Name of Road:-Constuction of BT Road Begun Katunda Road to Jhopadiya via Sukhpura Km 0/0 to 2/300
HUMP PIPE CULVERT (2 x 1000 mm dia) 1 Nos
At Ch. 1/600 = 1 Nos
Iten Length
S.No Description of Item No. Width (m) Height Quantity Rate Unit Amount
No. (m)
1 B- Earthwork in excavation for
13.1.3. foundation of structure
2 complete with all lift,
dewatering, shoring and shuttering
etc. including refilling of trenches
in 250 mm layer, ramming, watering
and disposal of surplus soil within
a lead of 1000 meters, as per
drawing and technical Earth in
excavation for foundation of
specification. [MoRTH
Specification : Clause 304]. In
Ordinary/Soft rock (not requiring
blasting) [MoRTH Specification :
Clause 301] BY MECHANICAL
MEANS Wall 1 10.05 1.45 1.05 15.3 Cum
Wall 1 10.50 1.45 1.05 15.99 Cum
Hoda for pipe 1 4.68 4.00 1.50 28.08 Cum
59.37 Cum 99.00 Per Cum 5878.00
2 R- Providing & laying mechanically
8.1.2.2 mixed and vibrated Cement Concrete
in foundation upto a depth of 1.5mtr,
below ground level and 1.5mtr. above
ground/bed level. [MoRTH
Specification : Clause 1000/1700]. (b)
Cement concrete 1:3:6 mix with
stone aggregate 40 mm crusher broken.
Iten Length
S.No Description of Item No. Width (m) Height Quantity Rate Unit Amount
No. (m)
Wall 1 10.05 1.35 0.15 2.04 Cum
Wall 1 10.50 1.35 0.15 2.13 Cum
Haunching 1 ( 6.30 + 5.48 )/2 4.00 1.23 28.98 Cum
Bed 1 ( 5.48 + 5.38 )/2 4.00 0.15 3.26 Cum
Deduction of pipe 2 ( 6.30 + 5.48 )/2 1.23 x 1.23 3.14/4 -13.99 Cum
22.42 Cum 2818.00 Per Cum 63180.00
1 Nos. 358664.00