S.N RES sor ITEMS NO. L B D QTY.

UNIT Rate Amount


O.

Providing and laying vitrified floor tiles in


different sizes with water absorption less
than 0.08% and confirming to IS:15622 of
approved make in all colours and shades laid
2556

on 20mm thick cement mortar 1:4 (1cement :


4sand) including grouting the joints with
white cement and matching pigments etc.,
complete.

Size of tile 1000 X 1000 10-12mm 1 6.25 3.8 23.75


1 2.3 2.8 6.44
1 3.6 2.8 10.08
40.27 sqm 1458 58713.66
2557

fixing on wall/skirting. 1 33.3 0.1 3.33


1 6.8 0.9 6.12
49.72 sqm 291.6 14498.35

Removing old plaster or edges, cleaning of


1422

joints and floor for new work and disposal of 40.27 sqm 21.1 849.697
unserviceable materials within 50m lead

6mm cement plaster to Ceiling. (a) In


1011

Cement mortar 1:3 (1cement, 3sand) 40.27 sqm 134.2 5404.234

Providing and laying water proofing


treatment on roofs of slabs by applying
cement slurry mixed with water proofing
cement compound consisting of applying (a)
after surface preparation, first layer of slurry
of cement @ 0.488 kg/sqm mixed with water
proofing cement compound @ 0.253 kg/sqm.
b) laying second layer of Fibre glass cloth
when the first layer is still green.Overlaps of
joints of fibre cloth should not be less than 10
25-134

cm. (c) third layer of 1.5 mm thickness


consisting of slurry of cement @ 1.289 1 6.25 6.8 42.5 sqm 186.3 7917.75
kg/sqm mixed with water proofing cement
compound @ 0.670 kg/sqm and sand @
1.289 kg/sqm. This will be allowed to air cure
for 4 hours followed by water curing for 48
hours. The entire treatment will be taken upto
30cm on parapet wall and tucked into groove
in parapet all around.

Steel work welded in built up sections,


framed work, including cutting hoisting fixing
in position in gratings, frames, guard bars,
902

ladders, railing, brackets and similar works &


trusses and trussed purlins up to 25m span
and 15 m over all height

door 2 30 60 Kg 77.8 4668

Distempering with dry distemper of approved


brand and manufacture (two coats) and of
required shade on undecorated wall surfaces
to give an even shade, over and including
priming coat of whiting after thoroughly
1320

brushing the surface free from mortar 1 43.1 3 129.3


dropping and other foreign matter including
preparing the surface even and sand
papered smooth

1 28.1 3.6 101.16


230.46 sqm 50.7 11684.32
electrification LS 15000
118736
118736
Citizen Information Board 1500
Lab test 1500
Gran Total 121736
say (In lakh) 1.22
S.N RES sor ITEMS NO. L B D QTY. UNIT Rate Amount
O.

Providing and laying vitrified floor tiles in


different sizes with water absorption less
than 0.08% and confirming to IS:15622 of
approved make in all colours and shades laid
2556

on 20mm thick cement mortar 1:4 (1cement : 1 6.9 4 27.6


4sand) including grouting the joints with
white cement and matching pigments etc.,
complete.

Size of tile 1000 X 1000 10-12mm 1 3.6 3.7 13.32


1 3.1 3.2 9.92
50.84 sqm 1458 74124.72
2557

fixing on wall/skirting. 1 31.4 0.1 3.14


1 10.6 0.9 9.54
63.52 sqm 291.6 18522.43

Removing old plaster or edges, cleaning of


1422

joints and floor for new work and disposal of 50.84 sqm 21.1 1072.724
unserviceable materials within 50m lead

6mm cement plaster to Ceiling. (a) In


1011

Cement mortar 1:3 (1cement, 3sand) 50.84 sqm 134.2 6822.728

Providing and laying water proofing


treatment on roofs of slabs by applying
cement slurry mixed with water proofing
cement compound consisting of applying (a)
after surface preparation, first layer of slurry
of cement @ 0.488 kg/sqm mixed with water
proofing cement compound @ 0.253 kg/sqm.
b) laying second layer of Fibre glass cloth
when the first layer is still green.Overlaps of
joints of fibre cloth should not be less than 10
25-134

cm. (c) third layer of 1.5 mm thickness


consisting of slurry of cement @ 1.289 1 6.9 7.9 - 54.51 sqm 304.2 16581.94
kg/sqm mixed with water proofing cement
compound @ 0.670 kg/sqm and sand @
1.289 kg/sqm. This will be allowed to air cure
for 4 hours followed by water curing for 48
hours. The entire treatment will be taken upto
30cm on parapet wall and tucked into groove
in parapet all around.

Steel work welded in built up sections,


framed work, including cutting hoisting fixing
in position in gratings, frames, guard bars,
902

ladders, railing, brackets and similar works &


trusses and trussed purlins up to 25m span
and 15 m over all height

door 1 30 30 Kg 77.8 2334


window 1 25 25 Kg 77.8 1945
Distempering with dry distemper of approved
brand and manufacture (two coats) and of
required shade on undecorated wall surfaces
to give an even shade, over and including
priming coat of whiting after thoroughly
1320

brushing the surface free from mortar 1 31.4 3 94.2


dropping and other foreign matter including
preparing the surface even and sand
papered smooth

1 10.6 3 31.8
1 31.2 3.6 112.32
238.32 sqm 50.7 12082.82
electrification & Misc. LS 25000
158486
158486
Citizen Information Board 1500
Lab test 1500
Gran Total 161486
say (In lakh) 1.61
S.N RES sor ITEMS NO. L B D QTY. UNIT Rate Amount
O.

Providing and laying vitrified floor tiles in


different sizes with water absorption less
than 0.08% and confirming to IS:15622 of
approved make in all colours and shades laid
2556

on 20mm thick cement mortar 1:4 (1cement : 1 6.25 3.8 23.75


4sand) including grouting the joints with
white cement and matching pigments etc.,
complete.

Size of tile 1000 X 1000 10-12mm 1 2.3 2.8 6.44


1 3.6 2.8 10.08
40.27 sqm 1458 58713.66
2557

fixing on wall/skirting. 1 33.3 0.1 3.33


1 6.8 0.9 6.12
49.72 sqm 291.6 14498.35

Removing old plaster or edges, cleaning of


1422

joints and floor for new work and disposal of 40.27 sqm 21.1 849.697
unserviceable materials within 50m lead

6mm cement plaster to Ceiling. (a) In


1011

Cement mortar 1:3 (1cement, 3sand) 40.27 sqm 134.2 5404.234

Providing and laying water proofing


treatment on roofs of slabs by applying
cement slurry mixed with water proofing
cement compound consisting of applying (a)
after surface preparation, first layer of slurry
of cement @ 0.488 kg/sqm mixed with water
proofing cement compound @ 0.253 kg/sqm.
b) laying second layer of Fibre glass cloth
when the first layer is still green.Overlaps of
joints of fibre cloth should not be less than 10
25-134

cm. (c) third layer of 1.5 mm thickness


consisting of slurry of cement @ 1.289 1 6.25 6.8 42.5 186.3 7917.75
kg/sqm mixed with water proofing cement
compound @ 0.670 kg/sqm and sand @
1.289 kg/sqm. This will be allowed to air cure
for 4 hours followed by water curing for 48
hours. The entire treatment will be taken upto
30cm on parapet wall and tucked into groove
in parapet all around.

Steel work welded in built up sections,


framed work, including cutting hoisting fixing
in position in gratings, frames, guard bars,
902

ladders, railing, brackets and similar works &


trusses and trussed purlins up to 25m span
and 15 m over all height

door 2 30 60 Kg 77.8 4668

Distempering with dry distemper of approved


brand and manufacture (two coats) and of
required shade on undecorated wall surfaces
to give an even shade, over and including
priming coat of whiting after thoroughly
1320

brushing the surface free from mortar 1 43.1 3 129.3


dropping and other foreign matter including
preparing the surface even and sand
papered smooth

1 28.1 3.6 101.16


230.46 sqm 50.7 11684.32
electrification LS 15000
118736
118736
Citizen Information Board 1500
Lab test 1500
Gran Total 121736
say (In lakh) 1.22