 on 29th Jun
ADC-NOCD-LTR-C-22-0212 29-May-22
2022.
ADC-NOCD-LTR-C-22-0212-01 29-Jun-22
Request of VO for Non BOQ - NOCD rejected proposal and inform that “GC Sub-clause 13.1 Right to Vary” is not applicable on
267 Building-2 L-ADC-22-0339 8-Aug-22
Waterproofing Items in Others Building 8th Aug 2022
ADC-NOCD-LTR-C-22-0337 31-Aug-22
- Provided ADC's further observations on the issue requesting further consideration on 31st Aug
ADC-NOCD-LTR-C-23-0081 12-Feb-23
2022
- Due to change in ECT & ICT outhouse submitted revised Cost proposal amounting to JPY
8,462,993 and BDT 28,047,230 on 12th Feb 2023.
- Requested EI acc to final MV cable Schedule issued by the Engineer on 5th Oct 2022
ADC-NOCD-LTR-ME-22-0132 5-Oct-22 - Based on ERRI-22-0431-01 submitted Variation cost proposal for MV cables schedule amounting
268 M&E ADC-NOCD-LTR-C-23-0082 11-Feb-23 Changes in MV Cable sizes to JPY 765,833,075 and BDT 107,252,312 on 11th Feb 2023.
L-ADC-23-0149 2-Mar-23 - NOCD found some missing items in the documents and asked to follow to attachment on 2nd Mar
2023.
- Requested EI to conduct additional tests which are not stipulated in relevant Spec, through verbal
instruction or comments to the material approval document, material inspection request & etc. on
10th Jan 2023
ADC-NOCD-LTR-C-23-0016 10-Jan-23
※ 3rd Party Test for Low Current Sample Cables/ Steel Conduit/ ELV Sample Cables
269 M&E ADC-NOCD-LTR-C-23-0020 15-Jan-23 Conducting additional test by 3rd Party
- Submitted cost for expenses incurred towards third party tests amounting to BDT 1,609,658 on
ADC-NOCD-LTR-C-23-0076 9-Feb-23
15th Jan
- Submitted variation amount for 3rd party testing of LS HFIX wire on MIR amounting to BDT 781,671
on 11th Feb 2023.
- Requested NOCD to look into the reinstatement work of retaining wall beside the VVIP road
demaged by Padma Oil (POCL) and to issue instruction to the Contractor for the work as variation
ADC-NOCD-LTR-G-23-0028 16-Jan-23 Reinstatement of a portion of the retaining on 16th Jan 2023.
270 Civil
EI-23-0052 20-Feb-23 wall along the existing VVIP road - NOCD instructed ADC to reinstate the demaged portion of the existing retaining wall for installation
of slope protection CC block and adjust the crossing drainage pipe and install the headwall due to the
high ground level of the outlet area on 20th Feb 2023
ADC-NOCD-LTR-C-21-0273 - ADC submitted the additional Cost incurred in the month of November 2021 ~ July 2022 on a
10-Nov-21
ADC-NOCD-LTR-C-21-0317, 0013 monthly basis every month for cumulative amount of BDT 65,518,555.00 /- on 10 Aug 2022.
7-Dec-21, 10-Jan-22
ADC-NOCD-LTR-C-22-0047, 0091 - ADC notified NOCD about the further change in Fuel price on 30th Aug 2022.
6-Feb-22, 16-Mar-22
ADC-NOCD-LTR-C-22-0142, 0149 - NOCD determined that the additional fuel cost, as the result of a Gazette notice can be claimed
12-Apr-22, 10-May-22
ADC-NOCD-LTR-C-22-0229, 0243 by application of General Condition 13.7 “Adjustment for Changes in Legislation” and instructed to
7-Jun-22, 17-Jul-22
ADC-NOCD-LTR-C-22-0311, 0338 submit the cost proposal with supporting particulars in each Interim Payment Application on 15th Sep
10-Aug-22, 30-Aug-22 Government Circulation for the Fuel Price
271 Civil L-ADC-22-0414 2022
15-Sep-22 Increase
ADC-NOCD-LTR-C-22-0385, 0429, - Submitted cumulative cost impact since the date of the initial Government notification in November
19-Sep-22, 23-Oct-22
0501 2021 until December 2022 amounting to BDT 221,628,372 on 23rd Jan 2023
24-Nov-22, 22-Dec-22
ADC-NOCD-LTR-C-22-0551 - Submitted cost proposal which shall be payable to ADC (upto Sep 2022) amounting to BDT
23-Jan-23
ADC-NOCD-LTR-C-23-0043 264,255,273 due to impact of fuel cost rise on 19th Feb 2023.
19-Feb-23
ADC-NOCD-LTR-C-23-0088 - Submitted cumulative cost impact since the date of the initial Government notification in December
22-Feb-23
ADC-NOCD-LTR-C-23-0091 2021 until January 2023 amounting to BDT 263,343,221 on 22nd Feb 2023
- Submitted cost proposal after visual survey for demolition inside POCL premises for site works due
to VB-1 location change amounting to JPY 1,020,964 and BDT 1,883,404 on 22nd Jan 2023.
- NOCD requested description of the proposed work to be performed and program for its execution
and proposal for any necessary modifications to the program according to Sub-Clause 8.3(Program)
and to the Time for completion. Also, 22.7% rate adjustment is not acceptable. on 24th Jan 2023
- The change was not necessitated by ADC but requested by POCL, hence it is an additional cost
ADC-NOCD-LTR-C-23-0035 22-Jan-23
and variation item of work and notified NOCD that ADC is firm in its position on 29th Jan 2023
L-ADC-23-0059 24-Jan-23
- NOCD notified variation has not yet been instructed as ADC has not submitted the necessary
ADC-NOCD-LTR-C-23-0049 29-Jan-23
Cost Proposal for site works due to VB-1 documents. For civil work: adjusted rates are not acceptable and requested to impliment necessary
272 Civil L-ADC-23-0101 9-Feb-23
location change inside POCL tank farm restoring works. For M&E Work: Link seal price as per BoQ & cost increase of piping work to be
ADC-NOCD-LTR-C-23-0086 15-Feb-23
resubmitted. on 9th Feb 2023.
L-ADC-23-0115 18-Feb-23
- Pertaining to M&E work, submitted VO amount(JPY 20,702,636 and BDT 7,298,702) on 15th Feb
ADC-NOCD-LTR-C-23-0101 23-Feb-23
2023.
- NOCD informed that M&E portion cost proposal has been reviewed and requested to submit the
cost proposal for Civil part, for discussing the variation due to VB-1 location change as a single
package with the Employer on 18th Feb 2023
- Confirmed acceptance of NOCD's assessment and submitted revised cost proposal amounting to
JPY 816,832 and BDT 1,274,198 on 23rd Feb 2023.
- Requested Engineer's advise and suggestion regarding remain soft soil after execution of drainage
installation work of the Employer which can be adverse impact on Road-H works (Excavation of
retention pond in Area-5) of the Contractor on 5th Dec 2022
ADC-NOCD-LTR-G-22-0360 5-Dec-22 - NOCD instructed ADC to do ① Employer's drain system protection ② Earth slope protection ③
273 Civil EI-23-0053 20-Feb-23 Excavation of Retention pond in Area-5 Pipe culvert layout revision & additional manhole without additional cost based on Specification
ADC-NOCD-LTR-C-23-0102 27-Feb-23 Division 10040 'The Site', 3. Existing Services within the Site on 20th Feb 2023
- Submitted cost proposal amounting to JPY 614,445 and BDT 1,856,780 for slope protection
adjacent to road O-1 and notified earthwork will be as per VO-105 and slope protection adjacent to
road-H will be as per VO-92 rates on 27th Feb 2023.
- Submitted cost proposal for additional work of BR railing at X-ray scanning area in T3 basement for
ADC-NOCD-LTR-C-23-0062 30-Jan-23 Additional BR Railing Works at X-ray an amount of JPY 1,121,906 and BDT 54,646 on 30th Jan 2023
274 Building-1
L-ADC-23-0122 23-Feb-23 Scanning Area of T3 Basement - NOCD shared evaluation result as accepting VO amount of JPY 832,459 and BDT 40,544 (declined
ADC's 25.8% VO amount) on 23rd Feb 2023
- Requested NOCD to issue EI for ADC to proceed with additional 2 nos Tariff Meter works for 3rd
party consumer of Padma Oil (33kV & 11kV Switchgear) on 3rd Dec 2022
- NOCD discussed with CAAB and Padma Oil Engineers for Tariff Meter on 11kV outgoing Feeders.
ADC-NOCD-LTR-ME-22-0186 3-Dec-22
CAAB issued requested letter to Padma Oil Ltd on 4th Dec 2022
L-ADC-22-0647 11-Dec-22
275 M&E Additional 2 Nos. Tariff Meters works - NOCD instructed ADC to install 2 srt CT Outgoing Feeder Panel (IPP) for Padma Oil Tariff Meter
EI-23-0020 24-Jan-23
on 24 Jan
ADC-NOCD-LTR-ME-23-0057 21-Feb-23
- Proposed to connect the existing CT/VT with Padma Oil Tariff Meter instead replacing with new one
which makes additional site modification cost (tentatively 26,800 Euro) with other abortive cost and
quality assurance fee on 21st Feb 2023
ADC-NOCD-
174 11 Sep’22 Delay in Approval of Landside Subbase Course Material
LTR-C-22-0366
Notice of Delay and Cost caused by Re-tests for the
ADC-NOCD-
175 12 Sep’22 Elongation Test by 3rd Party Testing Agency instructed by
LTR-C-22-0374
the Engineer
Observation to Notice of Delay and Cost Caused by Re-
ADC-NOCD-
176 27 Sep ‘22 Tests for Elongation Test by 3rd Party Testing Agency
LTR-Q-22-0013
Instructed by the Engineer
Notice of Delay in obtaining Import Permit due to CCI&E
ADC-NOCD-
177 04 Oct ‘22 server maintenance period from 1st September to 24th
LTR-PR-22-0796
September 2022
ADC-NOCD- Notice of Delay in Starting of Elevated Driveway (EDW)
178 10 Oct ‘22
LTR-G-22-0282 Piling Work at FDEE area
ADC-NOCD- Notification of Delay Event owing to Prohibition of Sand
179 19 Oct ‘22
LTR-G-22-0295 Dredging due to ‘Hilsa Fish’ Breeding Season
Notice of Delay due to withdrawal of previous approval to
ADC-NOCD-
180 20 Oct ‘22 the Supplier for Counter and Charging Station for the
LTR-C-22-0442
Terminal 3
Update of Delay in obtaining Import Permit due to CCI&E
ADC-NOCD-
181 24 Oct ‘22 server maintenance and HS Code Clarifications required by
LTR-PR-22-0841
CCI&E
ADC-NOCD-
182 25 Oct ‘22 Notice for Delay of Payment against Interim Payment IP-25
LTR-C-22-0455
ADC-NOCD- Notice for Delay in Payment of Onshore Portion of Interim
183 06 Nov ‘22
LTR-C-22-0467 Payment Certificate-25
ADC-NOCD-
184 10 Nov ‘22 Delay in Assignment of Super User
LTR-ME-22-0166
ADC-NOCD-
185 10 Nov ‘22 Financing Charges for Delayed Payment
LTR-C-22-0480
ADC-NOCD-
186 14 Nov ‘22 Notice for delayed reimbursement of Taxes/Duties
LTR-PR-22-0959
ADC-NOCD-
187 14 Nov ‘22 Notice of Delay – Material Submission Reply from Engineer
LTR-C-22-0484
ADC-NOCD- Delay in Approval of Variation Cost Proposal for Decoration
188 14 Nov ‘22
LTR-C-22-0487 Cable Stayed Bridge
ADC-NOCD- Notice of Delay due to Prolonged Delay in Selection of the
189 16 Nov ‘22
LTR-C-22-0490 Supplier for Seating Works for the Terminal 3
Update of Delay in obtaining Import Permit due to CCI&E
ADC-NOCD-
190 20 Nov ‘22 server maintenance and HS Code Clarifications required by
LTR-PR-22-0977
CCI&E
ADC-NOCD-
191 24 Nov ‘22 Notice of Delay for SOG Slab Works of T3
LTR-G-22-0344
ADC-NOCD-
192 24 Nov ‘22 Notice of Delay for Clearance of ELV Material Issue
LTR-ME-22-0179
ADC-NOCD-
193 28 Nov ‘22 Notice for Delay of Payment against Interim Payment IP-26
LTR-C-22-0510
Notice of Delay due to partial suspension of ECT/ICT works
ADC-NOCD-
194 28 Nov ‘22 caused by violence incident between subcontractors, which
LTR-G-22-0349
could be avoided by the deployment of police
Notice of Delay caused by Non-availability to open L/C due
ADC-NOCD-
195 04 Dec’22 to USD Shortage in Major Commercial Banks of
LTR-G-22-0359
Bangladesh
ADC-NOCD- Re:Notice of Delay – Material Submission Reply from
196 04 Dec’22
LTR-C-22-0513 Engineer
Notice of Delay in Removal of Existing Fuel Pipeline used
ADC-NOCD-
197 07 Dec’22 by PADMA, which is conflicted with Subgrading works, Fuel
LTR-C-22-0531
Hydrant System for AREA 4
ADC-NOCD- Notice of Delay – Mechanical Shop Drawing Submission
198 08 Dec’22
LTR-C-22-0533 Response from Engineer
ADC-NOCD- Notice of Delay due to cancellation of confirmed Variation
199 13 Dec’22
LTR-C-22-0536 to change the Brand of Doors and Windows to “Hörmann”
ADC-NOCD- Delay in Duct Bank work due to Ongoing works of another
200 17 Dec’22
LTR-G-22-0380 contractor(zone-1)
ADC-NOCD- Notification of Delay in Issuance of Engineer’s Instruction
201 18 Dec’22
LTR-PR-22-1123 with relevant design details
ADC-NOCD- Notification of Delay in Issuance of Engineer’s Instruction
202 19 Dec’22
LTR-ME-22-0203 with relevant design details
ADC-NOCD- Further Notice for Delay of Payment against Interim
203 19 Dec’22
LTR-C-22-0532 Payment IP-26
ADC-NOCD- Reply to Notice of Delay–Mechanical Shop Drawing
204 22 Dec’22
LTR-C-22-0549 Submission Response from Engineer
ADC-NOCD- Notice of Delay due to NOTAM issuance after Taxiway
205 22 Dec’22
LTR-G-22-0387 closure phase-2A
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent Import items Permit and
206 26 Dec’22
LTR-PR-22-1146 Delay of Duty/Tax Payment for imported materials which
are already assessed by Customs
ADC-NOCD-
207 02 Jan’23 Financing Charges for Delayed Payment
LTR-C-23-0002
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD-
208 02 Jan’23 Letters" to CCI&E for Permanent Import items Permit and
LTR-PR-23-0007
Delay of Duty/Tax Payment for imported
ADC-NOCD- Notice of Delay in Superstructure Works of EDW South and
209 05 Jan’23
LTR-G-23-0010 North Piers
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD-
210 09 Jan’23 Letters" to CCI&E for Permanent items and Delay of
LTR-PR-23-0043
Duty/Tax Payment for imported materials which are
ADC-NOCD- Notice of Delay in finalization/response of ELV/SAS
211 15 Jan’23
LTR-ME-23-0014 Engineering Submittals
ADC-NOCD-
222 7 Feb’23 Notice of delay regarding the VDGS works
LTR-ME-23-0033
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent items and Delay of
223 8 Feb’23
LTR-PR-23-0245 Duty/Tax Payment for imported materials which are already
assessed by Customs
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent items and Delay of
224 12 Feb’23
LTR-PR-23-0266 Duty/Tax Payment for imported materials which are already
assessed by Customs
ADC-NOCD- Delay notification regarding the MLCP XPM Lotus Screen
225 13 Feb’23
LTR-ME-23-0044 Lighting design
ADC-NOCD-
22 Feb’23 Notice of Delay due to Change in Door Brand
231 LTR-C-23-0096
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent items and Delay of
232 22 Feb’23
LTR-PR-23-0324 Duty/Tax Payment for imported materials which are already
assessed by Customs
ADC-NOCD- Delay in Process of Import Permit for Elastomeric Bearing
232 22 Feb’23
LTR-G-23-0076 Pads with Polychloroprene Rubber
ADC-NOCD-
233 23 Feb’23 Delay in Pending Works in front of Biman Building
LTR-G-23-0078
ADC-NOCD-
234 24 Feb’23 Delay in Handing Over of Existing VVIP Terminal Area
LTR-G-23-0079
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent items and Delay of
235 26 Feb’23
LTR-PR-23-0337 Duty/Tax Payment for imported materials which are already
assessed by Customs
Notice for delay issuance of "direct Import Permit Request
ADC-NOCD- Letters" to CCI&E for Permanent items and Delay of
236 27 Feb’23
LTR-C-23-0106 Duty/Tax Payment for imported materials which are already
assessed by Customs
Replied by
ADC-NOCD- Claim for Additional Costs due to Employer delay in
6 23-Feb-21 L-ADC-21-0051
LTR-C-21-0037 Import Permits
(25-Feb-21)
ADC-NOCD- Submission of 4th Interim Claim for Extension of Time,
7 30-May-21
LTR-C-21-0121 Loss and Expense
ADC-NOCD- Submission of 5th Interim Claim for Extension of Time,
8 28-Oct-21
LTR-C-21-0250 Loss and Expense with Acceleration Plans
Submission of Updated Presentation Materials for
ADC-NOCD-
9 30-Nov-21 Acceleration Plans and 5th Interim Claim for Extension of
LTR-C-21-0302
Time, Loss and Expense
Submission
Title Rev. No. Approved Date Status Action
Date
* Code & Standards: Submitted the hard copy and USB Flash Drive.
Approved/ Approved
455 8 463
w/comments
Rejected - - -
- Material Submittal & Approval Status for the month of Feb, 2023
Approved/
Rev. Submission
No Material Submittal EAC Issued Status Remarks
No Date
Date
Preparing
Fire Sealing system at expansion joint Revised &
1 0 19-Feb 23-Feb Revised
for T3 Building Resubmit
Documents
Preparing
Roof Access Hatch Door for T3 Revised &
2 0 22-Feb 27-Feb Revised
Building Resubmit
Documents
Approved/
Rev. Submission
No Material Submittal EAC Issued Status Remarks
No Date
Date
Preparing
Polyurethane Sealant (Nitoseal PUSO) Revised &
4 0 05-Feb 22-Feb Revised
for Expansion Joint at T3 Building Resubmit
Documents
Preparing
Sealer for Granite protection for other Revised &
6 0 01-Feb 16-Feb Revised
buildings Resubmit
Documents
Preparing
Curing Compound for Concrete Revised &
11 0 14-Feb 16-Feb Revised
Pavement of Civil work (FOSROC) Resubmit
Documents
Approved/
Rev. Submission
No Material Submittal EAC Issued Status Remarks
No Date
Date
Waiting for
23 Door Threshold for Other Buildings 0 26-Feb - -
Approval
Waiting for
24 Door Threshold for T3 Building 0 27-Feb - -
Approval
* Others: Lean, Temporary works, Waterproofing works, Soil Investigation, Site preparation, Survey, Fence etc.
Building 36.69 % [RC Works ( 33.03 %), Steel Structure ( 3.66 %)]
Infra. 41.87 % [Pavement ( 3.46 %),Earthworks (26.28%), RC Works (11.80 %), Drainage Layer (0.34%)]
Others 21.44 %
- Pending Ratio of Final Approval with respect to total inspected WIRs = 11,099 / 35,754 * 100 = 31.04 %
* Inspection Ratio by Activity: Material Inspection & Test (94.39%), Mix Design (5.61 %)
Bituminous material
1-1 GP Global (UAE) 23 ~ 30 Oct, 2021
PG76-10, PG76-16, PG82-16
Up to Feb, 2023
9 Façade PMU Jangho (China) 15 ~ 21 June, 2021
Schneider Electric
High Voltage Equipment and
28 Factory, 15 ~ 23 Nov, 2022
Panel 132kV or 33kV
Turkey
Schneider Electric
Medium Voltage Equipment
29 Factory, 15 ~ 23 Nov, 2022
and Panel 11kV
Turkey -
Table # 1
Date of submission of test Date of Date of test
in Chapter Item Name Factory Name
plan and schedule approval (estimate)
10160
TBD
3 Dowel bar, Admixture - - -
(Bangladesh)
9 Feb. 2022
15th Feb 2022 Completed:
4 Steel Girder bridge Samil, Korea (ADC-NOCD-RFA-PL-Q-CC-
(EAC-22-0188) (25 ~ 31 May, 2022)
22-0023)
Aeronautical Ground
Lighting System
(AGLS) and
14th July 2021
Aeronautical Lighting OCEM 6th June 2021 Completed:
6 (a)~(f) (L-CLEN-21-
control and monitoring (Italy) (ADC-NOCD-LTR-G-21-0041) (21 ~ 27 Feb 2022)
0399)
systems (ALCMS)
(a) AGL Lighting
Fixture
Completed:
Korea Factory: (28
DSHI 1st Jun.2021 for
Steel Structure 2nd Jun 2021 June ~ 2 July, 2021)
8-1 (Korea, (ADC-NOCD-RFA-PL-Q-21-
(ECT/ICT) (EAC-21-0740) Bangladesh Factory:
Bangladesh) 0015-03)
(17 Aug. ~ 7 Sep
2021)
Completed:
11 May 2021
Steel Structure Jinggong 16 May 2021 (27 ~ 29 Sep, 2022)
8-2 (ADC-NOCD-RFA-PL-Q-21-
(TE3) (China) (EAC-21-0655) Full Scale Joint Test
0016)
in Lab (China)
22 Apr. 2021
Façade Performance Jangho 17 May 2021 Completed:
9 (ADC-NOCD-RFA-PL-Q-21-
Mock-up (PMU) (China) (EAC-21-0667) (15 ~ 21 June, 2021)
0012)
(i) 28th March to 3rd
April 2023 for Saint
Gobian, Gyproc India
(ii) 28th March to 3rd
False Ceiling, TBD
April 2023 for Tiles-
10 (a)~(e) Acoustic Ceiling (China, Korea, - -
Wonderful Group
Panels etc. Thailand)
(Marcopolo), China
(iii) 23rd May to 29th
May 2023 GKS
Factory, China
Sanitary fixture
11 (toilets, hand basins, - - - -
etc.)
Imported Toilet
12th May to 18th May
12 compartment, Wall Jialifu, China - -
2023
partitions
Table # 1
Date of submission of test Date of Date of test
in Chapter Item Name Factory Name
plan and schedule approval (estimate)
10160
Lounge Furniture,
15 Check-in counters, - - - -
etc.
16 Signage - - - -
Table # 1
Date of submission of test Date of Date of test
in Chapter Item Name Factory Name
plan and schedule approval (estimate)
10160
16 Nov.2021
LG Electronics, (HSIA-ADC-PL-ME-21-0006), 24 Nov. 2021 Completed:
33 Chiller
Korea 10th May 2022 (EAC-21-0330) (15~22 May, 2022)
(ADC-NOCD-LTR-G-22-0054)
34 Cooling Tower - - - -
8 Mar. 2022
LG Electronics, 16 Mar. 2021 Completed:
38 Air handling unit (ADC-NOCD-RFA-PR-
Korea (EAC-22-338) (10 ~ 18 June, 2022)
ME-22-0012-01)
Fire pump
SPP Pump, 6 Jan. 2022 22 Mar. 2021 Completed:
40 sets(Electric
USA (HSIA-ADC-PL-ME-22-0007) (EAC-22-349) (24 ~ 30 Nov, 2022)
motor/engine driven)
Water treatment
41 Korea - - -
equipment
TBD : To be dated
Note :
The Row filled with the color ( ) stands for the completed Factory Witness Test item.
The Row filled with the color ( ) stands for the schedule of Factory Witness Test up-to next 3 months (May.)
13.6 Statistical Analysis Result of Hardened Concrete (consider minimum last 30 cumulative data)
- Standard Deviation of Compressive Strength [unit : MPa]
Data Standard
No. Concrete Classes Unit Min. Max. Avg.
amount Deviation
Standard
Field Lab.
Deviation
Total PJT Days worked since last Recordable Incident (LTI) 113
Total Incident Free Man-Hours since last Recordable Incident (LTI) 10,998,080
* PJT commence date was Dec 17, 2019 [NTP April 7, 2020]
Dangerous Occurrence
TreatmentCase)
Property Damage
(Restricted Work
MTC (Medical
Occupational Illness
RWC
Fatality
Year/
L5
L7
L2
L9
L1
Month
L3
L8
L6
Year 2019 00 00 00 00 00 00 00 00 00
Year 2020 05 04 01 00 00 00 01 00 00
Year 2021 00 01 05 00 00 00 00 00 00
Year 2022 00 00 01 00 00 00 01 01 02
January-2023 00 00 00 00 00 00 00 00 00
February-2023 00 00 00 00 00 00 00 00 00
Total 05 05 07 00 00 00 02 01 02
- NA
14.4 Noncompliance report action items status [S-CAR / Unsafe Act or Conditions]
Power & Hand Tools (Welding, Grinding, Cutting, Drill, etc.) 3,060 39,317
SL. Safety Training Record (In House training) This Month YTD 2023
j) Weapon Awareness 0 0 4 29
l) Excavation 0 0 13 434
o) CPR 1 17 18 186
SL. Safety Training Record (In House training) This Month YTD 2023
SOP for lifting activities in the site Accident prevention safe guard 22nd Feb. ~ 2023
29th Safety Committee Meeting Improve Positive Safety Culture 28th Feb. 2023
Positive Recovered
Total no. of test Negative Case Death Case
Criteria Case Case
31-Jan -23 15,247,014 127,542 2,037,588 3,042 13,209,426 124,500 29,443 0 1,992,694 3,042
28-Feb -23 15,254,399 127,542 2,037,829 3,042 13,216,570 124,500 29,445 0 1,998,448 3,042
Earthwork Earthwork
- Swamp soil removal & Excavation at - Swamp soil removal & Excavation at
Area 1, 3-1, 4, 5, 6-1 Area 1, 3-1, 4, 5, 6-1
- Soil Embankment at Area 4 - Soil Embankment at Area 4
- Sand Embankment at Area 2, 3-1, 4, 5 - Sand Embankment at Area 2, 3-1, 4, 5
- Sand delivery / Soil disposal - Sand delivery / Soil disposal
Drainage work Drainage work
- U-Shape Channel, BOX Culvert - U-Shape Channel, BOX Culvert at Area
at Area 3-1 3-1
- Slope Protection at Area 1,2, 4 - Slope Protection at Area 1,2, 4
- RC Pipe at Area 2, 3-1, 4 - RC Pipe at Area 2, 3-1, 4
- Trapezoidal channel Area 6-2, 7 - Trapezoidal channel Area 6-2, 7
Utility work Utility work
Civil - Duct Bank at Area 3-1,4, 5~ECT/ICT, - Duct Bank at Area 3-1,4, 5~ECT/ICT,
Construction Area 6-2, 7-1 Area 6-2, 7-1
- Fuel Hydrant, External Hydrant Pipe - Fuel Hydrant, External Hydrant Pipe
Installation at Area 2, 3-1, 4 Installation at Area 2, 3-1, 4
- Sewage Pipe/MH Installation at Area - Sewage Pipe/MH Installation at Area 2,
2, 3-1, 4 3-1, 4
- Utility Installation around T3 - Utility Installation around T3
Curbside : Other bean installation EDW
EDW - Footing, Column, Coping, Assebly of
- Bored Pile, Footing, Column, Coping, Steel BOX Girder, RC Girder installation,
Assebly of Steel BOX Girder, RC Super structure, Bent Installation, Steel
Girder installation, Super structure, box Girder Erection
Bent installation - MSE Wall
- MSE Wall - Retaining wall
- Retaining wall Pavement work
Pavement work - Apron Lean & Slab con’c paving at Area
- Apron Lean & Slab con’c paving at 3-1, 3-1B
Area 3-1, 3-1B - Aggregate & Asphalt paving at Area 3-
- Aggregate & Asphalt paving at Area 3- 1(connection part of con'c Pavement)
1(connection part of con'c Pavement) Taxiway Closure(Ph.6)
Taxiway Closure - Con'c duct bank & manhole installation
Aviation Dhaka Consortium (ADC) 140 / 146
Monthly Report (Feb 2023)
ICT, Roofing & Steel Structure Installation ECT, Utility & Sandwich Panel Installation
(28 February 2023) (28 February 2023)
T3 Left Wing, Pile Cap Work T3 Right Wing, Pile Cap Work
(28 February 2023) (28 February 2023)
T3, Façade & Roof Truss Installation T3, APP Ceiling Installation & Tile Work
(28 February 2023) (28 February 2023)
GH, RC,Brick Work & Utility Installation Oil Tank, Slab RC Work
(28 February 2023) (28 February 2023)
. .
EDW South, Girder Installation Work EDW North, Column Work & Girder Installation
(28 February 2023) (28 February 2023)
Attachments
1. Updated Programme (with actual start, finish dates & actual progress % as of 28 February
2023) (225pages)
4. Soft copy of work photos (to be uploaded in ACONEX with Monthly Progress Report)
(CD of work photos was submitted to CAAB)
5. Soft copy of work video (to be uploaded in ACONEX with Monthly Progress Report)
(CD of work video was submitted to CAAB)