CONSTRUCTION OF EXTERNAL WALL.

Bill of Quantities
Total
Item Description Unit QTY Rate (USD)
(USD)
Bill No. 01
A Preliminaries and Generals

Site clearance including ground leveling,tree cutting and garbage


1 Lumpsum 1 500 500
removal
Sub total of Preliminaries and generals 500
A Substructure
1 Foundation, Excavation Works

Earthwork in excavation for foundation walls (60cm deep and 40cm


1.1 wide), in all kinds of soil including dressing of bottom and sides of
trenches. Stack excavated soil clear from edges of excavation at least 1m.
Cu.m 31.20 12.5 390
Construction of 400mm rubble stone foundation all joints between
stones should be filled with cement/sand mortar with 1:4 ratio.
1.2
Minimum height of the foundation wall from the Ground level is
250mm.(avarage total depth 70cm) Cu.m 36.40 35 1274

1.3 Cast and construct 20cm thick of RCC Foundation Ring Beam with 12mm
dai rebar, 4NOs ,jointed with 6mm dai rebars @30cm c/c .Concrete mix
ratio should be 1:2:4 ( cement, Fine sand an Coarse aggregates ). Cu.m 10.40 300 3120

Subtotal Foundation, Excavation and Construction 4,784.00

SUPERSTRUCTURE
2 Wall construction

2.1
Construct 200mm thick solid concrete block walling bedded and jointed
in cement and sand (1:4)mortar Sq.m 200.00 18 3600

Construction 40cmx20cm solid block piller to prevent crack each 7mc/c Nos 22.00 55 1210
Construction of 200mmx200mm Reinforced Concrete continues lintel
2.2 beams over the walls 1:2:4 ratio with 4 nos 12mm ray-bars and 6mm dia
staffs c/c 30cm. . Cum 3.20 300 960

2.3
installing and fixing fence top of the boundry wall LS 1.00 1 1000

Subtotal of Wall Construction


` 6770

3 FIXTURES

Door

3.1
Supply and install metal door (2.5*2.5m) complete with imported keys Nos 1 900 900

subtotal of fixtures 900


4 FINISHES
Plastering and Painting

4.1 12mm thick plastering of 1:3 cement/sand ratio on both sides of the
walls including the foundation wall over GL Sq.m 400.00 5.3 2120
Apply three coats of white-washing and smoothing using stuco on both
4.2
sides of all wall faces with 1:275 lime/white glue Sq.m 400.00 2 800
Apply 3 coats of emulsion paint on to all sides of walls and 1.5m high
4.3 gloss paint on the internal walls.
Sq.m 400.00 2 800
Subtotal of Finishes 3,720.00

Grand Total 16,674.00


CONSTRUCTION OF SECUIRITY ROOMS AND MOTOR SHADE
Bill of Quantities
Rate Total
Item Description Unit QTY
(USD) (USD)
2 Floor Construction
250mm thick Back filling ,spreading , watering and
2.1 compacting the sand from the foundation trench
excavation. Sq.m 17.50 5 87.5

2.2 150mm thick hardcore durable stone (hardcore) and


aggregate to layed proberly. Cu.m 10.50 15 157.5
Laying 250mm thick floating floor RCC slab of 1:2:4
2.3 cement/sand/gravel concrete. reinforced with PRC
mesh including door steps . Cu.m 7.00 20 140
Cement screed with Tiles as per floor finishing with
2.3
2cm thick cement sand plaster 1:3 ratio on all floor Cu.m 70.00 20 1400

Subtotal of Floor Construction 1,785.00

SUPERSTRUCTURE

3 Wall construction

3.1
Construct 200mm thick solid concrete block walling
bedded and jointed in cement and sand (1:4)mortar Sq.m 175.00 20 3500

3.3 Construction of 200mmx200mm Reinforced Concrete


continues lintel beams 1:2:4 ratio with 4 nos 12mm
ray-bars and 6mm dia staffs c/c 30cm. Including Roof
lintel with same diamensions and reinforced with
bars. Cum 2.00 250 500
Construction of 200mmx200mm Reinforced Concrete
not continues lintel beams over the windows and
3.4
doors 1:2:4 ratio with 4 nos 12mm ray-bars and 6mm
dia staffs c/c 30cm. . Cum 1.50 200 300
3.6
casting varandah slab cum 3.00 250 750

Subtotal of Wall Construction 5,050.00

4 Roof Construction

Provide and fix timber 2m rise roof trusses c/c 2.30


,which its beams should be 150mmx50mm and
rafters of 100mmx50mm red timbers,nailed on
70mmX50mm purlings and CI gauge 28 with red-
4.1 oxide paint as the top roof . All the roof trusses will
be anchored with 6 mm dia. Bars casted in the
concrete roof linter. Roof purlins at gable ends will be
anchored with 6 mm dia. Bars.including 20cm wide
painted fascia board Sq.m 75.00 18 1350
Provide and install painted 6mm ply wood ceiling
board including ceiling wood joists 500mmx500mm
and ceiling frame including the scaffolding and
4.2
necessary tools

Sq.m 70.00 14 980

Subtotal of roof construction 2,330.00

5 FINISHES

Plastering and Painting

5.1
12mm thick plastering of 1:3 cement/sand ratio on
both sides of the walls including the foundation wall
over GL Sq.m 350.00 3.5 1225
5.2

Apply three coats of white-washing and smoothing


using stuco on both sides of all wall faces with 1:275
lime/white glue Sq.m 350.00 1 350
Apply 3 coats of emulsion paint on to all sides of walls
and 1.5m high gloss paint on the internal walls.
5.3

Sq.m 350.00 1.5 525

Subtotal of Finishes 2,100.00

6 FIXTURES

Doors and Windows

6.1
Supply and install metal door (1m*2.15m) complete
with imported keys Nos 3 85 255

6.2
Steel Window(SW for the store)(1.mX1.m) :Providing
and installing Three leaves steel window with steel
frame and metal grills with all their accessories such
as hinges, locks, etc Nos 5 65 325

Subtotal of Fixtures 580.00

7 EXTERNAL WORKS

excavation and construction of septic tank and


7.2 2,500.00
underground water reservior
Ls 1 1
Plumbing Works 600.00

ls 1 1

Electricity Works 600.00

Ls 1 1
subtotal of external works 3,700.00

Grand Total 15,545.00


Summary of Externall Wall and Two Rooms
Bill of Quantities
Rate Total
Item Description Unit QTY
(USD) (USD)
3 Floor Construction
3.1
External Wall ls 1.00 1 16,674.00

3.2 Two Rooms with septic tank and


underground water reservior ls 1.00 1 15,545.00

Grand Total of the Wall and two


32,219.00
Rooms