Dated. 15.06.

2020
(1)

Name of Project: Construction of 2-lane with paved shoulders configuration &


strengthening of NH-58 from km 350.00 to km 355.00 (Kaliyasaur re-alignment) (Length:
3.72 km) (Pkg-1)
• Sanctioned cost with Date : 148.02 Cr. & 18.12.2015

• Implementing Agency : PWD

• Mode of executions : EPC

• Awarded cost, : Rs. 126.93 Cr.

• C.B. No. with Date. : 08/CE-NH/2017, Dt. 27.05.2017

• appointed date : 16.01.2018

• Contractor and Authority : M/s Dharamraj Contracts (India) Private Limited/ M/s
Engineer Highway Engineering Consultants in association with L-
Telford Consulting Engineers Pvt. Ltd.
• Scheduled date of completion as : 15.07.2020
per contract (i) (01/03/2022 as per EOT Sanctioned)
(ii) (31.08.2020 As per EOT recommended by AE
due to COVID-19)

• Status of milestones:

S.N. As per C.B As per EOT EOT Applied Achieved /Not Achieved
1st 27.10.2018 11.06.2020 - -

2nd 15.04.2019 28.11.2020 - -

3rd 21.11.2019 06.07.2021 - -

4th 16.7.2020 02.03.2022 31.08.2022 -

• Tentative date of completion : 31.08.2022

• Financial progress in Rs Cr & in %) : 26.323 Cr. (20.47%)

• Physical progress (in %) : 10.74 %

S.N Item As per scope Progress S.N Item As per scope of Progress
of work (in (In work (in (In
Km/no.) Km/no.) Km/no.) Km/no.)
1 H.S.C 3.22 km 2.150 km. 7 B/Wall/Gabion 1.385 km 0.233 Km
wall
2 Sub Grade 3.22 km 1.900 Km. 8 Culvert 11 No 6 Nos.
3 GSB 3.22 km - 9 Drain - -
4 DLC 3.22 km - 10 Crash Barrier - -
5 PQC 3.22 km -
6 Utility Duct 3.22 km -
7 R/Wall 1.685 km 0.737 km
Minor Bridge NIL
Major Bridge 3 Nos Bridge
1. 182.10 meter = Abutment work complete and sub structure in progress.
2. 250.00 meter = Foundation excavation work in progress.
3. 162.10 meter = Dispute has been cleared on 25/02/2020 Geo-Technical
investigation & approach prepration work in progress.
Dated. 15.06.2020

 Status of COS:

S.No Detail of COS Cost of COS Status

1 Protective Works at Dumping Zones 6.03 Crore Under Review at AE

2 Hill Side & valley Side Protections work & 14.43 Crore Under Review at AE
Fixing of W-Beam Crash Barrier

3 Protection work Hill Side @ Km 345+430 to 20.6 Crore To be submit by contractor


345+640 = 210m & Cross drainage works

 Status of Dumping Zone-

Sanctioned (No) Used (No) New Required Remark


Additional dumping zone forest
9 7 2
proposal under process.

 Status of Forest Land Transfer Case.


Stage-I Stage-II

User DFO Nodal RO, MoEF User DFO Nodal RO, Remark
Agency Officer Agency Officer MoEF

Sent to
Stage- I Sanctioned DFO
on
16.05.2020
• Status of LA (Hindrance only):- Affected length is 1.435 km. (length of 35 m
affected from km. 344.870 to km 344.905 due to Khasara no 16 Tree cutting/forest
clearance: NPV & CA of Rs. 0.65 cr. released in December 2017. Issue in 1.4 km
length from Km 347.020 to km 348.420 due to opposition of bypass by local
villagers resulting in non-felling of 156 nos. trees.
 Utility shifting(Hindrance only):- NIL

 Tree Cutting/Forest Clearance – 1. Due to opposition of bypass by local villagers


Khankra 156 Nos trees have not been felled yet.
2. NPV & CA amount of Rs. 6536235.00 lacs.
deposited in
• Total Encumbrance free land available – 2.285 Km (61.42%)
 Any Other issues:
(i) Slow progress by contractor as the construction of diversion to transport heavy
equipments on other bank of river Alaknanda was delayed as coffer Dam being
constructed washed away. Presently contractor has transported equipment by boat.
(ii) Villagers of Khankra are opposing to bypass their village. Chief Secretary, Govt. of
Uttarakhand during meeting held on 10.12.2018 directed to expedite the matter and
progress of work. Again a joint survey has been made by NH PWD in July 2019 and new
alignment proposed by villagers was not found suitable hence rejected by NH PWD and
report submitted to District administration accordingly. Work was started on 11.11.2019
which was again stopped by villagers. DM Rudraprayag conducted meeting with villagers
on 10-12-2019 to resolve the issues but still villagers has not given consent to start the
works beyond second bridge. Construction of 2 No bridges is under progress. Works
beyond second bridge to be started after removal of hindrance of trees.
Dated. 15.06.2020
(3)
Name of Project: Widening and Strengthening to 2-lane with paved shoulder
from km 0.00 (Design km 0.00) to km 16.440 (Design km 18.700) including
existing 3.470 km of Rudraprayag Bypass of NH-109 (Length: 18.70 km) Pkg-6)
• Sanctioned cost with Date : 141.47 Cr. 08.01.2016

• Implementing Agency : PWD

• Mode of executions : EPC

• Awarded cost, : Rs 88.89 Cr.

• C.B. No. with Date. : 06 /CE-NH&B/2016, Dt. 18.12.2016

• appointed date : 21.11.2017

• Contractor and Authority : M/s R.G.Buildwell Engineers Ltd. & M/s


Engineer Highway Engineering Consultants in Association
with L-Telford Consulting Engineers.
• Scheduled date of completion as : 20.11.2019
per contract
• Status of milestones:

S.N. As per C.B As per EOT EOT Applied Achieved /Not Achieved
1st 20.05.2018 - Achieved
2nd 21.11.2018 - Achieved
3rd 25.05.2019 - Achieved within grace period
4th 20.11.2019 05.04.2020 28.12.2020 Interim EOT sanctioned
(137 days and EOT 2 applied
for 227 days) has been sent to
SE, NH, Circle on dated.

• Tentative date of completion 28.12.2020 (EOT-2


applied for 227 days)
• Financial progress (in Rs Cr & in %) : Rs. 70.83 Cr. (79.69 %)

• Physical progress (in %) : 82.40 %


 Status of COS
Sr. Detail of COS Cost of Status
No COS
1 Approach road of Existing 8.41 Under Review at PWD
Bridge @ 0+463 ( & Retaining Crore
Wall @ Km 0+550 to 0+660
=110meter
2 Dumping Zone Protection 4.55 Under Review at PWD
work Crore
3 Retaining Wall above 10.5 m 3.89 Under Review at PWD
Height Crore
S. Item As per Progress S.N Item As per Progress
N scope of (In Km/no.) scope of (In Km/no.)
work (in work (in
Km/no.) Km/no.)
1 H.S.C 18.3365 km 16.500 Km. 8 R/Wall 5320 Mtr. 5320 Mtr.
2 Sub Grade 18.3365 km 16.000 Km 9 B/Wall/Gabion wall 5410 Mtr. 5411 Mtr.
3 GSB 18.3365 Km 15.600 Km. 10 Culvert 47 Nos. 47 Nos.
4 WMM 18.3365 Km 15.250 Km. 11 Drain 22.600 Km. 15.150 Km.
5 DBM 18.3365 Km 13.400 Km. 12 Crash Barrier 9.739 Km 6.101 km
6 B.C. 18.3365 Km 9.600 Km. 13 Rehabilitation of minor 3.00 Nos 3.00 Nos.
bridge
7 Utility Duct 18.3365 km 13.000 Km.
Minor Bridge NIL

Major Bridge NIL

 Status of Dumping Zone-

Sanctioned (No) Used (No) New Required Remark


Forest proposal of additional
4 3 2 dumping zone under process.

 Status of Forest Land Transfer Case.


Stage-I Stage-II
User DFO Nodal RO, MoEF User DFO Nodal RO, Remark
Agency Officer Agency Officer MoEF
Sent to
DFO
Stage- I Sanctioned on
16.05.2020

• Status of LA (Hindrance only) :- Affected length is 2.264 Km due to Tilwara


area/Silli area compensation not given yet and due to pvt. structure on govt.
land, compensation not given yet

 Utility shifting (Hindrance only):- Not affecting the progress of work.

• Tree Cutting/Forest Clearance – Completed. NPV & CA amount of Rs. 71.77 lacs
deposited in September 2017

• Total Encumbrance free land available –16.436 Km (87.90%)


Dated. 15.06.2020
• Any other issues: The owners of many structures especially in the markets of
Tilwara (km.9.980 to 12.245) have filed a number (approximately 30) of writ
petitions in December 2017 which has been decided by the Hon’ble High Court,
Nainital in May 2019.
• For valuation of structure as per original designed 24m RoW has been made.
Hindrance issue of Tilwara area was referred to Ro-MoRTH. RO-MoRTH through
its letter No. NH-109-UR-2015-16-448 dt 16.01.2020 has issued direction to
reduce ROW at these locations to a minimum of 14 meter. Accordingly the
marking of land and structures valuation work completed.