Summary

Road bed (RUNWAY)

Test Result
%
Sl/No. Tested Date Chainage Side Material source from KM % Compaction Remark
Laboratory Field specification
MDD OMC MC Density

1 3/5/2023 5+300-5+560 RHS EXISTING 1.37 18.6 19.1 1.34 98 95 OK

EXISTING 1.37 18.6 18.6 1.36 99 95 OK

EXISTING 1.62 16 15.7 1.56 96 95 OK

10/5/2023 5+120-5+260 LHS EXISTING 1.37 18.6 18.1 1.32 96 95 OK

EXISTING 1.37 18.6 17.5 1.33 97 95 OK

12/5/2023 3+960-4+280 LHS EXISTING 1.28 19.3 19.15 1.25 98 95 OK

EXISTING 1.28 19.3 19.32 1.23 96 95 OK

13/05/23 4+940-5+060 LHS EXISTING 1.46 17 15.2 1.39 95 95 OK

16/05/2023 5+740-6+000 RHS EXISTING 1.62 16 16 1.55 96 95 OK

EXISTING 1.62 16 16 1.55 96 95 OK

16/05/2023 5+140-5+300 RHS EXISTING 1.37 18.6 18.09 1.35 99 95 OK

EXISTING 1.37 18.6 20 1.31 96 95 OK

20/05/2023 4+320-4+480 LHS EXISTING 1.28 19.3 18.45 1.26 98 95 OK

23/05/2023 4+520-4+880 LHS EXISTING 1.46 16.9 17.5 1.41 97 95 OK

24/05/2023 4+680-4+880 RHS EXISTING 1.46 16.9 16.81 1.43 98 95 OK

EXISTING 1.46 16.9 17.43 1.43 98 95 OK


Summary

EMBANKMENT (MAIN ACESS ROAD)

Test Result % %
Material source
Sl/No. Tested Date Chainage Side Layer Laboratory Field Compactio specificatio Remark
from KM
n n
MDD OMC MC Density
1 27/04/2023 12+500-13+000 RHS 3RD 8+200 1.26 27.7 25 1.1 87 95 FAILED

8+200 1.26 27.7 24 1.11 88 95 FAILED


8+200 1.26 27.7 24 1.07 85 95 FAILED

8+200 1.26 27.7 23.4 1.07 85 95 FAILED


2 27/04/2023 6+000-6+400 LHS 5TH 8+200 1.26 27.7 27.7 1.21 96 95 OK

8+200 1.26 27.7 27.8 1.22 97 95 OK

8+200 1.26 27.7 26.8 1.24 98 95 OK


3 27/04/2023 6+400-6+540 LHS 4TH 8+200 1.26 27.7 27.6 1.21 96 95 OK

8+200 1.26 27.7 28 1.21 96 95 OK


4 27/04/2023 6+000-6+500 RHS 4TH 8+200 1.26 27.7 26.9 1.23 98 95 OK

8+200 1.26 27.7 26.7 1.23 98 95 OK

8+200 1.26 27.7 27.6 1.22 97 95 OK


5 27/04/2023 5+320-5+620 LHS 4TH 8+200 1.26 27.7 28.2 1.2 95 95 OK

8+200 1.26 27.7 27.1 1.23 98 95 OK


8+200 1.26 27.7 27.9 1.2 95 95 OK

6 2/5/2023 5+640-6+000 LHS 4TH 8+200 1.26 27.7 27.1 1.22 97 95 OK


8+200 1.26 27.7 26 1.22 97 95 OK
8+200 1.26 27.7 27.3 1.21 96 95 OK
7 2/5/2023 6+400-6+540 LHS 5TH 8+200 1.26 27.7 27.3 1.22 97 95 OK
8+200 1.26 27.7 27.8 1.21 96 95 OK
8 2/5/2023 6+540-6+800 LHS 4TH 8+200 1.26 27.7 27.1 1.21 96 95 OK
8+200 1.26 27.7 27.7 1.21 96 95 OK

9 3/5/2023 6+400-6+500 RHS 4TH 8+200 1.26 27.7 27.4 1.22 97 95 OK


8+200 1.26 27.7 27.4 1.22 97 95 OK
4/5/2023 6+000-6+400 RHS 5TH 8+200 1.26 27.7 27.7 1.24 98 95 OK
8+200 1.26 27.7 27.4 1.22 97 95 OK
10 4/5/2023 5+300-5+560 RHS 1ST 8+200 1.26 27.7 95 95 OK
28 1.20
8+200 1.26 27.7 28 1.22 97 95 OK
11 6/5/2023 6+000-6+200 RHS 5TH 8+200 1.26 27.7 27.2 1.23 98 95 OK
8+200 1.26 27.7 27 1.25 99 95 OK
12 7/5/2023 6+000-6+400 LHS 6TH 8+200 1.26 27.7 26 1.23 98 95 OK
8+200 1.26 27.7 27.2 1.22 97 95 OK
7/5/2023 6+400-6+500 RHS 5TH 8+200 1.26 27.7 27.8 1.24 98 95 OK
7/5/2023 13+000-13+560 RHS 5TH 8+200 1.26 27.7 26.4 1.23 98 95 OK
8+200 1.26 27.7 27.4 1.22 97 95 OK
8+200 1.26 27.7 27 1.21 96 95 OK
8+200 1.26 27.7 26.4 1.26 100 95 OK
8/5/2023 6+000-6+400 RHS 6TH 8+200 1.26 27.7 27.7 1.23 98 95 OK
8+200 1.26 27.7 27.2 1.23 98 95 OK
8+200 1.26 27.7 27.7 1.22 97 95 OK
10/5/2023 5+300-5+560 RHS 2ND 8+200 1.26 27.7 27.8 1.24 98 95 OK
8+200 1.26 27.7 27.5 1.24 98 95 OK
10/5/2023 6+540-6+800 LHS 5TH 8+200 1.26 27.7 26.6 1.23 98 95 OK
8+200 1.26 27.7 26.3 1.23 98 95 OK
11/5/2023 5+300-5+620 LHS 5TH 8+200 1.26 27.7 26.7 1.21 96 95 OK
8+200 1.26 27.7 26.9 1.2 95 95 OK
11/5/2023 5+640-6+000 LHS 5TH 8+200 1.26 27.7 27.7 1.23 98 95 OK
8+200 1.26 27.7 27.3 1.23 98 95 OK
8+200 1.26 27.7 28 1.22 97 95 OK
13/5/2023 6+240-6+400 LHS 7TH 8+200 1.26 27.7 28 1.21 96 95 OK
8+200 1.26 27.7 26 1.25 99 95 OK
13/05/2023 6+400-6+540 LHS 6TH 8+200 1.26 27.7 28 1.23 98 95 OK
8+200 1.26 27.7 25.6 1.24 98 95 OK
14/05/2023 5+120-5+280 LHS 1ST 8+200 1.26 27.7 28 1.2 95 95 OK
8+200 1.26 27.7 29 1.21 96 95 OK
3/5/2023 5+300-5+560 RHS 3RD 8+200 1.26 27.7 26.53 1.22 97 95 OK
8+200 1.26 27.7 27.55 1.21 96 95 OK
17/5/2023 4+940-5+060 LHS 1ST 8+200 1.26 27.7 27 1.23 98 95 OK
8+200 1.26 27.7 28 1.21 96 95 OK
18/05/2023 5+740-6+000 RHS 1ST 8+200 1.26 27.7 26.8 1.22 97 95 OK
8+200 1.26 27.7 27 1.21 96 95 OK
18/05/2023 6+240-6+400 RHS 7TH 8+200 1.26 27.7 26.5 1.21 96 95 OK
8+200 1.26 27.7 27.7 1.21 96 95 OK
18/05/2023 6+400-6+540 RHS 6TH 8+200 1.26 27.7 27 1.2 95 95 OK
19/05/2023 6+000-6+240 LHS 7TH 8+200 1.26 27.7 27.27 1.21 96 95 OK
8+200 1.26 27.7 26.53 1.21 96 95 OK
24/05/2023 6+000-6+400 LHS 8TH 5+320 1.37 23.8 23.4 1.31 96 95 OK
5+320 1.37 23.8 23.5 1.31 96 95 OK
5+322 1.37 23.8 22.9 1.33 97 95 OK
24/05/2023 4+020-4+280 LHS 1ST 8+200 1.26 27.7 27.7 1.22 97 95 OK
8+200 1.26 27.7 27 1.23 98 95 OK
SUMMARY
REPLACEMENT( RUNWAY)
Test Result
%
Sl/No. Tested Date Chainage Side Layer Material source from KM Laboratory Field % Compaction Remark
specification
MDD OMC MC Density

1 27/04/2023 0+100-0+300 (-15,-45) 2nd 0 + 420 1.33 24.4 24.27 1.27 95 95 OK

0 + 420 1.33 24.4 24.79 1.28 96 95 OK

2 27/04/2023 0+100-0+300 (0,-15) 3RD 0 + 420 1.33 24.4 24.7 1.31 98 95 OK

0 + 420 1.33 24.4 25 1.3 98 95 OK

3 2/5/2023 0+100-0+300 (-15,-30) 3RD 0 + 420 1.33 24.4 24 1.31 98 95 OK

0 + 420 1.33 24.4 24 1.29 97 95 OK

4 2/5/2023 0+000-0+140 (0,15) 1ST 0 + 420 1.33 24.4 24 1.28 96 95 OK

0 + 420 1.33 24.4 24 1.28 96 95 OK

5 2/5/2023 0+140-0+300 (0,15) 3RD 0 + 420 1.33 24.4 24.5 1.3 98 95 OK

0 + 420 1.33 24.4 23.8 1.30 98 95 OK

6 2/5/2023 0+140-0+300 (15,30) 2ND 0 + 420 1.33 24.4 24 1.30 98 95 OK

0 + 420 1.33 24.4 24.7 1.28 96 95 OK

7 4/5/2023 0+000-0+140 (15,30) 1ST 0 + 420 1.33 24.4 23 1.29 97 95 OK

0 + 420 1.33 24.4 23 1.28 96 95 OK

4/5/2023 0+140-0+300 (30,45) 2ND 0 + 420 1.33 24.4 23.7 1.3 98 95 OK

0 + 420 1.33 24.4 24.6 1.28 96 95 OK

8 5/5/2023 0+000-0+100 (-45,0) 0 + 420 1.33 24.4 24.5 1.29 97 95 OK

0 + 420 1.33 24.4 24 1.3 98 95 OK

0 + 420 1.33 24.4 23.9 1.29 97 95 OK

0 + 420 1.33 24.4 0 95 OK

9 6/5/2023 0+140-0+300 (15,30) 3RD 0 + 420 1.33 24.4 23.5 1.29 97 95 OK

0 + 420 1.33 24.4 24.2 1.28 96 95 OK

10 7/5/2023 0+100-0+300 (-30,-45) 3RD 0 + 420 1.33 24.4 24 97 95 OK


1.29

0 + 420 1.33 24.4 95 95 OK


24.0 1.27

7/5/2023 0+100-0+300 (0,-15) 4TH 0 + 420 1.33 24.4 97 95 OK


24.3 1.29

0 + 420 1.33 24.4 24 1.30 98 95 OK

8/5/2023 0+000-0+140 (30,45) 1ST 0 + 420 1.33 24.4 24 1.27 95 95 OK

0 + 420 1.33 24.4 25 1.29 97 95 OK

8/5/2023 0+000-0+140 (0,15) 2ND 0 + 420 1.33 24.4 95 95 OK


24 1.26

0 + 420 1.33 24.4 96 95 OK


23 1.28

8/5/2023 0+140-0+300 (0,15) 4TH 0 + 420 1.33 24.4 95 95 OK


24 1.27

0 + 420 1.33 24.4 95 95 OK


24 1.26

9/5/2023 0+000-0+140 (15,30) 2ND 0 + 420 1.33 24.4 97 95 OK


24 1.29

0 + 420 1.33 24.4 96 95 OK


24 1.28

10/5/2023 0+000-0+100 (-15,-30) 2ND 0 + 420 1.33 24.4 95 95 OK


24 1.27

11/5/2023 0+000-0+100 (0,-15) 0 + 420 1.33 24.4 97 95 OK


2ND 23.7 1.29

11/5/2023 0+100-0+300 (0,-15) 0 + 420 1.33 24.4 97 95 OK


5TH 23.8 1.29

0 + 420 1.33 24.4 97 95 OK


24.5 1.29

0+000-0+140 (30,45) 0 + 420 1.33 24.4 95 95 OK


14/05/23 2ND 26 1.27

0+140-0+300 (30,45) 0 + 420 1.33 24.4 95 95 OK


14/05/23 3RD 24 1.27

0 + 420 1.33 24.4 96 95 OK


23 1.28

17/5/2023 0+000-0+140 (0,15) 0 + 420 1.33 24.4 97 95 OK


3RD 24 1.29

0 + 420 1.33 24.4 97 95 OK


23 1.29

17/5/2023 0+140-0+300 (0,15) 5TH 0 + 420 1.33 24.4 96 95 OK


25 1.28
0 + 420 1.33 24.4 95 95 OK
24 1.27

17/5/2023 0+000-0+140 (15,30) 0 + 420 1.33 24.4 95 95 OK


3RD 24 1.27

0 + 420 1.33 24.4 96 95 OK


23 1.28

19/5/2023 0+140-0+300 (15,30) 0 + 420 1.33 24.4 95 95 OK


4TH 24.72 1.26

0 + 420 1.33 24.4 95 95 OK


24.73 1.27

22/5/2023 0+300-0+500 (30,45) 1st 0 + 420 1.33 24.4 97 95 OK


24.4 1.29

0 + 420 1.33 24.4 96 95 OK


24 1.28

0+300-0+500 (-30,-45) 0 + 420 1.33 24.4 96 95 OK


23/5/2023 1st 24.1 1.28

0 + 420 1.33 24.4 97 95 OK


24.5 1.29

24/5/2023 0+000-0+300 (-15,-30) 0 + 420 1.33 24.4 96 95 OK


4TH 23.81 1.28

0 + 420 1.33 24.4 97 95 OK


23.85 1.29
Summary
PIPE BEDDING (MAIN ACESS ROAD)
Test Result
Material source Laboratory
Sl/No. Tested Date Chainage Side
from KM
MDD OMC
1 15/05/2023 22+740 MM 1+000 1.15 15
MM 1+000 1.15 15
17/05/2023 22+314 MM 1+000 5.14 1.15
MM 1+000 5.4 1.15
23/05/2023 19+033 MM 1+000 1.15 5
MM 1+000 1.15 5
ESS ROAD)
Test Result
% %
Field Compact specifica Remark
MC Density ion tion
4.76 1.12 97 95 OK
4.72 1.11 97 95 OK
5.13 1.13 22 95 OK
5.5 1.12 21 95 OK
5.2 1.13 98 95 OK
5.21 1.11 97 95 OK