የቢሮ ማስታወሻ
Consultant: - GONDWANA Engineering PLC with sub consultant YLS Engineering plc
:-Senior Environmentalist
Encl (አባሪ):-
Subject (ጉዳዩ) ፡-Review and comment on Traffic Management Plan for Dimtu-Bilate Road
Project.
A traffic management plan is a document that details the way activities in the road corridor will be
carried out so they minimize inconvenience and help ensure road users and workers remain as safe as
possible.
This review is intended to assist the contractor in finalizing the traffic management plan for the Dimtu-
Blate Military Training Center Road Project document and to assist in its execution. Generally speaking,
there are various components to the contractor's supplied traffic management plan. As a result, it needs to
be modified to fulfill all Traffic Management and related components. It is suggested that the document's
structure and basic contents/chapters be followed as they are in the ERA manual.
Comments on the traffic management plan are presented below for each section of the Dimtu-Blate
Military Training Center Road Project. As a result, it is strongly recommended that the contractor work
meticulously and carefully on the Traffic Management Plan as outlined in this document and make an
effort to produce an in-depth and excellent management plan.
No Reference Comments
1. Table of content on page i Please add List of tables, list of figures and Acronyms.
2. 1. Introduction part page-1 Please, Change the Client's name to Ethiopian Road
Administration.
3. 1.2 Objective and scope of traffic Please add some details regarding the TMP's scope and
management plan part page-3 objective in TOR of ERA’s standard specification
manual 2013, which is stated in Division 1500(a).
4. 1.3 Project location part page-4 and Change location map of Dimtu-Blate Road (figure 1.1)
page-5 with a color print hence it’s a guiding manual.
Please, change the Engineer’s name to Gondwana
Engineering plc with sub consultant YLS Engineering
plc which is found in table 1.1.
5. 2. Objective and scope of traffic Please delete the redundant topics and add table 2.1 to
management plan part page-8 and the chosen part since this section is already defined
page-9 under 1.2 of the project's Traffic Management Plan.
6. 4.Constraction of temporary traffic Please refer to Division 1500 of Sub-clause 1504 (b) of
diversions part page-11 the 2013 ERA Standard Specification Manual for the
minimum width for two-way traffic management, which
is 7.5 meters rather than 7 meters.
7. 5.Provision of detour part page-13 The maximum length of a temporary traffic diversion
shall not exceed 1 kilometer in an urban area and 5
kilometers in a rural area, unless otherwise directed by
the Engineer (please refer to Division 1500 of Sub-
clause 1504 (a) of the 2013 ERA Standard Specification
Manual).