SUB ESTIMATE

#REF!
Name of the work: Replacement of filter media in Slow sand filter of size 10.00M dia
Est.Cost Rs

S.No Description Measurements Qty


Nos L B D
Supply of the SS Filter media of Effective size 0.2-0.3mm Fine

sand including washing sieving placing in position ect complete.


filter1 1 0.785 10.00 10.00 0.50 39.25
filter2 1 0.785 10.00 10.00 0.50 39.25
78.50 cum
2 unforseen items of work

Executive Engineer Deputy Executive Engineer Asst. Engineer


RWS&S Div Ongole RWS&S SD Martur R.W.S. Yeddanapudi
Est.Cost Rs 1.37 lakhs

Rate Amount

1735.40 1.00 cum 136229.00


771.00
Total 137000.00

Asst. Engineer
R.W.S. Yeddanapudi
DATA SHEET
Datas-SSR -2011-2012
1 Supply of the SS Filter media of size 16-23 mm metal with
specific gravity not bleow than 2.5, including washing
sieving placing in position ect complete.

1 cum 16-23 mm metal Rs. 1396.49 cum 1396.49


1 cum Labour charges for fiRs. 45.00 cum 45.00
Sundries 0.01
Total rate per cum 1441.50

2 Supply of the SS Filter media of size 4-5.6 mm metal with


specific gravity not bleow than 2.5, including washing
sieving placing in position ect complete.

1 cum 4-5.6 mm metal Rs. 876.49 cum 876.49


1 cum Labour charges for fiRs. 45.00 cum 45.00
Sundries 0.01
Total rate per cum 921.50
3 Supply of the SS Filter media of Effective size 0.7-1.40mm
coarse sand including washing sieving placing in position ect
complete.

1 cum 0.7-1.40 mm coarse sRs. 807.90 cum 807.90


1 cum Labour charges for fiRs. 45.00 cum 45.00
Sundries 0
Total rate per cum 852.90

4 Supply of the SS Filter media of Effective size 0.2-0.3mm


Fine sand including washing sieving placing in position ect
complete.

1.7 cum 0.2-0.3mm fine sand Rs. 425.00 cum 722.50


1 Nos Filling charges (manuRs. 45.00 cum 45.00
1 cum 0.2-0.3mm fine sand Rs. 382.90 cum 382.90
Screening Charges
2 Nos Man mazdoor Rs. 215.00 cum 430.00
1 cum Hire charges Rs. 20.00 cum 20.00
3 liters Cost of diesel Rs. 45.00 liters 135.00
Sundries 0
Total rate per cum 1735.40
.Exe.Engin Deputy .Exe.Engineer Assistant Engineer
eer

R.W.S.
Divn R.W.S. Sub-Divn .Martur R.W.S. Yeddanapudi
.Ongole
Leads statement
Name of the work :--- AUGMENTATION OF P.W.S.SCHEME TO
PUNURU VILLAGE OF EDDANAPUDI MANDAL IN PRAKASAM DISTRICT

Conveyanc
lead after
Name of the e-
Sl.No Description of material Quantity lead (km) deducting 1 Initial cost
Quarry Excluding
km
14%

1 40mm size HBG (SS5) Chimmiribanda 1 Cum 10.20 9.20 745.00 89.04
2 20mm size HBG metal Martur 1 Cum 11.60 10.60 1175.00 105.70
3 CR Stone Ramathirdham 1 Cum 65.00 64.00 321.00 642.75
4 RR Stone Ramathirdham 1 Cum 20.00 19.00 205.00 304.75
5 C R Stone Chimmiribanda 1 Cum 10.20 9.20 321.00 89.04
6 R R Stone Chimmiribanda 1 Cum 10.20 9.20 225.00 89.04
7 Sand for mortar ipurupalem 1 Cum 39.00 38.00 325.00 319.47
8 Sand for filling Martur Vagu 1 Cum 11.00 10.00 250.00 97.37
9 Sand for filtermedia Kadavakuduru 1 Cum 35.00 34.00 425.00 291.75
10 Bricks Addanki 1000 No's 43.00 42.00 3100.00 464.16
11 Cement 1.0 MT 0.00 5300
12 Steel 1.0 MT 0.00 44000
13 Steel-I Beams -1.00 36500
14 6 mm size HBG metal Martur 1 Cum 11.60 10.60 655.00 105.70
15 12mm size HBG metal Martur 1 Cum 11.60 10.60 980.00 105.70
16 10mm size HBG metal Martur 1 Cum 11.60 10.60 820.00 105.70
17 uncoursed rubble stone Ramathirdham 20.00 230 267.32
18 Gravel Annangi 10.00 72.5 169.47
19 Shabad slabs Ongole 26.5 160 94.3
This is to certify that the leads are correct to the best of my knowledge

Executive Engineer Dy Executive Engineer


RWS&S Divison, Ongole RWS&S Sub-division,Martur
RAKASAM DISTRICT

diff. in
seignorage
Loading Unloading (G.O.Ms.N Total
o. 198, dt:
`13.8.2009)

77.19 38.60 0.00 949.83


77.19 38.60 0.00 1396.49
0.00 963.75
0.00 509.75
77.19 38.60 525.83
77.19 38.60 429.83
67.11 24.04 0.00 735.62
67.11 24.04 0.00 438.52
67.11 24.04 0.00 807.90
131.49 131.49 38.50 3827.14
5300.00
44000.00
36500.00
77.19 38.60 0.00 876.49
77.19 38.60 0.00 1201.49
77.19 38.60 0.00 1041.49
0.00 497.32
0.00 241.97
254.30

Dy Executive Engineer Asst Engineer


WS&S Sub-division,Martur RWS Yeddanapudi
Gannavaram VILLAGE OF EDDANAPUDI
Name of the Work : MANDAL IN PRAKASAM DISTRICT

Estimate Cost Rs 35,00,000 /--

Grant : NRDWP ( Critical Gaps)

Name of the Mandal


Sub- : Eddanapudi
Division : Martur

Name of the
Division : Ongole
Slow Sand Filter

Free Board 0.25

7.50
1.00
Supernatant Water

0.10
GL 100.000 100
0.5
2.80 Fine Sand
1.05
Depth of foundation Cut-off level
2.000
Coarse Sand 0.10 1.55
4.0 - 5.6 metal 0.15
16 - 23 metal 0.30
Drainage Blocks 0.20
Raft 0.15

0.30
Foundation Concrete
98.000

8.50
8.80

Note : Not to Scale


All Dimensions in Meters
100.000 Media Top Level

98.000 Relative Bed level