M/S M. B.

PATIL CONSTRUCTION
Paud Road

RCC Strom water chember Size- 0.900m x 0.900m x 1.50m (Thickness- 0.200m)

Rate Analysis (only Labour Charges)

1 ) Shuttering Quantity

Sr. No. Discription Unit No.s Length Depth Width Total Qty. Rate Total Amount

1 Shuttering work Sqm 4 0.90 1.50 5.40 100 540

2 Shuttering work Sqm 4 1.30 1.50 7.80 100 780

Total Amount - 1320

2 ) Concrete Quantity

Sr. No. Discription Unit No.s Length Ht./Depth Width Total Qty. Rate Total Amount

1 Cocrete work -M20 Cum 2 1.30 1.50 0.20 0.78 125 97.5

2 Cocrete work -M20 Cum 2 0.90 1.50 0.20 0.54 125 67.5

3 Cocrete PCC work Cum 1 1.50 1.50 0.10 0.23 125 28.125

4 Deduction for Pipe Cum -2 0.64 0.20 -0.25 125 -31.808625618

Total Labour Amount - 161.316374382

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement below 12mm dia.)
Total Qty. Total Qty. in
Sr. No. Discription Unit No.s Length Ht./Depth Rate Total Amount
inSqm. Kg

1 Steel Binding work (Labour charges 2600Rs/Mtone) Sqm 4 1.30 1.50 7.80 205.61 3400 699.0672

Total Labour Amount - 699.0672

Total Amount of above Detailed - 2180.4 Rs

Say for 1.5M Depth 2,180 Rs


M/S M. B. PATIL CONSTRUCTION
Paud Road

RCC Strom water chember Size- 0.900m x 0.900m x 2.0m (Thickness- 0.200m)

Rate Analysis (only Labour Charges)

1 ) Shuttering Quantity

Sr. No. Discription Unit No.s Length Depth Width Total Qty. Rate Total Amount

1 Shuttering work Sqm 4 0.90 2.00 7.20 100 720

2 Shuttering work Sqm 4 1.30 2.00 10.40 100 1040

Total Amount - 1760

2 ) Concrete Quantity

Sr. No. Discription Unit No.s Length Ht./Depth Width Total Qty. Rate Total Amount

1 Cocrete work -M20 Cum 2 1.30 2.00 0.20 1.04 125 130

2 Cocrete work -M20 Cum 2 0.90 2.00 0.20 0.72 125 90

3 Cocrete PCC work Cum 1 1.50 2.00 0.10 0.30 125 37.5

4 Deduction for Pipe Cum -2 0.64 0.20 -0.25 125 -31.808625618

Total Labour Amount - 225.691374382

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement below 12mm dia.)
Total Qty. Total Qty. in
Sr. No. Discription Unit No.s Length Ht./Depth Rate Total Amount
inSqm. Kg

1 Steel Binding work (Labour charges 2600Rs/Mtone) Sqm 4 1.30 2.00 10.40 274.14 3400 932.0896

Total Labour Amount - 932.0896

Total Amount of above Detailed - 2917.8 Rs

Say for 1.5M Depth 2,920 Rs


M/S M. B. PATIL CONSTRUCTION
Paud Road

RCC Strom water chember Size- 0.900m x 0.900m x 2.50m (Thickness- 0.200m)

Rate Analysis (only Labour Charges)

1 ) Shuttering Quantity

Sr. No. Discription Unit No.s Length Depth Width Total Qty. Rate Total Amount

1 Shuttering work Sqm 4 0.90 2.50 9.00 100 900

2 Shuttering work Sqm 4 1.30 2.50 13.00 100 1300

Total Amount - 2200

2 ) Concrete Quantity

Sr. No. Discription Unit No.s Length Ht./Depth Width Total Qty. Rate Total Amount

1 Cocrete work -M20 Cum 2 1.30 2.50 0.20 1.30 125 162.5

2 Cocrete work -M20 Cum 2 0.90 2.50 0.20 0.90 125 112.5

3 Cocrete PCC work (M10) Cum 1 1.50 2.50 0.10 0.38 125 46.875

4 Deduction for Pipe Cum -2 0.64 0.20 -0.25 125 -31.8086256176

Total Labour Amount - 290.066374382

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement below 12mm dia.)
Total Qty. Total Qty. in
Sr. No. Discription Unit No.s Length Ht./Depth Rate Total Amount
inSqm. Kg

1 Steel Binding work Sqm 4 1.30 2.50 13.00 342.68 3400 1165.112

Total Labour Amount - 1165.112

Total Amount of above Detailed - 3655.18 Rs

Say for 1.5M Depth 3,660 Rs


M/S M. B. PATIL CONSTRUCTION
Paud Road

RCC Strom water chember Size- 0.900m x 0.600m x 1.50m (Thickness- 0.200m)

Rate Analysis (only Labour Charges)

1 ) Shuttering Quantity

Sr. No. Discription Unit No.s Length Depth Width Total Qty. Rate Total Amount Remark

1 Shuttering work -(Internal) Sqm 2 0.60 1.50 1.80 100 180 Shorter Span

2 Shuttering work -(Internal) Sqm 2 0.90 1.50 2.70 100 270 Longer Span

3 Shuttering work-(External) Sqm 2 1.00 1.50 3.00 100 300 Shorter Span

4 Shuttering work-(External) Sqm 2 1.30 1.50 3.90 100 390 Longer Span

Total Amount - 1140

2 ) Concrete Quantity

Sr. No. Discription Unit No.s Length Ht./Depth Width Total Qty. Rate Total Amount Remark

1 Cocrete work -M20 -(Longar Span) Cum 2 1.30 1.50 0.20 0.78 125 97.5 Longer Span

2 Cocrete work -M20-(Shorter Span) Cum 2 0.60 1.50 0.20 0.36 125 45 Shorter Span

3 Cocrete PCC work Cum 1 1.50 1.20 0.10 0.18 125 22.5

4 Deduction for Pipe Cum -2 0.28 0.20 -0.11 125 -14.1371669412

Total Labour Amount - 150.862833059

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement below 12mm dia.)

Sr. No. Discription Unit No.s Length Ht./Depth Total Qty. Total Qty. in Rate Total Amount Remark
inSqm. Kg

Steel Binding work


1
(Labour charges 2600Rs/Mtone)
Sqm 2 1.30 1.50 3.90 102.80 3400 349.5336 Longer Span

Steel Binding work


2
(Labour charges 2600Rs/Mtone)
Sqm 2 1.00 1.50 3.00 79.08 3400 268.872 Shorter Span

Total Labour Amount - 618.4056

Total Amount of above Detailed - 1909.3 Rs

Say for 1.5M Depth 1,910 Rs


M/S M. B. PATIL CONSTRUCTIO
Paud Road

RCC Strom water chember Size- 0.900m x 0.600m x 2.00m

Rate Analysis (only Labour Charges

1 ) Shuttering Quantity
Sr. No. Discription Unit No.s Length Depth

1 Shuttering work -(Internal) Sqm 2 0.60 2.00

2 Shuttering work -(Internal) Sqm 2 0.90 2.00

3 Shuttering work-(External) Sqm 2 1.00 2.00

4 Shuttering work-(External) Sqm 2 1.30 2.00

2 ) Concrete Quantity

Sr. No. Discription Unit No.s Length Ht./Depth

1 Cocrete work -M20 -(Longar Span) Cum 2 1.30 2.00

2 Cocrete work -M20-(Shorter Span) Cum 2 0.60 2.00

3 Cocrete PCC work Cum 1 1.50 1.20

4 Deduction for Pipe Cum -2 0.28


Total La

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement be

Sr. No. Discription Unit No.s Length Ht./Depth

1 Steel Cutting & Binding work Sqm 2 1.30 2.00


(Labour charges 3400Rs/Mtone)

2 Steel Cutting & Binding work Sqm 2 1.00 2.00


(Labour charges 3400Rs/Mtone)

Total La

Total Amount of above Detailed

Say for 1.5M Depth

Prepared By Checked BY
L CONSTRUCTION
ud Road

0m x 0.600m x 2.00m (Thickness- 0.200m)

only Labour Charges)

Width Total Qty. Rate Total Amount Remark

2.40 100 240 Shorter Span

3.60 100 360 Longer Span

4.00 100 400 Shorter Span

5.20 100 520 Longer Span

Total Amount - 1520.00

Width Total Qty. Rate Total Amount Remark

0.20 1.04 125 130 Longer Span

0.20 0.48 125 60 Shorter Span

0.10 0.18 125 22.5

0.20 -0.11 125 -14.137


Total Labour Amount - 198.36

taining reinforcement below 12mm dia.)


Total Qty. Total Qty. in
Rate Total Amount Remark
inSqm. Kg

5.20 137.07 3400 466.0448 Longer Span

4.00 105.44 3400 358.496 Shorter Span

Total Labour Amount - 824.54

Amount of above Detailed - 2542.90 Rs

Say for 1.5M Depth 2,540 Rs

Approved by (Project Manager)


M/S M. B. PATIL CONSTRUCTIO
Paud Road

RCC Strom water chember Size- 0.900m x 0.600m x 2.50m (

Rate Analysis (only Labour Charges)

1 ) Shuttering Quantity
Sr. No. Discription Unit No.s Length Depth

1 Shuttering work -(Internal) Sqm 2 0.60 2.50

2 Shuttering work -(Internal) Sqm 2 0.90 2.50

3 Shuttering work-(External) Sqm 2 1.00 2.50

4 Shuttering work-(External) Sqm 2 1.30 2.50

2 ) Concrete Quantity
Sr. No. Discription Unit No.s Length Ht./Depth

1 Cocrete work -M20 Cum 2 1.30 2.50

2 Cocrete work -M20 Cum 2 0.60 2.50

3 Cocrete PCC work Cum 1 1.50 1.20

4 Deduction for Pipe Cum -2 0.28

Total Labo

3 ) Steel binding & Cutting (26.36Kg/Sqm) (Structure containing reinforcement be


Sr. No. Discription Unit No.s Length Ht./Depth

Steel Cutting & Binding work


1 (Labour charges 3400Rs/Mtone) Sqm 2 1.30 2.50

Steel Cutting & Binding work


2 Sqm 2 1.00 2.50
(Labour charges 3400Rs/Mtone)

Total Labo

Total Amount of above Detailed

Say for 1.5M Depth

Prepared By Checked BY
L CONSTRUCTION
ud Road

0m x 0.600m x 2.50m (Thickness- 0.200m)

nly Labour Charges)

Width Total Qty. Rate Total Amount Remark

3.00 100 300 Shorter Span

4.50 100 450 Longer Span

5.00 100 500 Shorter Span

6.50 100 650 Longer Span

Total Amount - 1900.00

Width Total Qty. Rate Total Amount Remark

0.20 1.30 125 162.5 Longer Span

0.20 0.60 125 75 Shorter Span

0.10 0.18 125 22.5

0.20 -0.11 125 -14.137

Total Labour Amount - 245.86

taining reinforcement below 12mm dia.)


Total Qty. Total Qty.
inSqm. in Kg Rate Total Amount Remark

6.50 171.34 3400 582.556 Longer Span

5.00 131.80 3400 448.12 Shorter Span

Total Labour Amount - 1030.68

mount of above Detailed - 3176.54 Rs

Say for 1.5M Depth 3,180 Rs

Approved by (Project Manager)