Estimate For Construction of Fountain Tank
AS Per Urban Development ISSR W.E.F. 02/08/2021
S.NO. SOR ITEM
Description of Item unit Measurements Quantity Rate Amount
NO.
No. L B H
1 2 3 4 5 6 7 8 9 10 11
1 V-2,2.6 Earth work in excavation for
foundation, trenches for pipes / cables
or drains etc. by mechanical means /
manual means
(exceeding 30cm in depth.) including
ramming of bottom, dressing of sides,
disposal of excavated earth including of
all
2.6.1 lift
All and lead
kinds of upto
soil 50m. Disposed earth
Longer side 2 3.3 0.95 1.05 6.5835
Shorter side 2 1.4 0.95 1.05 2.793
CUM
Total 9.3765 151.00 1415.85
16 V-2,11.45.1.1 Graniteworkgangsawcut(polishedandma
chinecut)ofthickness18mm
forwalllining(veneerwork),backingfilled
withagroutofaverage12mm
thickincementmortar1:3(1cement:3sand
)includingpointingwith
whitecementmortar1:2(1whitecement:2
marbledust)withan
admixtureofpigmenttomatchthemarbles
hade:(Tobesecuredtothe
backing by means of cramps, which
shall be paid for separately).
At top of Brickwork
Long wall 2 3.3 0.225 1.485
Short wall 2 2.9 0.225 1.305
Around Pedestal
Longer side 2 1.0 0.225 0.45
Shorter side 2 0.6 0.225 0.27
SQM
Total 3.5 2084.00 7314.84