EARTHWORKS AT THE NTOTROSO RESETTLEMENT SITE.

RATE AMOUNT
ITEM DESCRIPTION QTY UNIT
(GHC) (GHC)
Earthworks
Remove topsoil and stockpile as directed 1413.13 m² 1.39 1,964.25

Grade and compact formation to required profile and


677.3 m² 3.48 2,357.00
level
Provide and place approved sub-base material 250mm
186.9 m³ 37.53 7,014.36
thick, spread and compact to thickness as directed
Extra over items R114.1 for haulage of gravel material
1121.4 m³km 1.49 1,670.89
in excess of 1km but not more than 20km

Provide and install 12mm thick plate (12.00X1500 X


3 nr 936.00 2,808.00
6000mm) on existing drains
Sub-Total 15,814.50

Preliminaries 3,953.62

Grand Total 19,768.12

CLAIMS 1 PROFCON LTD
 CONSTRUCTION OF  SHED AND SECURITY FENCE AT THE NTOTROSO RESETTLEMENT SITE.

RATE AMOUNT
ITEM DESCRIPTION QTY UNIT
(GHC) (GHC)
A TEMPORAL SHED

2
1 Trim and compact ground surface to receive concrete 20.35 m 4.87 99.10
3
2 Place concrete grade 25/20 (1:2:4) in ground slab 3.05 m 240.47 733.43
3 Formwork to edges of slab 1.84 m2 13.90 25.58
Sub-total 858.11
CONCRETE PEDESTAL
3
4 Excavate pit to receive plinth 1.2 m 6.26 7.51
3
5 Place concrete grade 25/20 (1:2:4) in plinth 2.03 m 240.47 488.15
6 Formwork to sides of plinth 8.1 m2 16.68 135.11
Sub-total 630.77

METALWORKS
75mm dia. Galvanized steel pipe post welded to 250 x
7 250 x 10mm thick base plate and 150 x 150 x 8mm thick 6 No 295.00 1,770.00
U-shape rafter cap
8 Supply and install M8 bolts 12 No 9.30 111.60
9 Supply and install HD-A-M16-400 anchor bolts 24 No 11.15 267.60
10 50 x 50 x 6mm thick angle cleats 18 No 24.39 439.02
Sub-total 2,588.22

ROOFING
0.35mm Corrugated aluminium roofing sheets fixed with
two corrugations side laps and 150mm end laps fixed to
11 29.8 m2 27.80 828.44
hardwood purlins (m/s) with aluminium drive screws
and washers
Sub-total 828.44

CARPENTRY
Sawn treated hardwood;
12 50 x 150mm rafters 14.7 m 10.50 154.35
13 50 x 100mm purlins 36.6 m 7.56 276.70
14 25 x 300 fascia 22 m 7.58 166.76
Sub-total 597.81
Summary for TEMPORAL SHED 5,503.35

CHAINWIRE MESH SECURITY FENCE


Transport fencing materials to site
Collect and transport fencing materials from Akyem
1 Lump 695.00 695.00
workyard to Ntotroso Resettlement site

Chain link fencing complete


Install chain-link fencing with 2in dia. Galvanised pipe as
fence post spaced with an interval of 15ft in pit
foundation 30" deep and strung with 2 layers of barb 293.5 m 12.91 3,789.09
wire at top part, height of fence 6ft as per the drawings.
Materials such as post , strands, stays , chainlink, barb
wire are being provided by NGGL

Main Gate Complete


Provide and install 2No 10ft metal gate with chain link
and barbed wire as per fencing. Frame of gate is 2in
dia. Galvanized steel pipe, welded and braced. Provide
galvanised drop bolt at west leaf and sliding lock at east
leaf. The gate supports are 4in dia. galvanised steel 2 nr 450.00 900.00
posts; 5ft deep hole and 12in concrete all round post for
full depth of hole. Materials such as chainlink,
Galvanised posts and barb wire are being provided by
NGGL
Sub-Total 5,384.09

SUMMARY
TEMPORAL SHED 5,503.35

CHAINWIRE MESH SECURITY FENCE 5,384.09

Total 10,887.44

Preliminaries 2,721.86

Grand Total 13,609.30

CLAIMS 1 PROFCON LTD
CLAIMS ‐ REMEDIAL EARTHWORKS AT NTOTROSO RESETTLEMENT SITE

ITEM Description Quantity Unit Rate (GH¢) Amount (GH¢)


Dayworks
1 Excavator          4.00 hrs               292.64               1,170.54
2 Trucks        34.00 hrs               163.47               5,558.01
3 Payloader          8.00 hrs               214.22               1,713.77
4 Dozer          8.00 hrs               336.42               2,691.36
5 Roller          8.00 hrs               163.47               1,307.77
6 Grader          4.00 hrs               272.34               1,089.34

Total             13,530.79

Discount               2,265.00

Agreed Negotiated Price             11,265.79

PROFCON LTD 1