DETAILED ESTIMATE
CD1 - SITAPUR
1 Report :-
(a) Proper reference have been quoted and attested copies attached to estimate.
(b) In case of revised estimate the amounts of excess has been given item wise in the
comparative statement with detailed reasons.
(c) Signatures of A.E., E.E., & S.E. exist.
2 Specifications :-
(a) Details of specifications for each item of work are included in the estimate.
(b) Signatures of A.E., E.E., & S.E. exist.
3 Designs :-
(a) These have been prepared as per standard practices and C.E's instructions.
(b) Each design has been signed by E.E. & S.E. in the end, and important designs by C.E. as well.
4 Analysis of Rates :-
(a) Analysis of non-schedule of item are based on the market rates.
(b) Each analysis have been signed by J.E., A.E., E.E., & S.E. in the end.
5 Details of measurements :-
Each page has been signed J.E., A.E. & E.E. in the end of each set.
6 Bill Of Quantity :-
Each page has signature of J.E., A.E. & E.E. in the end of each set.
7 Summary of estimated cost :-
These have been signed by J.E., A.E., E.E. & S.E.
8 Plans :-
These have been signed by J.E., A.E., E.E. & S.E.
9 General :-
1- Name and designation should exist, below all signature and corrections.
2- Each page of the designed, analysis of rates, details of the measurements, bill of quantity
and summary of estimated cost should be certified 'Checked and corrected' by JE(T)
of divisional office and circle office with their signature at the end.
3- The signature of the local head of the department exist on report,
specification, summary of estimated cost and the plans.
10 Designation :-
All the work shall be carried out as per Detailed Specifications of U.P.P.W.D., M.O.R.D. & H./ I.R.C
/ SOR/ DSR. and as per Circulars issued from time to time by Engineer-in-Chief, Chief Engineer and as
per directions of Engineer-in-Charge of the work.
Quarry Details
Bitumen/Emulsion Details
Certified that the cartage from the shortest possible route where the overall rates are cheapest has been adopted
134 Item Name :- Construction of Embankment with Material Obtained from Roadway Cutting
MORD Construction of embankment with approved materials deposited at site from roadway cutting and
excavation from drain and foundation of other structures graded and compacted to meet requirement of
Chapter-03 Tables 300.1 and 300.2 as per Technical Specification Clause 301.5
3.3 Output Quantity :- 100.00 Cubic Meter
242
MORD Item Name :- (ii)Providing and applying tack coat with Bitumen VG-10 using bitumen distributor at
the rate of 0.30 to 0.40 kg per sqm on the prepared dry and hungry bituminous surface cleaned with
Chapter-05 Hydraulic broom as per Technical Specification Clause 503.
(Bases an
5.2(ii) Output Quantity :- 1,750.00 Square Meters
Item No : 3.3
Item Description : Construction of Embankment with Material Obtained from Roadway Cutting
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other
structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5
Unit Name : Cubic Meter
Km Chainage Chainage Number Length Calculation
Description Width Depth Unit Quantity
No. From To Description
0.000 2.000 2.000 2000.00 1.875 0.150 1125.000
1.00 patri m³
0
Item No : 4.7(3)(A)
Item Description : 3)WBM Grading 3
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to
fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405.
(A)By Manual Means
Unit Name : Cubic Meter
Km Chainage Chainage Number Length Calculation
Description Width Depth Unit Quantity
No. From To Description
0.000 2.000 0.250 2000.00 3.000 0.075 81.000
1.00 Patch m³
0
Item No : 5.2(ii)
Item Description : (ii)Providing and applying tack coat with Bitumen VG-10 using bitumen distributor at the rate of 0.30 to 0.40 kg per sqm on the
prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
Unit Name : Square Meters
Km Chainage Chainage Number Length Width/Hei Calculation
Description Unit Quantity
No. From To ght Description
0.000 2.000 1.000 2000.00 3.000 6000.000
1.00 tack m²
0
Item No : 5.9Case-I(I)
Item Description : 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration
grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either
Type A or Type B or Type C as per Technical Specification Clause 508.
Case - I By Manual Means
(I)Bitumen (S-90)
Unit Name : Square Meters
Km Chainage Chainage Number Length Width/Hei Calculation
Description Unit Quantity
No. From To ght Description
0.000 2.000 1.000 2000.00 3.000 6000.000
1.00 PC m²
0
Group Name : Road Work, Total group amount (in Rs.) :2,148,887.19
Sr. SOR Item No. Item Description Quantity Unit Rate Amount
No.
Construction of Embankment with Material
Obtained from Roadway Cutting
Construction of embankment with approved
materials deposited at site from roadway
1 MORD 3.3 cutting and excavation from drain and 1125.000 Cubic Meter 56.78 63,877.50
foundation of other structures graded and
compacted to meet requirement of Tables
300.1 and 300.2 as per Technical Specification
Clause 301.5
3)WBM Grading 3
Providing, laying, spreading and compacting
stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand packing,
4.7(3)(A) rolling with smooth wheel roller 80-100 kN in
2 MORD stages to proper grade and camber, applying 81.000 Cubic Meter 5470.49 4,43,109.69
and brooming, stone screening to fill-up the
interstices of coarse aggregate, watering and
compacting to the required density Grading 3
as per Technical Specification Clause 405.
(A)By Manual Means
(ii)Providing and applying tack coat with
Bitumen VG-10 using bitumen distributor at the
5.2(ii) rate of 0.30 to 0.40 kg per sqm on the prepared Square
3 MORD dry and hungry bituminous surface cleaned 6000.000 Meters 17.53 1,05,180.00
with Hydraulic broom as per Technical
Specification Clause 503.
20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade/modified
bitumen) Binder
Providing, laying and rolling of open-graded
premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or emulsion to
required line, grade and level to serve as
5.9Case- Square
4 MORD I(I) wearing course on a previously prepared base, 6000.000 Meters 210.94 12,65,640.00
including mixing in a suitable plant, laying and
rolling with a three wheel 80-100 kN static roller
capacity, finished to required level and grades
to be followed by seal coat of either Type A or
Type B or Type C as per Technical
Specification Clause 508.
Case - I By Manual Means
(I)Bitumen (S-90)
Seal Coat
Providing and laying seal coat sealing the voids
5.12 A. in a bituminous surface laid to the specified
By levels, grade and cross fall using Type A, Type Square
5 MORD Manual B and Type C as per Technical Specification 6000.000 Meters 45.18 2,71,080.00
Case-III- Clause 510
Type c(I) A.By Manual Means
Case - III : Type C
(I)Bitumen (S-90)
Total Amount :2,148,887.19
Abstract Of Cost
Sign By: