You are on page 1of 5

CONSPRO MANAGEMENT SERVICES

29/01/2020
Project Specifics
Project Identification Construction of Cyber Crime office and 9 Type -1V Staff Quarters for C.P Mumbai

Project Organisation Maharashtra State Police Housing & Welfare Corporation

Project Manager Mr Kaushik Chandawalla

Sponsor Organisation Maharashtra State Police Housing & Welfare Corporation

Contents of Report
Progress Summary .............................................................................................................................. 1
Permissions Obtained .......................................................................................................................... 2
Renewable Permissions ....................................................................................................................... 3
Laboratory Equipment .......................................................................................................................... 3
Site Mobilisation .................................................................................................................................. 3
Sub Structure Milestones ...................................................................................................................... 4
Up Coming Milestones (Super Structure Milestone) ................................................................................. 4
Status as on Date ................................................................................................................................ 4
Machinery Deployed............................................................................................................................. 4
Material at Site .................................................................................................................................... 5

Review confirmation
This report has been received and represents a true account of the project’s performance.
Project Manager Sponsor
Sign

Date

On track Variance within Variance outside


Progress Summary acceptable limits acceptable limits
CONSPRO MANAGEMENT SERVICES
29/01/2020

Construction of Cyber Crime office and 9 Type-1v Staff Quarters for C.P Mumbai, at C.T.S no 1275

➢ Achievements
Pile 133/134 has been Completed
➢ Issues
Low Labour Strength
Material Shortage
Technical Staff Shortage
➢ Proposed Action
Shore Pilling Proposal Has been Submitted for approval on 10.01.2020
Puzzle Parking Proposal Has been Submitted for approval on 03.01.2020

Permissions Obtained
Documents Obtained Date Remarks
PR Card Obtained
Survey Report From Obtained
A.E Survey
CTS Plan Obtained
N.O.C
CFO NOC Compliance in Progress of Letter Dated
24.10.2019
LOA (Bldgs. 08.08.2018 CHE/3486/BP/ (Spl.Cell)/AHE/337
Approval)
SWM NOC 17.10.2019 /004034/2019/H/W/SPL Dated 17.10.2019
CRZ 10.01.2020 Obtained
Tree Cutting NOC 14.01.2020 DYSG/TA/Z-III /194/P Dated 14.01.2020
SWD Remark Obtained
Sewerage Remark Obtained
Metro NOC In Progress
Civil Aviation 25.06.2019 Valid up to 24.06.2027 JUHU/WEST/B/061819/406812 Dated
25.06.2019 (AMSL = 57.13 M)
HE NOC In Progress
Geological Survey 11.06.2019 Obtained
Report
CONSPRO MANAGEMENT SERVICES
29/01/2020

Renewable Permissions
Document Date Renew Date Remarks Present Status
Dewatering Permission 01.08.2019 31.01.2020 H/W/13684/A.E.M.) Last Date
Dated 01.08.2019
Debris Management (Royalty) 20.09.2019 19.12.2019 AC/DESK-IV/MNL/SR- Expired
285/2019-20
CAR Policy 07.05.2019 06.05.2021 To be up to Defect To be Renewed
Liability Period in May’20
Bank Guarantee 26.09.2019 06.10.2021 BG 31900IGL0000919
Security Deposit (SD) 14.02.2019 13.02.2026 0027BGFD001619
Dated 14.02.2019
Labour Licence 15.07.2019 30.06.2020 1913700110028265 To be Renewed
in June’20
Employee & Workman 07.05.2019 06.05.2019 11060036190100000051 Top Sheet to has
Compensation Policy (EC/WC) different Number
Anti-Termite BG
Water Proofing BG

Laboratory Equipment
Equipment’s Required AT Site Remarks
Slump Cones 2 Nos 2 Nos
Cube Moulds 30 Nos 28 Nos
Vicat apparatus 1 Nos Not Laid
Oven including Set of 1 Nos Not Laid
Pans
Automatic CTM 1 Nos 1 Nos
Digital Weighting 1 Nos 1 Nos
Balance
Spring Balance 1 Nos Not Laid
I.S Sieves 1 Set 1 Set
Silt Measuring Jar 3 Nos Not Laid
Total Station 1 Nos Not Laid
Micro Meter 2 Nos Not Laid
Vernier Calliper 2 Nos 1 Nos
Spectrometer NA NA NA

Site Mobilisation
Milestone Actual Date Remarks
Site Clearance – Scrapping & Debris 20.03.2019 Completed
Shifting

Site Barricading/ Bench mark 27.05.2019 Completed


Establishing
Site Office Setup for Client/ PMC/ 01.05.2019 Completed
Contractor
Survey- Building Line Marking & Pile 27.05.2019 Completed
Location Marking
Open Space Checking 28.05.2019 Completed
Geological Survey 11.06.2019 Completed
Bhoomi Puja 15.06.2019 Completed
CONSPRO MANAGEMENT SERVICES
29/01/2020

Sub Structure Milestones


Milestone Baseline Baseline Rev. Rev. Actual Actual Remarks
Start Finish Baseline Baseline Start Finish
Start Finish
Test Pile 29.03.2019 Completed

Test Pile 10.05.2019 Completed


Testing Dynamic

Pile 29.03.2019 29.08.2019 17.04.2019 14.04.2020 15.07.2019 133 Piles


Foundation Completed as
on 29th Jan-20
Plinth Work 23.08.2019 19.09.2019 19.03.2020 17.04.2020

Up Coming Milestones (Super Structure Milestone)


Milestone Baseline Baseline Rev. Rev. Actual Actual Remarks
Start Finish Baseline Baseline Start Finish
Start Finish
RCC 20.09.19 25.05.20 30.03.2020 02.09.2020
Block work 10.12.19 15.06.20 22.05.2020 30.12.2020
Internal 07.02.20 08.06.20 30.05.2020 08.12.2020
Plaster
External 09.06.20 20.07.20 14.12.2020 28.01.2021
Plaster

Status as on Date
Work Description Total Estimated Executed Remarks
Boring Pile for Foundation 134 133 Stopped due to Material
Shortage from 12th Dec-2019
Excavation / Muck Removal for Pile Caps 2000 Brass 400 Brass Stopped due to Royalty
Expired From 19th Dec-2019
Pile Breaking 134 42 Low Labour Strength

Machinery Deployed

Work Description Entry Exit


JCB 10.07.2019 20.10.2019
Pilling Rig 1 of 185 Torque 11.07.2019
Pilling Rig 2 of 185 Torque 27.07.2019 13.12.2019
Poclain 200 19.10.2019 Ideal due to Royalty
CONSPRO MANAGEMENT SERVICES
29/01/2020

Material at Site
Work Description Total Received Approx. Balance on Remarks
Site
Steel Fe500 66.67 MT 15 MT 16mm Dia & 20mm Dia Not available
from 10.12.2019

Concrete M35 552.50 Cum RMC


Sahabad Tiles 4370 Sft For Waterproofing
Liner 78.45 MT

You might also like