PROJECT: RECONSTRUCTION/REHABILITATION OF 50 FULLY DAMAGED

SCHOOLS IN BARA, DISTRICT KHYBER (UNDER CHINA ASSISTANCE)


ADP NO. 358/191268-190280 (2022-23 )
CLIENT DEPTT: ELEMENTARY & SECONDARY EDUCATION DEPARTMENT,
GOVT OF KHYBER PAKHTUNKHWA
Background
Original Approved PC-I Rs. 1,628.288 (M) dated 12-01-2016
1st Revised PC-I
Rs. 2,323.340 (M) dated 03-09-2019
Original Commencement with Completion February 2020 - February 2022

Work Stoppage September 2021 – October 2022

Physical Progress at Stoppage of work 12 % of the total project scope


Contractors Reluctance due to below reasons:
Reasons for Delay • Revision of MRS 2022 Due to Unprecedented Price Hike
• Issue in Releases
Foreign Rs.2265.34 M
Cost of the Project Rs. 3,215.79 M (USD 10.2974 USD)
(2nd Revised PC-I approved on 05th August 2022)
Local GoKP: Rs.950.389 M
Revised Tender Date October 2022

Revised Commencement Date December 2022

Revised Completion Date December 2023


(subject to timely availability of funds)
Financial Progress of the Project

Component PKR in Million USD in Million Percentage /


Item details PKR in Million Total cost

Foreign 303.000 1.506 13.37 %

Cumulative Release 833.000


Local 530.000 - 55.70 %

Foreign 203.000 1.160 8.79 %

Cumulative Expenditure 733.000


Local 530.000 - 55.70 %

Physical Progress 40%

Financial Progress 24%


YEAR WISE FINANCIAL DETAILS

GoKP Share Release Total Release Expenditure


S. No. Financial Years (Rs in Million) China Grant released (Rs in Million) (Rs. In Million)

1 2019-20 4.000 - 4.000 4.000

2 2020-21 146.073 - 146.073 146.073

60.000
3 2021-22 -- 60.000 60.000

203.0 (USD 1.159 M) 240.144


4 2022-23 37.144 240.144

5 2023-24 282.796 100.000* 382.796 282.796


(USD 0.347 M)

Total 530.013 (55%) 303.000 (13.37%) 833.013 (25.80%) 733.013


(22.80%)

*Rs. 100 Million credited to Federal Account No.1 on September 25, 2023. Subsequently amount transferred to Finance
Department KP on September 28th 2023. Finance Dept has been approached for the release of amount.
Details of Pending IPCs
S.No. Amount Amount Date of Submission Updated Status
(PKR in Million) (USD in Million)

01. 270 0.924 13th July 2023 Pending at China Side

Details of
02.
Pending 220 0.798 10th October 2023 In Process

Total
IPCs
490 1.72
Schools Numbers

Boy's Primary Schools 12

Girl’s Primary Schools 24

Boy’s Middle Schools 04

SCHOOLS Girl’s Middle Schools 02


BREAK UP
Boy’s High Schools 06

Girl’s High School 01

Girl’s Higher Secondary School 01

Total 50
Issues and Way Forward
S# Agenda Item Current Status Issues Way Forward

 Rs. 530 million released in local  Delays in releases from China side  EAD is requested to take up the
component. has affected the progress of the matter with the Chinese to
project. expedite the foreign
 Rs. 203 million (USD 1 million disbursement’s as per approved
received against foreign  CMC takes more than 3 months as MOU.
component so far. (Total foreign agreed in the Supplementary
1. Financial Progress component Rs.2265 M) Minutes for processing of IPCs
which causes delays in foreign
IPCs of Rs. 490 million has been disbursements therefore, delaying  CMC has been requested to
 reduce the processing time of
submitted to Chinese the project.
Management Company IPCs from 03 months to 01
month, Moreover, CMC has
already been requested through
EAD to expedite the processing
of already submitted IPCs and to
simplify the disbursement
mechanism.
Issues and Way Forward
S# Agenda Items Current Status Issues/Updates Way Forward

 Work in progress on all 50 Delays in disbursement EAD is requested to take up the


2. Physical Progress schools from China side is matter with the China to expedite
 Physical progress 40% hampering the physical the foreign disbursements.
progress

Revised supplementary minutes  Meeting held with CMC  As agreed in the meeting
incorporating comments of on 13th September Chinese Embassy was
3. Revised Supplementary Minutes concerned stakeholders has been 2023. approached through EAD for
shared with the CMC and requested  Revised Supplementary time extension upto December
on 9th, 16th & 28th August, 2023 Minutes agreed with 2024.
respectively to convene a meeting the Chinese  Moreover, EAD was requested
to finalize the implementation Management Company on 15th Sept to approach
minutes. including extension of Chinese Embassy for
the project. confirmation of date for
signing of revised
supplementary minutes. (letter
annexed)
Packages Description
Physical Contract -Price Expenditure
Package Progress % (PKR M) (PKR M)
School name
No.
GHS Akhun Talab Bara 45%
1 172.012 56.086
GHS Gul Zamir Killi 51%
GGHSS Kalanga Bara 21%

2 GPS Aman Talab Bara 42% 162.458 34.38


GGPS Sadam Jan Killi Bara 62%

GPS Zarmat Jan Killi 85%


GGPS Khial Zaman Bara 65%
3 150.520 51.094
GMS Yara Jan Killi Bara 40%
GGPS Nazir Shah Killi Bara 57%
GMS Gul Meran Killi Bara 81%
4 GGMS Malang Ghari Alamgudar Killi Bara 21% 136.590 30.439
GGPS Fazal Muhammad Killi Bara 21%
GGHS Karighar Ghary Bara 50%
5 184.350 51.047
GHS Alamgudar Bara 35%
Packages Description Physical Contract Price Expenditure
Progress % (PKR M) (PKR M)
Package No. School name
GGPS Najebullah Killi Bara 43%
GGPS Amir Khan Killi Bara 26%
6 155.844 53.250
GPS Babu Jan Killi Mandi Kas Bara 43%
GPS Abdar Killi Bara 35%
GPS Spin Qabar 20%
GMS Speen Qabar Bara 25%
7 175.005 34.720
GGPS Hussain Khan Killi Bara 38%
GPS Haji Gulab Khel Killi Bara 16%
GGPS Mian Khan Killi Bara 25%
GGPS Gul Muhammad Killi Bara 24%
8 154.169 48.084
GGPS Sher Killi Bara 73%
GGPS Akhunzada Killi Bara 25%
GPS Abdul Qatar Bara 25%
GGPS Juma Khan Killi Bara 55%
9 137.787 17.983
GGPS Sultan Muhammad Killi Bara 21%
GGPS Haji Bazot Killi Bara 45%
GGPS Gulab Khan Killi Bara 21%
GGPS Aqal Jan Killi Bara 45%
10 174.438 31.084
GMS Gandao Bara 22%
GPS Yara Din Killi Bara 22%
Packages Description Physical Contract Price Expenditure
Progress % (PKR M) (PKR M)
Package No. GGPMS Badshah khan School
killi Naveyname
kaApril Bara 29%
GPS Tamaash Killi Bara 22%
11 166.349 31.186
GGPS Ibrahim Aman Killi Bara 20%
GGPS Saida Jan Killi Bara 17%
GPS Khan Wali Killi Bara 20%
GMS Azeem Killi, Bara 20%
12 186.800 52.755
GGPS Babo Khan Killi Bara 30%
GGPS Akhtar Shah Killi Bara 55%
GHS Hissara Arjali Nadi Shalobar Bara 26%
13 GPS Shalobar No.1 Noor Muhammad Killi 70% 156.750 30.613
GGPS Shah Hussain Killi Achini Bara 21%
GHS Shalobar Jamal Baz Killi Bara 61%
14 117.797 29.812
GGPS Minar Killi Muslim Dhand Bara 21%
GHS Janas Killi Bara 22%
15 GPS Khana Ziarat Kamar Khel Bara 18% 169.569 32.482
GPS HINDUSTAN KILLI 22%
16 Solarization of All listed Schools 124.965 -
51
PACKAGE-01

1. GHS Akhun Talab Bara

2. GHS Gul Zamir Killi


GHS Akhun Talab Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary and Middle Structure Completed
89.705 M 21.289 M Balance Work Balance Work
 High Block Structure Completed up to Plinth Beam
01-12-2022 30-12-2023
GHS Gul Zamir Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary and Middle Gray Structure Completed
82.306 M 34.797 M Balance Work Balance Work  High Block Structure Completed up to FF Column
01-12-2022 30-12-2023 Finishing work ,toilet block and boundary wall is in progress
GHS Gul Zamir Killi
PACKAGE-02

1. GGHSS Kalanga Bara

2. GPS Aman Talab Bara

3. GGPS Sadam Jan Killi Bara


GGHSS Kalanga Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Ground Floor Columns and Brick work Completed. Form work
94.205 M 14.08 M Balance Work Balance Work
and steel is in progress
01-12-2022 30-12-2023
GPS Aman Talab Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block Gray Structure Completed up Roof Slab
33.070 M 7.59 M Balance Work Balance Work
 Boundary wall and Toilet Block work start
01-12-2022 30-12-2023
GGPS Sadam Jan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block Gray Structure Completed
35.183 M 12.71 M Balance Work Balance Work
 Boundary wall and Toilet Block work start
01-12-2022 30-12-2023
PACKAGE-03
1. GPS Zarmat Jan Killi

2. GGPS Khial Zaman Bara

3. GMS Yara Jan Killi Bara

4. GGPS Nazir Shah Killi Bara


GPS Zarmat Jan Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary ,Toilet block and boundary wall Gray Structure
31.814 M 12.323 M Balance Work Balance Work Completed
01-12-2022 30-12-2023 Finishing work is in progress
GPS Zarmat Jan Killi
GGPS Khial Zaman Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary Gray Structure Completed ,Toilet block and boundary
28.900 M 12.068 M Balance Work Balance Work wall Structure work is in progress
01-12-2022 30-12-2023  Plaster Completed ,Marble fixing in progress
GMS Yara Jan killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Gray Structure Completed up to FF columns
53.660 M 13.758 M Balance Work Balance Work
 Middle structure Completed
01-12-2022 30-12-2023
GGPS Nazir shah Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Gray Structure Completed
36.146 M 12.945M Balance Work Balance Work
 Plaster work is in progress
01-12-2022 30-12-2023
PACKAGE-04

1. GMS Gul Meran Killi Bara

2. GGMS Malang Ghari Alamgudar Killi Bara

3. GGPS Fazal Muhammad Killi Bara


GMS Gul Meran Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary and Middle Block Gray Structure Completed and
43.774 M 11.441 M Balance Work Balance Work Finishing work is in progress
01-12-2022 30-12-2023  Toilet , Boundary wall structure and work is in progress
GMS Gul Meran Killi
GGMS Malang Ghari Alamgudar Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary and Middle block Gray Structure Completed up to GF
56.856 M 9.569 M Balance Work Balance Work
Columns Primary Block GF Slab Work is in Progress
01-12-2022 30-12-2023
GGPS Fazal Muhammad Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
35.961 M 9.429 M Balance Work Balance Work  Primary Block GF Slab Work is in Progress
01-12-2022 30-12-2023
PACKAGE-05

1. GGHS Karighar Ghary Bara

2. GHS Alamgudar Bara


GGHS Karighar Ghary Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary and Middle block Gray Structure Completed
87.204 M 29.026 M Balance Work Balance Work
 High block Gray structure completed up to GF Beam
01-12-2022 30-12-2023
Revised Contract
GHS Alam Gudar Bara
Expenditure Commencement Completion Present Status
Cost

97.326 M 22.022 M GGHS ALAM GUDAR


Old 10/02/2020
Balance Work
01-12-2022
Old 09/02/2022
Balance Work
30-12-2023
 All block GF Columns completed
Site Start 6 month delay due to land issue

GHS Alamgudar Bara


PACKAGE-06
1. GGPS Najebullah Killi Bara

2. GGPS Amir Khan Killi Bara

3. GPS Babu Jan Killi Mandi Kas Bara

4. GPS Abdar Killi Bara


GGPS Najeeb ULLAH Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
32.14 M 8.001 M Balance Work Balance Work Gray Structure Completed
01-12-2022 30-12-2023
GGPS Amir Khan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost

43.30 M 9.479 GGPS Amir Khan Killi Bara


Old 10/02/2020
Balance Work
01-12-2022
Old 09/02/2022
Balance Work
30-12-2023
 Primary block FF Slab form work in progress
GPS Babu Jan Killi Mandi Kas Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost

43.521 M GPS Babu Jan Killi Mandi Kas Bara


17.312 M
Old 10/02/2020
Balance Work
01-12-2022
Old 09/02/2022
Balance Work
30-12-2023
 Gray structure Completed up FF Columns
GF finishing is in progress
GPS Abdar Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
36.882 M 13.266 M Balance Work Balance Work  Primary Gray structure Completed..
01-12-2022 30-12-2023
PACKAGE-07
1. GPS Spin Qabar

2. GMS Speen Qabar Bara

3. GGPS Hussain Khan Killi Bara

4. GPS Haji Gulab Khel Killi Bara


GPS Spin Qabar
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
35.316 M 2.317 M Balance Work Balance Work  GF Columns and Brick Work completed
01-12-2022 30-12-2023
GMS Speen Qabar Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary and Middle Block GF Column completed and Brick
67.773 M 17.299 M Balance Work Balance Work
work is also completed
01-12-2022 30-12-2023
GGPS Hussain Khan Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
35.008 M 10.314 M Balance Work Balance Work  FF Slab form work is in progress
01-12-2022 30-12-2023
GPS Haji Gulab Khel Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
36.908 M 3.416 M Balance Work Balance Work  Primary Block GF columns Completed
01-12-2022 30-12-2023
PACKAGE-08
1. GGPS Mian Khan Killi Bara

2. GGPS Gul Muhammad Killi Bara

3. GGPS Sher Killi Bara

4. GGPS Akhunzada Killi Bara


GGPS Mian Khan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
35.667 M 10.004 M Balance Work Balance Work  Primary Block Column and Brick Work Completed
01-12-2022 30-12-2023
GGPS Gul Muhammad Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
43.419 M 12.192 M Balance Work Balance Work  Primary Block column Completed
01-12-2022 30-12-2023
GGPS Sher Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary Block Grey Structure Completed and Finishing work is
38.204 M 13.345 M Balance Work Balance Work in progress
01-12-2022 30-12-2023 Boundary wall work is in progress
GGPS Sher Killi Bara
GGPS Akhunzada Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block GF Column Completed and Boundary wall is in
36.879 M 2.195 M Balance Work Balance Work
progress
01-12-2022 30-12-2023
PACKAGE-09
1. GPS Abdul Qatar Bara

2. GGPS Juma Khan Killi Bara

3. GGPS Sultan Muhammad Killi Bara

4. GGPS Haji Bazot Killi Bara


GPS Abdul Qatar Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary ,Toilet block and boundary wall Gray Structure
33.439 M 3.903 M Balance Work Balance Work Completed
01-12-2022 30-12-2023 Plaster Completed ,Marble fixing in progress
GGPS Juma Khan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
37.007 M 2.536 M Balance Work Balance Work  Primary Blok Grey Structure Completed
01-12-2022 30-12-2023
GGPS Sultan Muhammad Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost

Old 10/02/2020 Old 09/02/2022  Primary ,Toilet block and boundary wall Gray Structure
34.802 M 4.127 M Balance Work Balance Work Completed
01-12-2022 30-12-2023 Plaster Completed ,Marble fixing in progress
GGPS Haji Bazot Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
32.539 M 4.665 M Balance Work Balance Work  Primary Block Grey Structure Completed Up FF Columns
01-12-2022 30-12-2023
PACKAGE-10
1. GGPS Gulab Khan Killi Bara

2. GGPS Aqal Jan Killi Bara

3. GMS Gandao Bara

4. GPS Yara Din Killi Bara


GGPS Gulab Khan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
39.298 M 12.258 M Balance Work Balance Work  Primary Block GF Structure Completed
01-12-2022 30-12-2023
GGPS Aqal Jan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
32.265 M 6.337 M Balance Work Balance Work  Primary Block Grey Structure Completed Up FF Columns
01-12-2022 30-12-2023
GMS Gandao Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
63.576 M 6.92M Balance Work Balance Work  Primary and Middle GF Column Completed
01-12-2022 30-12-2023
GPS Yara Din Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
39.298 M 5.569 M Balance Work Balance Work  Primary Block Sub Structure Completed
01-12-2022 30-12-2023
PACKAGE-11
1. GGPMS Badshah khan killi Navey killi Bara

2. GPS Tamaash Killi Bara

3. GGPS Ibrahim Aman Killi Bara

4. GGPS Saida Jan Killi Bara


GGPMS Badshah khan killi Navey kamar Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary and Middle GF Structure Completed and slab Form
54.661 M 15.572 M Balance Work Balance Work
Fork is in Progress
01-12-2022 30-12-2023
GPS Tamaash Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
35.606 M 5.931 M Balance Work Balance Work  Primary Block GF Slab Work is in Progress
01-12-2022 30-12-2023
GGPS Ibrahim Aman Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
36.574 M 6.188 M Balance Work Balance Work  Primary Block GF Column and Bick Work completed
01-12-2022 30-12-2023
GGPS Saida Jan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
39.508 M 5.495 M Balance Work Balance Work  Primary Block Sub Structure Completed
01-12-2022 30-12-2023
PACKAGE-12
1. GPS Khan Wali Killi Bara

2. GMS Azeem Killi, Bara

3. GGPS Babo Khan Killi Bara

4. GGPS Akhtar Shah Killi Bara


GPS KHAN WALI KILI BARA
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
43.188 M 11.749 M Balance Work Balance Work  Primary Block GF Column Completed
01-12-2022 30-12-2023
GMS Azeem Killi, Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
64.169 M 12.30 M Balance Work Balance Work  Primary Block GF Column Completed Slab Form work start
01-12-2022 30-12-2023
GGPS Babo Khan Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block GF Columns Completed an Boundary wall is in
42.538 M 12.298 M Balance Work Balance Work
progress
01-12-2022 30-12-2023
GGPS Akhtar Shah Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block Grey structure almost Completed and Boundary
36.904 M 16.408 M Balance Work Balance Work
wall work is in progress
01-12-2022 30-12-2023
PACKAGE-13
1. GHS Hissara Arjali Nadi Shalobar Bara

2. GPS Shalobar No.1 Noor Muhammad Killi

3. GGPS Shah Hussain Killi Achini Bara


GHS Hissara Arjali Nadi Shalobar Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
84.711 M 8.479 M Balance Work Balance Work  All block GF Column Completed
01-12-2022 30-12-2023
GPS Shalobar No.1 Noor Muhammad Killi
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 Primary Block Grey Structure Completed
37.466 M 15.486 M Balance Work Balance Work
Finishing Work and Boundary wall Work is In progress
01-12-2022 30-12-2023
GGPS Shah Hussain Killi Achini Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
34.573 M 6.647 M Balance Work Balance Work  Primary block GF structure completed
01-12-2022 30-12-2023
PACKAGE-14

1. GHS Shalobar Jamal Baz Killi Bara

2. GGPS Minar Killi Muslim Dhand Bara


GHS Shalobar Jamal Baz Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022  Primary and Middle Block Grey Structure Completed finishing
21.157M 14.079 M Balance Work Balance Work work is in progress
01-12-2022 30-12-2023 High Block GF slab & Boundary wall work is In Progress
GHS Shalobar Jamal Baz Killi Bara
GGPS Minar Killi Muslim Dhand Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
40.427 M 8.655 M Balance Work Balance Work  Primary Block GF Column Work Is in progress
01-12-2022 30-12-2023
PACKAGE-15
1. GHS Janas Killi Bara

2. GPS Khana Ziarat Kamar Khel Bara

3. GPS Hindustan killi


GHS Janas Killi Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
 All Block GF Columns completed and GF Slab Work is in
95.279 M 17.558 M Balance Work Balance Work
progress
01-12-2022 30-12-2023
GHS Janas Killi Bara
GPS Khana Ziarat Kamar Khel Bara
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
37.575 M 6.180 M Balance Work Balance Work  Primary Block Sub Structure work Completed
01-12-2022 30-12-2023
GPS HINDUSTAN KILLI
Revised Contract
Expenditure Commencement Completion Present Status
Cost
Old 10/02/2020 Old 09/02/2022
36.716 M 8.744 M Balance Work Balance Work  Primary Block GF Structure Completed
01-12-2022 30-12-2023