Requirment of Material and Labor

S.No Description Cement Sand Crush Bricks Unskilled


Unit Qty Steel (Ton) Skilled Labor(No)
(Bags) (M3) (M3) (No.) Labor(No)
A RCC/PCC V dry=1.54x V wet
1 P.C.C(1:4:8) M3 100.00 335.00 47.400 94.700

2 P.C.C(1:3:6) M3 100.00 435.00 46.200 92.400

3 P.C.C/R.C.C(1:2:4) M3 100.00 621.50 44.00 88.00

4 P.C.C/R.C.C(1:1.5:3) M3 100.00 791.00 42.00 84.00

5 P.C.CR.C.C(1:1:2) M3 100.00 1087.00 38.500 77.000

6 Reinfr.Steel (Def.bars) in RCCSlab/Lintels(1%) M3 100.00 7.85

1Cft Cantain 20% Wet Vol of Mortor(Vdry=1.54xVol wet)


B Burnt Brick(CSM)
and Volume of One Brick=0.0623Cft=0.00179M3(Actual)&0.07031Cft=0.00199M3(Nominal)
7 Brick Cement Mortar(1:6) M3 100.00 121.50 25.70 47700

8 Brick Cement Mortar(1:5) M3 100.00 141.20 25.00 47700

9 Brick Cement Mortar(1:4) M3 100.00 169.51 24.00 47700

10 Brick Cement Mortar(1:3) M3 100.00 211.86 22.500 47700

C Damp Proof Course(DPC) AreaxThickness gives Volume and Vdry =1.54V wet

11 D.P.C. 1:2:4 (2" thick) M2 1.00 0.32 0.02 0.05

12 D.P.C. 1:1.5:3( 1" thick/2.5cm) M2 1.00 0.20 0.01 0.02

D Plastering(Cement Sand) AreaxThickness gives Volume and Vdry =1.20x1.30V wet

13 Cement plaster (1:6) 1/2" thick(12mm) M2 100.00 7.80 1.6700

14 Cement plaster(1:5)1/2" thick(12mm) M2 100.00 9.18 1.6250

15 Cement plaster(1:4)1/2" thick (12mm) M2 100.00 11.00 1.5600

16 Cement plaster(1:3)1/2" thick(12mm) M2 100.00 13.77 1.4600

17 Cement plaster(1:2)1/2" thick(12mm) M2 100.00 18.00 1.30

18 Cement plaster (1:6) 3/4" thick(20mm) M2 100.00 12.00 2.600

19 Cement plaster(1:5)3/4" thick(20mm) M2 100.00 14.00 2.500

20 Cement plaster(1:4)3/4" thick(20mm). M2 100.00 17.00 2.400

21 Cement plaster(1:3)1/2" thick(20mm) M2 100.00 22.00 2.300

22 Cement plaster(1:2)3/4" thick(20mm) M2 100.00 28.00 2.000

23 Ceiling plaster(1:3)1/2" thick(12mm) M2 100.00 13.00 1.350

24 Ceiling plaster(1:4)1/2" thick(12mm) M2 100.00 10.00 1.440

25 Ceiling plaster(1:3)1/4" thick(6mm) M2 100.00 7.000 0.7500

26 Ceiling plaster(1:4)1/4" thick(6mm) M2 100.00 5.600 0.800

E Flooring AreaxThickness gives Volume and Vdry =1.54V wet

27 2'(5cm)Thick PCC Floor (1:2:4) M2 1.00

28 2'(5cm)Thick PCC Floor (1:2:4) M2 1.00

29 Brick Tiles(10"x5"x1.25") M2 1.00

F Pointing

30 Cement pointing (1:3) M2 100.00 4.65 0.490

31 Cement pointing (1:2) M2 100.00 6.00 0.400