Professional Documents
Culture Documents
Ministry of Irrigation
Department of Irrigation
Far Western Regional Irrigation Directorate
Irrigation Development Sub Division
Dadeldhura
4 Certified
a The drawings and measurements of the proposed work are based on the field verification.
The design and estimate of the proposed work is based on departmental norms and general engineering
b
principles in practice.
c The proposed estimate is prepared on the basis of approved rate and rate analysis norms.
d All numbers and arithmetical calculations carried out in this estimate are correct.
………… …………
Submitted by Checked & Forwarded by
(Sub-Engineer) (Sub Division Chief)
The submitted cost estimate, drawinggs are correct in accordance with the approved departmental norms
and follow the general engineering principles in practice, hence is recommended for approval.
………………. ………………..
(Engineer) (Senior Divisional Engineer)
6 Approved
For this work the drawings and amount of NRs…………………………... is approved.
……………………………
(Regional Director)
(FWRID)
Project Name:Bahirisen Irrigation Project
Location:Aalital-3 Dadeldhura
Distance(Km)
Metalled Terai 15 (Nearest Market= Dhangadthi
Metalled Hill 64
Gravel 15
Haulage 1.5
Location:Aalital-3 Dadeldhura
Transporation Cost [ By Truck ] By porter
Cost at Loading/Unloading
Cost at Site
S.No Material Unit Source Weight Metalled Road Terai Metalled Road Hill Earthern Road Foot Track Remarks
(NRs.)
(NRs.) Distance Rate Unit Amount Distance Rate Unit Amount Distance Rate Unit Amount Rate Unit Amount Distance Rate Unit Amount
1 Cement Mt. 16,500.00 1,000.00 15 0.016 /km/kg 235.50 64 0.024 /km/kg 1,536.0 15 0.0320 /km/kg 480.00 0.4200 /kg 420.00 1.5 1.969 /km/kg 2,953.12 22,124.62 /Mt
2 Sand cu.m 1,972.00 1,450.00 0 0.016 /km/kg 0.00 0 0.024 /km/kg 0.0 0 0.0320 /km/kg 0.00 0.3470 /kg 503.15 0 1.156 /km/kg 0.00 2,475.15 /cu.m
3 Boulder cu.m 1,684.00 2,400.00 0 0.00 0 0.0 0 0.00 0.00 0 0.000 0.00 1,684.00 /cu.m
4 Gravel cu.m 2,188.00 1,600.00 0 /km/kg 0.00 0 /km/kg 0.0 0 /km/kg 0.00 /kg 0.00 0 0.000 /km/kg 0.00 2,188.00 /cu.m
5 MS Rod Mt. 77,000.00 1,000.00 15 0.021 /km/kg 307.50 64 0.074 /km/kg 4,736.0 15 0.1220 /km/kg 1,830.00 0.4200 /kg 420.00 1.5 2.625 /km/kg 3,937.50 88,231.00 /Mt.
different size
6 Binding Wire kg 100.00 1.00 15 0.021 /km/kg 0.30 64 0.074 /km/kg 4.7 15 0.1220 /km/kg 1.83 0.4200 /kg 0.42 1.5 2.625 /km/kg 3.93 111.21 /kg
7 Nails kg 180.00 1.00 15 0.021 /km/kg 0.30 64 0.074 /km/kg 4.7 15 0.1220 /km/kg 1.83 0.4200 /kg 0.42 1.5 2.625 /km/kg 3.93 191.21 /kg
8 Local wood cu.m 32,992.80 0 0.00 0.0 0.00 0.00 0 0.000 0.00 32,992.80 /cu.m
9 G.I.Wire kg 92.00 1.00 15 0.021 /km/kg 0.30 64 0.074 /km/kg 4.7 15 0.1220 /km/kg 1.83 0.4200 /kg 0.42 1.5 2.625 /km/kg 3.93 103.21 /kg
10 MS Channel kg 105.00 1.00 15 0.021 /km/kg 0.30 64 0.074 /km/kg 4.7 15 0.1220 /km/kg 1.83 0.4200 /kg 0.42 1.5 2.625 /km/kg 3.93 116.21 /kg
11 Barbed wire kg 95.00 1.00 15 0.021 /km/kg 0.30 64 0.074 /km/kg 4.7 15 0.1220 /km/kg 1.83 0.4200 /kg 0.42 1.5 2.625 /km/kg 3.93 106.21 /kg
12 90mm Rm 442.99 1.72 15 0.021 /km/kg 0.52 64 0.074 /km/kg 8.1 15 0.122 /km/kg 3.14 0.3470 /kg 0.59 1.5 2.625 /km/kg 6.76 462.13 /Rm
6kg/cm2
HDPE pipe Rm
19 63 mm 151.19 0.59 15 0.021 /km/kg 0.18 64 0.074 /km/kg 2.8 15 0.122 /km/kg 1.07 0.3470 /kg 0.20 1.5 2.625 /km/kg 2.30 157.71 /Rm
4kg/cm2
HDPE pipe
GI PIPES
Medium duty
13 100 mm Dia Rm 1,384.00 12.720 15 0.021 /km/kg 3.91 64 0.074 /km/kg 60.2 15 0.122 /km/kg 23.27 0.3470 /kg 4.41 1.5 2.625 /km/kg 50.08 1,525.91 /Rm
GI Pipe
16 Rm 583.00 5.350 15 0.021 /km/kg 1.64 64 0.074 /km/kg 25.3 15 0.122 /km/kg 9.79 0.3470 /kg 1.85 1.5 2.625 /km/kg 21.06 642.67 /Rm
50 mm Dia GI
Pipe
18 Rm 147.00 1.290 15 0.021 /km/kg 0.39 64 0.074 /km/kg 6.1 15 0.122 /km/kg 2.36 0.3470 /kg 0.44 1.5 2.625 /km/kg 5.07 161.36 /Rm
15 mm Dia GI
Pipe
Location:Aalital-3 Dadeldhura
1 Sand m3 Unskl 3.45 100.00 0.40+((L-10)/10)*0.12 1.48 4.93 400.00 1972.00 3-1b & 22-1.1(a&b)
2 Boulder m3 Unskl 1.40 100.00 1.10+((L-10)/10)*0.19 2.81 4.21 400.00 1684.00 3-4 & 22-1.3 (a&b)
3 Gravel m3 Unskl 4.00 100.00 0.30+((L-10)/10)*0.13 1.47 5.47 400.00 2188.00 3-2b & 22-1.2(a&b)
1 Fell trees, cut up and dispose 5m away from the const. site(12-15cm) (Ref.No. 1.1) Unit/each
Cutting thin vegetation, grubing their roots and disposal 25m far from the const.site(dia.<=30cm &
2 (Ref.No. 1.3) Unit/m2
density>15nr/100m2)
Unskilled labour 0.04 No @ Rs 400.00 16.00
Contractor's Overhead and Profit @ 15% 2.40
Rate/m2 Rs 18.40
3 Excavation of soft soils including disposal (up to 10 m lead & 1.5 m lift). (Ref.No. 2.9) Unit/m3
Unskilled labour 1.00 No @ Rs 400.00 400.00
Tools and plant @ 3% 12.00
Sub total 412.00
Contractor's Overhead and Profit @ 15% 61.80
Rate/m3 Rs 473.80
Excavation for foundation, drain, pipeline etc. in boulder mixed soils, disposal(up to 10 m lead & 1.5 m
4 (Ref.No. 2.14) Unit/m3
lift).
Unskilled labour 1.59 No @ Rs 400.00 636.00
Tools and plant @ 3% 19.08
Sub total 655.08
Contractor's Overhead and Profit @ 15% 98.26
Rate/m3 Rs 753.34
5 Foundation excavation under water in boulder and gravel ) with disposal up to 10 m lead 6 m deep (Ref.No. 2.24.f) Unit/m3
excavation and 7.5 m lift
Unskilled labour 4.30 No @ Rs 400.00 1720.00
Tools and plant @3% 51.60
Sub total 1771.60
Earth Work in back filling with ordinary soil in 15 cm layers and hand compcation without sprinkling
6 (Ref.No. 2.25.b) Unit/m3
water (10m lead )
Unskilled labour 0.25 No @ Rs 400.00 100.00
Tools and plant @ 3% 3.00
Sub total 103.00
Contractor's Overhead and Profit @ 15% 15.45
Rate/m3 Rs 118.45
7 Rubble Masonry works including supply of hard stone blocks. Preparing cement mortar and (Ref.No. 6.1.b) Unit/m3
construction of wall up to 5m high (haulage distance up to 10 m). Cement mortar 1:4
Skilled labour 1.50 No @ Rs 600.00 900.00
Unskilled labour 5.00 No @ Rs 400.00 2000.00
Cement 0.159 M.t @Rs 22124.62 3517.81
Sand 0.45 m3 @Rs 2475.15 1113.81
Stone 1.10 m3 @Rs 1684.00 1852.40
Sub total 9384.02
Contractor's Overhead and Profit @ 15% 1407.60
Rate/m3 Rs 10791.62
Rubble Masonry works including supply of hard stone blocks & constrution of walls up to 5.0 m high
8 (Ref.No. 6.2.a) Unit/m3
(haulage 30.0 m) Dry wall.
Skilled labour 1.00 No @ Rs 600.00 600.00
Unskilled labour 2.00 No @ Rs 400.00 800.00
Stone 1.10 m3 @Rs 1684.00 1852.40
Sub total 3252.40
Contractor's Overhead and Profit @ 15% 487.86
Rate/m3 Rs 3740.26
Concreting (cement conc.) of foundations, vert. faces, walls including supply of materials and haulage
9 (Ref.No. 7.2.c) Unit/m3
(dist. up to 30 m). P.C.C. 1:3:6.
Skilled labour 1.00 No @ Rs 600.00 600.00
Unskilled labour 4.00 No @ Rs 400.00 1600.00
Cement 0.22 Mt. @Rs 22124.62 4867.41
Aggregates 0.89 m3 @Rs 2188.00 1947.32
10 cutting,bending,placing in position as shown in the drawing & binding by G.I. wire of (Ref.No. 7.5) Unit/mt
reinforcement steel bars for R.C.C works incl. haulage distance of 30 m
Skilled labour 12.00 No @ Rs 600.00 7200.00
Unskilled labour 12.00 No @ Rs 400.00 4800.00
Cement 0.00 Mt. @Rs 22124.62 0.00
MS Rods 1.05 mt @Rs 88231.00 92642.55
wires 10.000 kg @Rs 111.21 1112.10
Sub total 105754.65
Contractor's Overhead and Profit @ 15% 15863.19
Rate/mt Rs 121617.84
Concreting (cement conc.) of foundations, vert. faces, walls including supply of materials and haulage
11 (Ref.No. 7.2.d) Unit/m3
(dist. up to 30 m). P.C.C. 1:2:4.
Skilled labour 1.00 No @ Rs 600.00 600.00
Unskilled labour 4.00 No @ Rs 400.00 1600.00
Cement 0.32 Mt. @Rs 22124.62 7079.87
Aggregates 0.85 m3 @Rs 2188.00 1859.80
Coarse sand 0.445 m3 @Rs 2475.15 1101.44
Sub total 12241.11
Contractor's Overhead and Profit @ 15% 1836.16
Rate/m3 Rs 14077.27
Concreting (cement conc.) of super structure including supply of materials and haulage (dist. up to 30
12 m). P.C.C. 1:1.5:3. (Ref.No. 7.4.b) Unit/m3
Skilled labour 0.80 No @ Rs 600.00 480.00
Unskilled labour 7.00 No @ Rs 400.00 2800.00
Cement 0.40 Mt. @Rs 22124.62 8849.84
Aggregates 0.86 m3 @Rs 2188.00 1881.68
Coarse sand 0.425 m3 @Rs 2475.15 1051.93
Sub total 15063.45
Contractor's Overhead and Profit @ 15% 2259.51
Rate/m3 Rs 17322.96
Making wooden forms including supply and selection of mat. fixing, nailing according to drawings,
14 (Ref.No. 8.2.b) Unit/10m2
placing separators, dismantling forms and hauling up to 30 m distance.
12.5mm thick cement sand plastering works including supply and prepartion of materials in 1:4
15 (Ref.No. 12.1.c) Unit/100m2
cement-sand ratio.
Skilled labour 12.00 No @ Rs 600.00 7200.00
Unskilled labour 16.00 No @ Rs 400.00 6400.00
Cement 0.538 M.t @Rs 22124.62 11903.04
Sand 1.46 m3 @Rs 2475.15 3613.71
Sub total 29116.75
Contractor's Overhead and Profit @ 15% 4367.51
Total Rs 33484.26
Rate/m 2
Rs 334.84
17 Filling by stones in the foundation and levelling including haulage distance upto 30m (Ref.No. 6.5) Unit/each
Unskilled labour 1.50 No @ Rs 400.00 600.00
Stone 1.20 m3 @Rs 1684.00 2020.80
Sub total 2620.80
Contractor's Overhead and Profit @ 15% 393.12
Rate/m3 Rs 3013.92
18 Filling with ordinary soils in 15cm thick layers and hand compaction(Haulage distance 10m) (Ref.No. 2.25.b) Unit/m3
Making rectangular gabion box (3.0 x 1.5 x 0.75m.) with two way knot incl. wire cutting, netting etc.
19 (Ref.No. 16.10.b) Per. No
complete. (Mesh size 100 x 100mm. , mesh wire 10 SWG.)
21 125 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 480.00 720.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 600.00 1800.00
125mm dia. pipe 10Kg/cm2 50.00 Rm @Rs 1335.81 66790.70
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 78.31
Sub total 70041.51
Contractor's Overhead and Profit @ 15% 10506.23
Total 80547.74
Rate/Rm Rs 1610.95
22 125 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 480.00 720.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 600.00 1800.00
125mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 886.31 44315.70
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 78.31
Sub total 47566.51
Contractor's Overhead and Profit @ 15% 7134.98
Total 54701.49
Rate/Rm Rs 1094.02
23 125 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 480.00 720.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 600.00 1800.00
125mm dia. pipe 4Kg/cm2 50.00 Rm @Rs 616.08 30804.10
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 78.31
Sub total 34054.91
24 110 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 600.00 900.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 400.00 1200.00
110 mm dia. pipe 10Kg/cm2 50.00 Rm @Rs 1047.28 52363.90
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 67.77
Sub total 55184.17
Contractor's Overhead and Profit @ 15% 8277.63
Total 63461.80
Rate/Rm Rs 1269.23
25 110 mm dia.6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 710.00 1065.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 400.00 1200.00
110 mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 684.99 34249.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 71.91
Sub total 37238.91
Contractor's Overhead and Profit @ 15% 5585.84
Total 42824.75
Rate/Rm Rs 856.49
26 110 mm dia. 4kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 710.00 1065.00
Helper 1.50 No @ Rs 400.00 600.00
Labour 3.00 No @ Rs 400.00 1200.00
110 mm dia. pipe 4Kg/cm2 50.00 Rm @Rs 478.27 23913.30
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 71.91
Sub total 26902.71
Contractor's Overhead and Profit @ 15% 4035.41
Total 30938.12
Rate/Rm Rs 618.76
28 90 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 600.00 600.00
Helper 1.00 No @ Rs 400.00 400.00
Labour 2.00 No @ Rs 400.00 800.00
90 mm dia. pipe 6 Kg/cm2 50.00 Rm @Rs 462.13 23106.30
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 45.18
Sub total 24956.73
Contractor's Overhead and Profit @ 15% 3743.51
Total 28700.24
Rate/Rm Rs 574.00
29 90 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 400.00 400.00
Labour 2.00 No @ Rs 400.00 800.00
90 mm dia. pipe 4 Kg/cm2 50.00 Rm @Rs 328.62 16430.90
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 47.94
Sub total 18394.09
Contractor's Overhead and Profit @ 15% 2759.11
Total 21153.20
Rate/Rm Rs 423.06
31 75 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 400.00 400.00
Labour 2.00 No @ Rs 400.00 800.00
75 mm dia. pipe 6 Kg/cm2 50.00 Rm @Rs 320.54 16026.90
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 47.94
Sub total 17990.09
Contractor's Overhead and Profit @ 15% 2698.51
Total 20688.60
Rate/Rm Rs 413.77
32 75 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 400.00 400.00
Labour 2.00 No @ Rs 400.00 800.00
75 mm dia. pipe 4 Kg/cm2 50.00 Rm @Rs 227.69 11384.40
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 47.94
Sub total 13347.59
Contractor's Overhead and Profit @ 15% 2002.14
Total 15349.73
Rate/Rm Rs 306.99
34 63 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
35 63 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
37 50 mm dia. 6kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
38 40 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
40 32 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
41 32 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
43 20 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
49 100 mm dia. GI pipe(Medium duty) supplying and laying (Ref.No. 17.4-1.5) Per 30 Rm
50 125 mm dia. GI pipe(Medium duty) supplying and laying (Ref.No. 17.4-1.6) Per 30 Rm
56 100 mm dia. GI pipe(Heavy duty) supplying and laying (Ref.No. 17.4-1.5) Per 30 Rm
58 15 and 20 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
59 25 and 32 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
60 40,50 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
62 100 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
63 125 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
64 Barbed wire fencing work on RCC Posts (100 mm x 100 x 2.2m) @ 3m c/c (2 diagonals & 5 horizontals) (Ref.No. 24.7) Per 30 Rm
66 CGI sheet roofing works with supply of materials complete(Per 10 m2) Per No
Quantity and Cost Estimate of : Resorvoir Tank,Valve Box,Fittings and Barbed wire fencing
Size of the Tank
Length 8 Height 2
Width 8
Rate per unit Amount
S.No. Description of Works No. Length Breadth Height Quantity Remarks
(Rs.) (Rs.)
1 E/W excavation in Foundation in BMS soil
RVT
13 RVT Fittings
13.1 Inlet 4"size
a G.I. Elbow 4" 2.00 2.00 pcs 1269.42 2538.83
b G.I. Socket 4" 1.00 1.00 pcs 697.48 697.48
c G.I. Union 4" 1.00 1.00 pcs 1663.25 1663.25
d GI Pipe 4" (0.65+0.4+1.8) 2.85 2.85 mtr 1894.52 5399.38
13.2 Outlets 4" size For 1 nos outlets
a G.I. Elbow 4" 1.00 1.00 pcs 1269.42 1269.42
b G.I. Elbow -1/2" 2.00 2.00 pcs 37.79 75.57
c G.I. Union 4" 1.00 1.00 pcs 1663.27 1663.27
d G.I. Union -1/2" 1.00 1.00 pcs 92.13 92.13
e G.I. Nipple 4" 75mm long 2.00 2.00 pcs 626.23 1252.46
f GI Nipple -1/2" (75 mm long) 1.00 1.00 pcs 165.41 165.41
g G.I.Equal Tee-1/2" 1.00 1.00 pcs 55.49 55.49
h G.I.Reducing Tee4" *1/2 1.00 1.00 pcs 134.65 134.65
i Brass Union 4" 1.00 1.00 pcs 10504.02 10504.02
j Brass Gate Valve 4" 1.00 1.00 pcs 28134.64 28134.64
k G.I. Pipe4" (0.4 +1.6) 2.00 2.00 mtr 1894.52 3789.04
l G.I. Pipe -1/2" (0.5+0.6+1.2) 2.30 2.30 mtr 230.41 529.94
13.3 Washout
a G.I. Elbow-2" 1.00 1.00 pcs 266.95 266.95
b GI Nipple 2" 3.00 3.00 pcs 163.14 489.43
c Brass Gate Valve- 2" 1.00 1.00 pcs 4938.19 4938.19
d G.I PIPE 2" (0.25+1.35) 1.60 1.60 mtr 823.59 1317.74
e Brass union 2" 1.00 1.00 pcs 1495.31 1495.31
f HDPE 63mm/ 4kg-cm2 5.00 5.00 mtr 226.51 1132.55
13.4 Overflow
a G.I. Elbow-2" 2.00 2.00 pcs 266.95 533.89
b GI pipe-2" (0.25+1.3+0.35) 1.90 1.90 mtr 823.59 1564.82
c GI Nipple 2" 1.00 1.00 pcs 163.14 163.14
59568.05
Total of RVT,Fittings and Barbed wire
1297577.8
fencing =
Location:Aalital-3 Dadeldhura
Quantity and Cost Estimate of : Pump house
S.N. Description of works No Length Breath Height Quantity Rate per Unit (RsAmount (Rs.) Remarks
1) E/W excavation for foundation in GMS
TOTAL Rs.177,739.81
a Well pi()/4*(2.3+.3*2)^
1 6.61 11.00 72.650 2
72.65 m3 2037.340 148012.751
2 E/W in back filling @ 67 % of
excavation quantity
0.67 48.68 m3 115.000 5597.683
3 Stone soling work on the floor bed
a Well
1 1.01 12.00 12.150
6 Form work
2 7.23 12.00 173.410
500.390 86772.630
173.41 m2
7 Supplying and fitting, fixing required
perforated pipes, filters and all other
accessories as per instructions, all
complete.
L.S. 50000.00
Operation Cost
Delivery Discharge 6.11 lps
Working hour 12 hr
Water Delivered per annum 96342.48 m3
Electricity cost 3.125 per unit
Pump Power 25 Hp
Pump power 18.5 Kw
Pumping hour per annum @ 12 hr/day 4380 hour per annum
Electricity charge for a 18.5 KW pump @Rs. 3.125 per unit 253218.75 per annum
Total Electricity For 2 Pumps 506437.5 per annum
Cost of Pump operator 48000 per annum
Total operation cost 554,437.50 Per annum
Maintenance cost
(Assuming one servicing per year)
Pump pull out and reinstallation 10000
Replacing of bush and spare parts 10000
Service charge and unforseen expenditure 10000
Total 30,000.00 Per annum
Amount
S.No. Description of Works Remarks
(Rs.)
A. GOVERNMENT PART
1 Sump Well Structure Rs.688,829.48
2 Reservoir Tank and Barbed Wire Fencing Rs.1,297,577.76
Slicing of Work
Name of Project :- Bahirisen Irrigation Project
Name of Work :-Lift Irrigation Feasibility Study
SN Name of structure Unit Slice 1 (NCB Part) Slice 2 (WUA Slice 3 Slice 4 (Departmental)
Total Quantity Payable) (WUA Contribution)
Quantity Cost Quantity Cost Quantity Cost Quantity Cost
A Civil Works
1 (Sump Well) 1.00 No. 1.00 688,829.48
2 RVT,Valve Box, and Barbed Wire Fencing 1.00 No. 1.00 1,297,577.76
4 Orifice Intake with Covered Canal 1.00 No. 1.00 178,413.68 .
5 Field Outlet 3.00 No. 3.00 181,868.52
6 Pump House 1.00 No. 1.00 177,739.81
7 Pipelines 1.00 No. 1.00 5,597,348.00 618.00 298237.56
8 Pumps and accessories with Transportation and Installation 2.00 No. 2.00 491,340.00
9 Electric Lines 1.00 No. 1.00 1,284,128.75
A Civil Works
1 (Sump Well) No. 1.00 688,829.48
2 RVT,Valve Box, and Barbed Wire Fencing No. 1.00 1,297,577.76
3 Orifice Intake with Covered Canal No. 1.00 178,413.68
4 Field Outlet No. 3.00 181,868.52
5 Pump House No. 1.00 177,739.81
6 Pipelines No. 1.00 5,895,585.56
7 Pumps and accessories with Transportation and Installation No. 1.00 491,340.00
8 Electric Lines No. 1.00 1,284,128.75
Sub Total (A) 10,195,483.57