Method
14-662000-4800000322-
Project name Design & Build Truck Service Centre Statement
MOB-MEC-MST-000021
Submittal no.
Contractor
Contractor MOBCO
Drawing
Specification no. Date 03/09/2022
reference
Architectural Civil/ Structural Mechanical
Discipline
Electrical Other (please specify):
Date of Programmed
03-09-2022 Submitted for Approval Information
work
Contractor Authorized
Bakur Signature
representative
QA/QC Manager’s
Date
name
Signature
14-662000-40800-70100000003-120201-M13O-ABC-MM-CEOCN-M- Page 1 of 2
Project Manager’s comments
Provide Reference for this method of statement.
Manufacturer shall stamp this method of statement to confirm it illegibility.
Provide Specs reference for the method of statement.
Standard for GRP Tanks installation shall be mentioned and followed.
Tests shall be as per approved ITP.
Components of the tank for installation shall be listed. (Panels, Angles, Bolts, Ladder, Lining and leak stoppingetc.)
Signature
Received by Contractor
Name Date
Signature
14-662000-40800-70100000003-120201-M13O-ABC-MM-CEOCN-M- Page 2 of 2
Method Statement
14-Outer Regions - NEOM Truck Service Center
Rev. 01 - 03 Sep,2022
14-662000-4800000322-MOB-MEC-MST-000021_01
Document history
Revision code
Description of changes Purpose of issue Date
01 First Issue
For Approval 03-09-2022
Document approval
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
METHOD STATEMENT
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
TABLE OF CONTENTS
1. GENERAL.........................................................................................................................................................3
2. PURPOSE..........................................................................................................................................................3
3. SCOPE...............................................................................................................................................................3
4. ROLES & RESPONSIBILITIES.......................................................................................................................3
5. EQUIPMENT, TOOLS AND RESOURCES.....................................................................................................5
6. PERSONNEL QUALIFICATION.....................................................................................................................6
7. Methodology......................................................................................................................................................6
8 Water tightness test............................................................................................................................................8
9 Tank Water Filling Record.................................................................................................................................9
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
Document Title:
MST-Risk assessment for Installation of
GRP water tank
1. GENERAL
This document covers the sequence activities for Fixation GRP water Panel Tank
2. PURPOSE
The purpose of This method statement is to be sure that GRP water tank installation for D &B Truck service center
.
3. SCOPE
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
• The supervisor has to check and confirm the panel and accessories quantity when the goods arrive at the
installation site.
• The construction of a water tank is unique, given the fact that orderly putting the parts together can
complete it . As partial assembly is impossible, you need to check whether the work is done properly
during every stage of the assembly process..
• If you find any defect in the parts during the installation process, you need to stop the construction right
away. Then you should report it to our company., Ltd. which will take adequate measure to address it.
During the process, you should prevent workers from replacing them with other manufacturer’s part.
• If the installation is completed, you need to fill up the tank full. Then, the project owner, constructor, and
supervisor should co-operatively perform the test for leaks. And the confirmed test results need to be
reported to the related department.
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
Document Title:
MST-Risk assessment for Installation of
GRP water tank
5.1 Tools
DRILL HP1640KX3 WITH ALL BIT WATER LEVEL HOSE 6MM*1MM*20Y
TOOL BOX
WATER LEVEL 100 CM STABLE
HAMMER 2 KGM
TIN STEEL CUTTER 12 INCH
STEEL TAPE 30M
STEEL TAPE 10M CABLE WHEEL 50M
ONE SIDE SPANNER 12MM
SCAFOLDING RATCHET 14-17
ONE SIDE SPANNER 14MM
ONE SIDE SPANNER 17MM GRINDER 100 MM GA4040Z/220-MAKITA 1100 WATT - WITH 2 DIAMOND
ONE SIDE SPANNER 19MM IMPACT WRENCH 12.7 MM(1/2") TW035/220 400 WATT - MAKITA
5.3 Manpower
7.3.1 Supervisor 1 person
7.3.2 Technician 1 person
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
Document Title:
MST -Risk assessment for Installation of
GRP water tank
6. PERSONNEL QUALIFICATION
• All personnel would be competent for the tasks that they will be carrying out,
7. Methodology
7.1 Instructions of Installation and storage recommended
Unloading by customer : at the nearest point of easy standing – the “Delivery Point”.
Receipt Signatures: a responsible employee or representative must be on hand to receive the goods.
Onsite Storage: to store the goods in a clean, safe, secure location, providing necessary product
protection against loss or damage and by fully insuring the goods against loss or damage. Tank Supplier
does not accept responsibility for lost or damaged goods following their delivery to site.
Site Movement: to ensure the product or components are safely moved from the delivery point to the
immediate vicinity of, the tank foundation. so, the Customer should be moving the components
carfully and If packages are broken, or opened, the Customer will be responsible for the cost of
replacing any damages or shortages.
Foundation: the concrete foundation for sectional tank types, shall be flat, level and free from any local
irregularities and not vary more than 2mm in any metre or a total of 6mm in any 6 metres measured
laterally or diagonally. The Customer is responsible for ensuring the structural integrity of the tank
foundation / supports which must be capable of supporting the tank and its contents without movement.
Working Space: shall be in accordance with Health and Safety legislation requirements and free from
any debris. A minimum 600mm clearance is required all around the tank for installation and
maintenance. A minimum of 750mm is required above the roof of the tank for installation, access and
maintenance. On handed over on completion of tank installation, the Customer is responsible for its
protection against damage.
Testing / commissioning: . It is essential that the tank be filled and tested within 10 working days of
complete assembly and for it to remain filled thereafter.
Sterilisation by customer : tanks should not be sterilised until they have been tested and proved to be
watertight.
Moving of Sectional Tanks: after installation, it is not advised and no responsibility is taken by the
manufacturer should a tank be moved or repositioned.
Scaffolding: to be provided issue by the Customer.
Overflow Discharges: The provision of Regulation compliant pipework capable of conducting any
possible tank overflowing discharges safely and securely to suitable and appropriate drainage facilities
is the responsibility of the Customer.
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
Document Title:
MST -Risk assessment for Installation of
GRP water tank
14-662000-4800000322-MOB-MEC-MST-000021_01
Project Name: D &B NEOM TRUCK CENTER
If the utility department has already installed water pipes, you can fill the tank while closing the valves
for drain and outlet.
The water should be filled up to 500 ~ 600 mm, then it will be held for 6 hours (each stage).
Let the exterior accessories of the water tank free from any drop of water.
Closely check nozzle, panel, bottom and corner parts.
The water tightness test should be done while there is a sunlight and fully filling up the water tank.
If the water tank is installed in the basement or inside of the building, enough lighting is required to
check whether the tanks leaks or not.
If there is a leak, mark the area with red marker. The Identify any address the cause of water leaks
14-662000-4800000322-MOB-MEC-MST-000021_01
D &B NEOM TRUCK CENTER
ADDITIONAL
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
RISK LEVEL
FINAL RISK
SEVERITY
SEVERITY
SEVERITY
CONTROLS
LEVEL
IDENTIFIED HAZARDS TARGET
S. No.
(Hierarchy of DATE
ACTIVITY (Give necessary EXISTING CONTROLS
controls to be
description of Hazard)
followed as described
in EHSP-07)
L S R1 L S R2 DD/MM/YY L S R3
Table Of Content :
1- Excavator
2- Working Platform
3- Working Area Access
4- Working outdoors
5- Operate Excavator
6- Lifting Equipments
7- Boom Truck controol the load
14-662000-4800000322-MOB-MEC-MST-000021_01
OHS FM-06 Rev.01
D &B NEOM TRUCK CENTER
ADDITIONAL
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
RISK LEVEL
SEVERITY
SEVERITY
SEVERITY
IDENTIFIED HAZARDS CONTROLS TARGET
RISK
(Hierarchy of
S. No.
FINAL
ACTIVITY (Give necessary EXISTING CONTROLS DATE
controls to be
description of Hazard)
followed as
L S R1 L S R2 described in EHSP- DD/MM/YY L S R3
07)
14-662000-4800000322-MOB-MEC-MST-000021_01
OHS FM-06 Rev.01
D &B NEOM TRUCK CENTER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
RISK LEVEL
SEVERITY
SEVERITY
SEVERITY
ADDITIONAL TARGET
RISK
FINAL
IDENTIFIED HAZARDS CONTROLS DATE
S. No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
RISK LEVEL
SEVERITY
SEVERITY
SEVERITY
TARGET
RISK
FINAL
IDENTIFIED HAZARDS ADDITIONAL CONTROLS DATE
S. No.
L S R1 L S R2 DD/MM/YY L S R3
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
SEVERITY
SEVERITY
SEVERITY
ADDITIONAL
LEVEL
CONTROLS TARGET
RISK
FINAL
IDENTIFIED HAZARDS (Hierarchy of DATE
S. No.
• Do not overload.
• Maintain and check lifting system
Parts of the equipment as per Manufacturers as per NEOM SO P an d Ma nufacture requie rments
6 Lifting Equipments 4 4 1 6 2 4 8 N/A 01/09/2022
collapsing requirements.
• Keep all personnel clear when
loading, unloading and during
transportation.
14
D &B NEOM TRUCK CENTER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
LIKELIHOOD
LIKELIHOOD
LIKELIHOOD
RISK LEVEL
RISK LEVEL
ADDITIONAL
SEVERITY
SEVERITY
SEVERITY
CONTROLS TARGET
RISK
FINAL
IDENTIFIED HAZARDS (Hierarchy of DATE
S. No.
Organizational Control – Clear
organizational structure and
reporting lines; job descriptions;
psychological counseling on
referral by physician
Personal control – staff have
access to well – equipped gym
Training and information
Mental Stress from work
3 3 9 Soft skills course in: 1 3 3 N/A 01/09/2022
load pressure 1. Coping with accusation
in workplace
2. Managing workplace stress
3. Coping with aggressive
behavior in workplace
4. Preventing unhealthy
workplace conflicts
5. Facing and resolving
conflicts in workplace
Reviewed &
Division / Department Manager / Project Manager 01/09/2022
Approved By