Professional Documents
Culture Documents
February 2022
Tsehay
1 Dodola –S/Washa- 20,272,395.64 Performance
Insurance
08/06/20 13/06/23
Goba Heavy Road Bond Active
Maintenance
Tsehay
36,142,683.00 Advance Bond 04/08/20 04/08/22
Insurance
Active
The contractor has not yet submitted either time and/or cost claim
or combination of them up to date.
Status of Change Order/Variations/
The contractor has requested for approval of unit rate for pay
items not included in the BOQ (sub base material provision and
Class B masonry construction for retaining walls), while the
activities were required to complete the project. Waiting client’s
approval, but they usedWKthe provisional
CMC PLC
rates.
Feb. 2022
Problems Encountered
- Late mobilization of contractor (2 Months delay) and suspension of
the project activities since November 14th 2021 (3 months)
- Contractor’s failure to mobilize both crusher and asphalt plant as
per the schedule
- Lack of experience for such kind of works contract for both the
contractor and/or his staffs
- Poor site management
- Late establishment of laboratory
- Maintained section in 2013 EFY including asphalt paving were
failed again; WK CMC PLC Feb. 2022
Cause of Failure for Failed Road Sections
- The gradation of samples shows that the gradation curve falls on the finer side of
the grading envelope of the specification.
- In general, all the sub base materials which have collected from the failed section
of the project have found WK CMC PLC
unsuitable Feb. construction.
for sub base 2022
Sample collection for quality test on recently maintained section st. 376+080
- The level of compaction of all base course material found to be below the
requirement of specification i.e. below 98 % of the maximum dry density
achieved by heavy compaction test except one test conducted on station
km 384+300 which pass marginally.
- Similarly the tests conducted on the sub base layer reveals that the level of
compaction of all sub base layers is found below the required specification.
87
85
83
81
79
77
75
73
71
69
67
65
376+356 376+600 379+000 381+000
sation
86
82
78
74
70
66
62
58
54
50
325+000 327+510 341+200 378+200 381+600 383+600 384+300
station
- Side drains and cross drainage structures were closed/ blocked by silt are - In
addition to this, some of the road section may become interrupted
- Due to contractors sudden stoppage, material dumped on the road, and
excavation for the construction of check dam/ retaining wall and gabion
structures has effect the existing (station 357+157 and 376+300)
of the other project within the same package (Aposto –H/Selam Heavy
Maintenance Road Project) and recommence the project within short period of
time.
- The contractor should hire/ assign qualified person for respected position
Structural excavation
Back fill (selected material and granular fill)
Ditch clearing by machine
Reinforced ditch cover for pedestrian and vehicular crossing
Natural sub base and class B masonry (has provisional rate)
Construction, repair and maintenance of temporary diversions and accommodating Km 40.00 200,000.00 8,000,000.00
15.01 traffic
121 Culvert Clearing M3 553.90 100.00 55,390.00
122 Ditch clearing (manual) M3 14,851.24 20.00 297,024.86
123 Repair Erosion Damage (Selected Fill) M3 210.00 100.00 21,000.00
124 Repair Erosion Damage (Rock Fill) M3 550.00 320.00 176,000.00
125 Mortared Masonry Repair M3 400.00 1,000.00 400,000.00
126 Dry Masonry Repair M3 450.00
127 Gabion Structures M3 14,960.00 1,200.00 17,952,000.00
214 Asphalt patching (Hot mini mix) M3 1,780.01 5,300.00 9,434,053.00
313 Asphalt Over lay M3 21,323.50 5,600.00 119,411,600.00
315 Bitumen Tack Coat Lt 43,648.40 45.00 1,964,178.00
314 Prime coat Lt 150,330.00 50.00 7,516,500.00
316 Pavement reconstruction (Aggregate Road base) M3 19,955.45 650.00 12,971,042.50
44.01 (a) Rock fill M3 35,548.90 280.00 2,217,600.00
42.03(a) Common Excavation to waste of pumped Road section M3 52,997.22 85.00 4,504,763.70
51.01 (c ) Natural Sub base M3 16,750.25 254.33 4,260,091.08
81.01 (c ) Granular Back fill M3 1,535.25 70.00 107,467.50
230 Ditch clearing (machine) Km 45.00 7,300.00 328,500.00
240 Shoulder Blading Km 20.00 2,500.00 50,000.00
241 Shoulder Rehabilitation M3 43,076.6 200.00 7,122,800.00
34.040a Paved water way M2 11,792.00 450.00 5,306,400.00
89.01 Class B Masonry M3 2,491.50 2,820.00 7,026,030.00
No
33.17 b (i&ii) Reinforced Concrete drain Cover 2,500.00
Sub-Total 211,886,432.64
VAT (15%) 31,782,964.90
Total 243,669,397.54
Blocked Pipe at st. 271+500 ( Inlet) Blocked Pipe at st. 271+500 (Outlet)
Silted side ditch @322+610 RHS Pipe closed by farmer at st. 324+200
Alligator crack and Rutting at st. 376+520 -376+580 Cumulated water due to blocking of pipe by farmers 384+200
(RHS)
Rutting and shoulder deformation at st. 440 +200 LHS Cracking, rutting and pothole at 441+500 RHS
Providing access for traffic at st. 373+800 Ditch Clearing at St. 376+760 RHS