PRESENTATION OUTLINE
Introduction
1. Project Information
2. Basic Contract Data
3. Important Contractual Dates
4. Mobilization
ROW status
Outstanding Issues
1
Introduction
Project Information:
Total Length: 19.132km
From 0+000 to 3+400 Urban section (Guder Town)
From 3+400 to 8+200 Pre-Urban
From 8+860 to 19+132 Urban section (Ambo Town)
2
Cont’d
3
Cont’d
Basic Contract Data
Project Name Construction Works of Guder Town –Ambo Town Design and build Road Project
Defects Liability Period 365 Days From the issuance of the Taking Over Certificate
5
Warranty Period Four (4) years after the end of defect liability period
Cont’d
Consultant Mobilization
Following the notice to commence issued by the Employer, the Consultant has commenced the Consultancy
Service of the project on July 14th, 2021.
7
Physical and Financial Action Plan Vs Accomplishments
8
Cont’d
Plan 7.25% 65,478,028.20 0.04% 342,266.60 13.02% 117,559,009.3 55.77% 503,765,667 63.02% 569,243,694.8
Actual 2.92% 26,410,947.85 3.59% 32,404,710.04 9.02% 81,511,964.32 26.61% 240,287,766 29.53% 266,698,713.5
Actual/
40.33% 69.34% 47.71% 46.85%
Plan (%)
9
Linear Progress for each weighted work items
Item No Amount(Birr)
Acc. Vs
Work Description Wt (%) Contract Amount A/P
Planned Accomplished Contract
Survey, Investigation and Design as per
1 2.00% 18,064,739.24 18,064,739.24 17,897,508.58 99% 99.07%
the Employers requirement
Series 1000/Division 1500/ Detour and
2 1.00% 9,032,369.62 7,166,637.02 5,445,192.13 76% 60.29%
Traffic Management
Series 2000/Division4000/ Site
3 25.00% 225,809,240.45 186,591,870.53 161,816,675.49 87% 71.66%
Clearance and Earthwork
4 Series 5000/ Division 5100 Sub base 7.00% 63,226,587.33 40,349,730.94 29,378,291.45 73% 46.47%
Series 5000 /Division 5200 Base
5 14.00% 126,453,174.65 72,053,090.97 - 0% 0.00%
Course
Series 6000/ Bituminous Surface
6 21.00% 189,679,761.98 98,206,977.35 - 0% 0.00%
including Shoulders
Series 3000,Series 8000/
7 20.00% 180,647,392.36 108,120,883.95 38,396,166.21 36% 21.25%
Bridges ,Culverts and Drainage
11
Availability of major Equipment to achieve the progressed
12
ROW Status Along the project
N length Type of
Estimated
Remark
Station Identified Measured Send to Client Paid
o Km properties
1 0+00-1+400 1.4 House,fence & trees Yes Yes Yes Yes Yes Guder town
T/Kutaye
4 4+200-10+391 6.191 Farm,House,fence & trees
And Ambo
Ambo Town
6 12+00-14+300 2.3 House,fence & trees On Progress
13
Cont’d
Obstruction Status On Camp, Borrow site, Quarries, production site, crusher and Asphalt plant
N Offset Type of
Estimated
Remark
Station Identified Measured Send to Client Paid
o Km properties
1 6+000 near Farm Yes Yes Yes Yes Yes T/Kutaye
Farm
5 7+060 near Ambo Town
On progress T/Kutaye
7 4+000 2.8 Farm and grazing land
14
Cont’d
15
Cont’d
Paid Unpaid
S/No. Items Amount Valuation
Amount % Amount %
Owner properties on
1 178,733,616.79 108,461,060.4 61% 70,272,556.38 39%
the Main Road
16
Outstanding Issues
Delay from Contractor Mobilization and Production
Delay in establishment Asphalt plant
Late nearly established crusher plant but still on trial production
Delay in investigation of Asphalt aggregate material searching
Delay in preparations Asphalt Mix Design and base course production.
Delay from Employer and need series attention given to:
Delay in compensation payment for utility and properties owners obstruction on the main road
Delay in respond CAR Policy and Sub Contractors Request For approval or comment Consent
Action on the existing straight light Obstruction from Km 10+800-18+180 Both side on Ambo city
Action on Homicho water line existing on Guder-Ambo project ROW from Km 1+400-3+000RHS
Action on the additional 3km ahead to adiss from Project end proposed by Ambo city administration and
18
About the Supplementary Project Information Lot-1 and Lot-2
Earth work and site clearance Undercut excavation and common excavation
Replacement fill construction
Site clearance
21
Outstanding Issues
Issues on Lot-2
• ROW obstruction Existing Irrigation canal on Route -12
• Compline proposed on Route 4 and 2 related to sub grade treatment process because the indicated
routes carrying heavy trucks load based on this they needs review the design
• And the consultant has staff mobilized and supervision the work process even not yet contract signs
22
Thank You
23