Professional Documents
Culture Documents
2020
(1)
• Contractor and Authority : M/s Dharamraj Contracts (India) Private Limited/ M/s
Engineer Highway Engineering Consultants in association with L-
Telford Consulting Engineers Pvt. Ltd.
• Scheduled date of completion as : 15.07.2020
per contract (i) (01/03/2022 as per EOT Sanctioned)
(ii) (31.08.2020 As per EOT recommended by AE
due to COVID-19)
• Status of milestones:
S.N. As per C.B As per EOT EOT Applied Achieved /Not Achieved
1st 27.10.2018 11.06.2020 - -
S.N Item As per scope Progress S.N Item As per scope of Progress
of work (in (In work (in (In
Km/no.) Km/no.) Km/no.) Km/no.)
1 H.S.C 3.22 km 2.150 km. 7 B/Wall/Gabion 1.385 km 0.233 Km
wall
2 Sub Grade 3.22 km 1.900 Km. 8 Culvert 11 No 6 Nos.
3 GSB 3.22 km - 9 Drain - -
4 DLC 3.22 km - 10 Crash Barrier - -
5 PQC 3.22 km -
6 Utility Duct 3.22 km -
7 R/Wall 1.685 km 0.737 km
Minor Bridge NIL
Major Bridge 3 Nos Bridge
1. 182.10 meter = Abutment work complete and sub structure in progress.
2. 250.00 meter = Foundation excavation work in progress.
3. 162.10 meter = Dispute has been cleared on 25/02/2020 Geo-Technical
investigation & approach prepration work in progress.
Dated. 15.06.2020
Status of COS:
2 Hill Side & valley Side Protections work & 14.43 Crore Under Review at AE
Fixing of W-Beam Crash Barrier
User DFO Nodal RO, MoEF User DFO Nodal RO, Remark
Agency Officer Agency Officer MoEF
Sent to
Stage- I Sanctioned DFO
on
16.05.2020
• Status of LA (Hindrance only):- Affected length is 1.435 km. (length of 35 m
affected from km. 344.870 to km 344.905 due to Khasara no 16 Tree cutting/forest
clearance: NPV & CA of Rs. 0.65 cr. released in December 2017. Issue in 1.4 km
length from Km 347.020 to km 348.420 due to opposition of bypass by local
villagers resulting in non-felling of 156 nos. trees.
Utility shifting(Hindrance only):- NIL
S.N. As per C.B As per EOT EOT Applied Achieved /Not Achieved
1st 20.05.2018 - Achieved
2nd 21.11.2018 - Achieved
3rd 25.05.2019 - Achieved within grace period
4th 20.11.2019 05.04.2020 28.12.2020 Interim EOT sanctioned
(137 days and EOT 2 applied
for 227 days) has been sent to
SE, NH, Circle on dated.
• Tree Cutting/Forest Clearance – Completed. NPV & CA amount of Rs. 71.77 lacs
deposited in September 2017