FEDERAL DEMOCRATIC REPUBLIC

OF
ETHIOPIA

ETHIOPIAN ROADS ADMNISTRATION

SODDO JUNCTION (DIMTU) – BILATE MILITARY


TRAINING CENTER ROAD PROJECT

MONTHLY STATUS REPORT


for
OCTOBER 2023

GONDWANA ENGINEERING PLC


In Sub-Contract with
YLS Engineering PLC
Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

MONTHLY STATUS REPORT

Reporting Period: September 26th, 2023 – October 25th, 2023

Prepared By: Resident Engineer, Tamrat Aberra

I. CONTRACT DATA

Construction Contract Data

Construction Works of Soddo Junction (Dimtu) - Bilate


Project Name
Military Training Centre Road Project

Southern Ethiopia, Wolaita Zone, Duguna Fango


Project Location
Woreda, Bilate

70 km (25 km Main Road, 23 km Compound Road,


Project Length Airfield: 3.12 km Runway+0.45 km Taxiway/est. 22
km)

Asphalt Concrete (AC) surfacing to a DC-5 Design


Scope of the Design
Standard.

Types of Contract Ad-measurement (DBB)

Federal Democratic Republic of Ethiopia/


Funded by
Government Budget

Employer Ethiopian Roads Administration (ERA)

Contractor Powecon PLC

Dates

Letter of Acceptance issued 04th of March, 2022

Date of Signing of Contract 14th of March, 2022

Date of Commencement 14th of April, 2022

Time for Contractor’s Mobilization 120 Calendar Days

Page |1 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

Construction Contract Data

Time for Construction 3 Years (1,095 Calendar Days)

Defects Liability Period 2 Years (730 Calendar Days)

Original Contract Completion Date 13th of April, 2025

Elapsed Time To date 559 Calendar Days (51.05%)

Financial Data

Original Total Contract Price


ETB 2,375,680,864.47
(Including 15% VAT)

Value of Variation Orders to-date -

Value of Claims Approved to-date -

- ETB 208,909,265.56 (Cash to the Contractor – 100%)


- ETB 208,909,265.56 (Payment to Supplier – 100%)
Advance payment certified to-date
(Including 15% VAT) - ETB 417,818,531.13 (Total Certified which is 100%
of the total Advance Payment)

After Certification of 30% of the Contract Price Less


Starting of Advance Repayment
Contingency, PS and Daywork

Amount of Advance Repayment 40% of IPC

Minimum Amount of Interim


ETB 10,000,000.00
Payment

Percentage of Retention Money 5% (Five Percent)

Amount of Liquidated Damages 0.1% of the Final Contract Price per day

Limit of Liquidated Damages 10% of the Final Contract Price

Interest on Late payments 4% Annually

Interim Payments paid to-date


including PA, MoS and 15% VAT ETB 274,405,862.69
(From IPC-01 to IPC-12)

Page |2 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

Construction Contract Data

Total Price Adjustment to-date


ETB 37,988,994.09
(Since March 17th, 2023)

Retention (5%) To-date


ETB 11,452,528.95
(From IPC No. 01 - IPC No. 11)

Material On-site Paid To date


ETB 2,318,612.18
(From IPC No. 01 - IPC No. 11)

Sub-contract Data

Contract Agreement Date 01st of August, 2023

Sub-Contractor ET General Contractor & Machinery Renting

Scope of Sub-contract Only Earthworks from Km 0+000 to 14+000

Sub-contract Amount (Including


ETB 103,808,006.40
15% VAT)

Advance Payment (Without 15%


ETB 5,000,000.00 (50% Before & After Mobilization)
VAT)

20 CDs after signing contract & receiving advance


Commencement Date
payment from the Main Contractor

Completion Date 200 CDs after the date of commencement

Page |3 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

II. PHYSICAL AND FINANCIAL PROGRESS:

Physical & Financial Accomplishment


Physical Accomplishment
Total of Previous Total of
This 2 nd Quarter This Month (Oct Cumulative of
For 2014 FFY For 2015 FFY Months of 2016 Previous Total To-date
of 2016 EFY 2023) 2016 EFY
EFY Months

% Km % Km % Km % Km % Km % Km % Km % Km

Plan 1.87% 1.31 27.44% 19.21 9.01% 6.30 38.32% 26.82 17.14% 12.00 5.40% 3.78 14.41% 10.09 43.72% 30.60

Actual 0.16% 0.11 14.91% 10.44 3.43% 2.40 18.50% 12.95 1.44% 1.01 1.44% 1.01 4.87% 3.41 19.93% 13.95

Actual/Plan (%) 8.54% 54.33% 38.08% 48.27% 8.38% 26.61% 33.78% 45.60%

Financial Accomplishment (Million ETB)


Total of Previous Total of This 2nd
This Month (Oct Cumulative of
For 2014 EFY For 2015 EFY Months of 2016 Previous Quarter of 2016 Total To-date
2023) 2016 EFY
EFY Months EFY

% ETB % ETB % ETB % ETB % ETB % ETB % ETB % ETB

Plan 1.87% 35.12 27.44% 514.37 9.01% 168.85 38.32% 718.34 17.14% 321.37 5.40% 101.27 14.41% 270.11 43.72% 819.60

Actual 0.16% 2.73 14.91% 254.27 3.43% 58.50 18.50% 315.50 1.44% 24.51 1.44% 24.51 4.87% 83.01 19.93% 340.01

Actual/Plan (%) 8.54% 54.33% 38.08% 48.27% 8.38% 26.61% 33.78% 45.60%

III. PHYSICAL PROGRESS

In this reporting month, October 2023, the Contractor has managed to achieve for is 1.44%
(ETB 24,512,688.84) which is 1.01 km whereas the planned amount figure excluding
Dayworks is 5.40% (ETB 101,265,637.72) equivalent to 3.78 km as per the Contractor’s
masterwork program.

The actual to-date progress of the project that the Contractor has managed to accomplish has
become 19.93% (ETB 340,011,045.40), which is equivalent to 13.95 km against the planned
figures of 43.72% (ETB 819,594,556.17) equivalent to 30.60 km. The total time elapsed to-date
is about 559 calendar days (51.05%). Hence, the slippage from time and plan is -31.12% and -
23.78%, respectively.

Page |4 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

Current Status of the Works


Plan Actual
% Wt Orignal Contract Revised Contract This Month (Oct This Month (Oct
Item Description Unit Previous Months To date Previous Months To date
Amount Amount 2023) 2023)
Amount %age Amount %age Amount %age Amount %age Amount %age Amount %age

1 General 8.2 % 153,714,356.12 153,714,356.12 94,706,927.07 61.61% 3,267,456.02 2.13% 97,974,383.09 63.74% 67,603,734.18 43.98% 722,516.45 0.47% 68,326,250.62 44.45%

2 Site Clearance 0.3 km 5,666,487.75 6,248,505.66 5,666,487.75 100.00% - 0.00% 5,666,487.75 100.00% 5,015,651.16 80.27% - 0.00% 5,015,651.16 80.27%

3 Drainage 22.2 Km 416,585,302.22 423,668,607.74 197,126,483.09 47.32% 27,499,676.80 6.60% 224,626,159.89 53.92% 9,031,490.03 2.17% - 0.00% 9,031,490.03 2.17%

4 Earthwork 17.2 Km 321,668,221.00 294,137,310.79 213,798,486.52 66.47% 15,534,168.71 4.83% 229,332,655.23 71.29% 230,597,890.81 71.69% 23,428,778.58 7.28% 254,026,669.38 78.97%

5.1 Subbase 3.0 Km 56,843,760.00 45,709,526.19 22,692,595.61 39.92% 2,944,617.74 5.18% 25,637,213.35 45.10% - 0.00% 361,393.81 0.64% 361,393.81 0.64%

5.2 Base Course 6.7 Km 125,052,426.00 99,025,388.50 32,516,580.11 26.00% 6,783,504.24 5.42% 39,300,084.35 31.43% - 0.00% - 0.00% - 0.00%

Bituminous
6 38.5 Km 721,372,967.40 609,361,193.81 138,937,908.88 19.26% 43,682,366.85 6.06% 182,620,275.73 25.32% - 0.00% - 0.00% - 0.00%
Surfacing

8 Structures 1.0 Km 18,851,586.84 18,851,586.84 12,883,449.43 68.34% 1,553,847.36 8.24% 14,437,296.79 76.58% 3,249,590.40 17.24% - 0.00% 3,249,590.40 17.24%

9 Ancillary Works 2.9 Km 54,947,201.92 54,947,201.92 - 0.00% - 0.00% - 0.00% - 0.00% - 0.00% - 0.00%

Physical Progress
(Excluding General 91.8 km 1,720,987,953.13 1,551,949,321.45 623,621,991.38 36.24% 97,998,181.70 5.69% 721,620,173.08 41.93% 247,894,622.39 15.97% 23,790,172.39 1.53% 271,684,794.78 17.51%
Item)
Overall Progress
(Including General 100.0 km 1,874,702,309.25 1,705,663,677.57 718,328,918.45 38.32% 101,265,637.72 5.40% 819,594,556.17 43.72% 315,498,356.56 18.50% 24,512,688.84 1.44% 340,011,045.40 19.93%
Item)
100.00%
80.27%

78.97%

76.58%
71.29%
63.74%

53.92%

45.10%
44.45%

31.43%

25.32%

17.24%
2.17%

0.64%

0.00%

0.00%

0.00%
0.00%

Page |5 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

A. LINEAR PROGRESS OF MAJOR EARTHWORK ACTIVITIES

Progress
Total to the Total to
for
Contract Revised End of October
Bill No. Activity Description Unit October
Quantity Quantity Sept 2023 2023
2023

Km % Km % Km %

Bill 2: SERIES 2000:


2.0 Km 70 70 56 80 - - 56 80
Site Clearance

Bill 4: SERIES 4000:


4.0
Earthworks

Removal of
41.01(a) Km 70 70 44.6 64 - - 44.6 64
Unsuitable Material

Roadbed
41.02 Km 70 70 59 83 - - 59 83
Preparation

Cut to Borrow to
42.01 (a) Fill (Embankment Km 70 70 42 60 2 3 44 63
Fill)

Common
42.03 (a) Km 70 70 62 89 - - 62 89
Excavation

42.01 (b) Capping Layer Km 70 70 - - - - - -

Hard Rock
42.03 (b) Km 70 18 26 7 6 25 36
Excavation

Page |6 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

IV. LINEAR PROGRESS OF DRAINAGE WORKS

Progress
Total to the Total to
for
Contract Revised End of Sept October
Bill No. Activity Description Unit October
Quantity Quantity 2023 2023
2023

No. % No. % No. %

Bill No 3&8: Series


3.0/8.0 3000 & 8000 Bridge,
Culvert, Drainage

8.2 Slab Culverts No. 8 12 - - - - - -

Pipe Culverts
8.3 No. 59 61 9 4.75 - - 9 4.75
(Construction)

a) Pipe Production No. 710 1,680 232 13.81 15 0.89 247 14.70

U-Drain
8.4 No 56.2K 60K 823 1.37 - - 823 1.37
(Production)

Curb Stone
8.5 No 115.2K 116.43K 142 0.13 - - 142 0.13
(Production)

Page |7 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

V. CONTRACTOR’S EQUIPMENT STATUS

Equipment Status
Reporting Month: October 2023
S. No Description Unit
Planned Mobilized Active Shortage
1 Dozer No. 3 3 3 -
2 Chain Excavator No. 11 6 6 -5
3 Chain Excavator (JH) No. 1 3 3 -
4 Grader No. 6 5 5 -1
5 Single Drum Roller No. 8 7 7 -1
6 Loader No. 9 5 5 -4
7 Dump Truck No. 48 32 32 -16
8 Quarry Truck No. 5 2 2 -3
9 Water Truck No. 8 15 15 -
10 Fuel Truck No. 1 1 1 -
11 Wagon-Drill with Air Compressor No. 2 1 1 -1
12 Crusher (350 Ton/Hr) No. 2 1 1 -1
13 Bitumen Distributor No. 2 -2
14 Asphalt Paver No. 1 -1
15 Pneumatic Tyre Roller No. 1 -1
16 Double Steel Drum Roller No. 1 -1
17 Asphalt Plant No. 1 -1
18 Cutter No. 1 -1
19 Stationary Boiler No. 1 -1
20 Concrete Mixer (250 Lts) No. 13 2 2 -11
21 Compactor (Hand Tamper) No. 4 -4
22 Power Broom No. 1 -1
22 Chips Spreader No. 1 -1
22 Compressor No. 1 -1
22 Generator (1000KVA) BC & Aggregate No. 2 -2
24 Generator (100KVA) No. 1 1 1 -
25 Generator Camps (30KVA) No. 1 1 1 -
26 Truck Crane No. 1 1 1 -
27 Engineer's Car No. 9 9 9 -
28 Contractor's Car No. 12 12 12 -
29 Lowbed No. 1 1 1 -
Total 159 108 108 -60

Page |8 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

VI. MAJOR OFFICE WORKS DONE BY THE ONSULTANT


▪ Preparation of Measurement sheet and interim payment for IPC-12.

Page |9 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

▪ Approval of subbase construction data for the Main Access Road from km 2+420 to
22+480 and km 0+007 to 2+400.
▪ Compile as-built data for the monthly progress report of the executed works for
undercut excavation, embankment works, hard rock excavation, rock fill quantity and
final subgrade (Airfield).
▪ Approval of capping construction data for the Main Access Road from km 0+007 to
2+400 and km 2+420 to 22+480.
▪ Approval of subgrade construction data for the Main Access Road from km 0+007 to
2+400.
▪ Approval for canal working template for the Main Access Road from km 8+300-9+820
LHS, km 11+500-12+060 BHS, km 12+080-13+720 LHS, km 10+300-11+060 LHS and
km 11+080-11+280 BHS.
▪ Granting approval for the submitted Apron and Taxiway working Template
drawings.
▪ Granting approval for the submitted Main Access Road Revised template for Dimtu
Junction from km 0+000 to 0+600.

VII. OUTSTANDING ISSUES


▪ Shortage and timely mobilization of resources (Earthmoving machineries, asphalt
plant, cement, fuel, bitumen etc).
▪ Improve daily production rate for the precast productions (RC Pipe, RC U-drain, edge
cub stone etc.).
▪ Poor and unsustainable performance of the crusher plant and inadequate quarry
development.
▪ Failure to start preparatory works for Asphalt Surfacing works (Bitumen supply,
Asphalt plant installation etc.).
▪ Limitations in the provision of Engineer’s facilities (Office furniture, Tools, Lab
Equipments etc.)
▪ Non-compliance on dust control and management of crusher site and access roads.

P a g e | 10 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

VIII. ACTIONS TAKEN AND PROPOSED SOLUTIONS/WAY FOWARD

A. ACTIONS TAKEN BY THE EMPLOYER

▪ The Employer has strongly stated its concern in the slow rate progress of works.

▪ Fully released advance payments (Full of the supplier and the cash portions).

▪ Prioritizing the project in timely effect of Interim and advance Payments.

▪ Writing letter of concern to the Contractor for non-compliance on dust minimization

of crusher plant and access roads.

▪ Forwarding compliance monitoring of ESOSH issues of the project.

B. ACTIONS TAKEN BY THE ENGINEER

▪ The Engineer has frequently forwarded its concern in the contemporary slow rate

progress of works through official letters, minutes of meetings, verbal discussions etc.

▪ Most of the design issues are resolved, except for the compound roads (pavement

stratification) where it needs the consent of the from the Employer after submitting

the final design review report.

▪ All of the project RoW issues has been identified, measured and forwarded to the

Employer except for few at the compound roads sections.

▪ Timely approval and reply of shop drawings and RFIs.

C. ACTIONS TAKEN BY THE CONTRACTOR

▪ Mobilization of mandatory sub-contractors for the permanent works and STD/HIV

Prevention and control works in August 2023.

▪ Preparing three-months and annual agreed action plan.

▪ Purchasing of asphalt plant (Not arrived to the site yet).

D. PROPOSED SOLUTIONS/ WAY FORWARD

P a g e | 11 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

1. BY THE CONTRACTOR

▪ Mobilization of additional earthwork machineries and key personnel based on the

action plan.

▪ Diversify drainage structures construction and precast elements production.

▪ To start asphalt preparatory works.

2. BY THE EMPLOYER

▪ Ensure that the Contractor’s interim payments are timely paid.

▪ Clearing RoW obstructions of any.

3. BY THE ENGINEER

▪ Timely issuance of any instructions, approvals and reply to Contractor’s queries.


▪ Advise the Contractor and the Employer on the project risks and possible mitigation
measures.
▪ Manage the project in respect of time, cost and quality.
▪ Manage the project to ensure sustainability in terms of Environmental, Social and
Safety aspects.
▪ In collaboration with the stakeholders, facilitate and settle challenges of any that may
hinder the progress of the project.

IX. STATUS OF VARIATION ORDERS

Amount of Varied Work


Status
Date of
VO No. Description Addition as
Reduction as result Issue
result of VO
of VO (ETB)
(ETB)

VO-01

Total

P a g e | 12 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

X. EoT STATUS AND DEVELOPMENT

▪ No EoT granted until this reporting month.


XI. CLAIMS STATUS

▪ The Contractor has submitted the notice of claim for EoT and recovery of additional
cost due to the shortage of cement on the market through his letter of Ref. No.
PY/SBMTC/02/0029/15 dated August 17, 2023.
XII. DISPUTES TO DATE

▪ No disputes until this reporting month.


XIII. KEY ISSUES & REMARKS

▪ No Key issues so far except remarks are presented under section above.

XIV. SUPERVISION SERVICE CONTRACT

Supervision Contract

GONDWANA Engineering PLC in sub-consultancy


Supervision Consultant
with YLS Engineering PLC

Date of Contract signature 07th of July, 2022

Original Contract Amount


ETB 35,573,398.50
(Including 15% VAT)

Type of Contract Man-Month (Time Based)

Commencement date 21st of July, 2022

Contract period 36 Months plus 2 Years DLP

P a g e | 13 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

XV. FINANCIAL REPORT FOR CONSULTANT

Financial Accomplishment
Cumulative Previous Cumulative Total to-
Period This Month
of 2015 EFY Total of 2016 EFY date

Description ETB ETB ETB ETB ETB

Actual with 15%


VAT (From
8,981,503.60 11,526,940.33 995,349.94 3,540,786.68 12,522,290.27
Invoice No. 01 to
14)

XVI. WORKS CONTRACT GUARANTEE STATUS

Source of
S Amount (Local Expiry
Description Bond No Guarantee/ Remarks
No. Currency) ETB Date
Insurance

Oromia Including
Performance P/10/1702/21- March
1 237,568,086.45 Insurance DLP
Bond 22/1/00033 08, 2026
Co. period

P/10/1703/21- Effective
Advance Oromia
22/1/00020 March from
2 Payment 417,818,531.13 Insurance
1/E/10/1703/21- 22, 2025 March 23,
Bond Co.
22/17502/00003 2022

Retention
3 Payment - - - - -
Guarantee

Contractor’s 14th Apr


The United
All Risk 2022 up Section I
Insurance
4 (CAR) 2,732,032,994.14 GU/05/5011/2022/00004 to 14th Material
Company
Insurance Apr Damage
S.C.
Policy 2025

P a g e | 14 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

Source of
S Amount (Local Expiry
Description Bond No Guarantee/ Remarks
No. Currency) ETB Date
Insurance

followed
Third Party Section II
by 730
Liability Third
5 10,000,000.00 DLP
Insurance Party
Policy Liability

Contractor’s
Plant and
Equipment
6
Insurance
Policy-CPM,
Clause 21.1
(c)
Commercial
7
Vehicle Policy

Insurance for
The CoPA obliged Contractor to cover for amounts not recovered.
Damage to
8 Person and
Property
(Clause 22.1)

Accidents or
Injury to
9 Workmen
Policy (Clause
24.1 & 24.2)

P a g e | 15 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC


Contract Name: Construction Works of Soddo Junction (Dimtu) – Bilate
Military Training Centre Road Project
Contract No: W/36/ICB/OC/GOE/2014 EFY October 2023

Source of
S Amount (Local Expiry
Description Bond No Guarantee/ Remarks
No. Currency) ETB Date
Insurance

Contractor’s
Undertaking
letter for
Responsibility
10 for amounts
not
Recovered as
Sub-clause
21.3 of CoPA

P a g e | 16 Gondwana Engineering PLC in Sub-consultancy with YLS Engineering PLC