BILL OF QUANTITIES AND SPECIFICATIONS

CONSTRUCTION OF FENCE WALL PROJECT

No. Description Unit Quantity Price Total In US


I. SUB-STRUCTURE
1 Clear the site and excavate the top soil an average L. Sum 1 100 100.00
depth 100mm and remove from site
2 Excavate the foundation trench to 500mm depth M3 21 25 525.00
and 500mm wide
3 M3 2.1 150 315.00
Lay 50mm thick blinding concrete below the
column footing and foundation with ratio 1:4:8
4 Construct stone foundation an average height M3 28.56 45 1,285.20
850mm (450mm underground and 400mm above
the ground) and 400mm thick
5 Construct RCC ground beam 150mm thick with M3 5.04 350 1,764.00
#4 bars of 12mm dia and links of 6mm dia at
200c/c using concrete class M20
Sub-Total 3,989.20
II. SUPER STRUCTURE
6 Construct 200mm thick super structure wall with M2 199.5 20 3,990.00
1:4 mix ratio of cement and sand mortar including
scaffolding and all necessary tools. Wall heigh
should be 2500mm all work should be completed
as per drawings
7 Construct 50mm PCC ring beam over the M3 0.84 150 126.00
concrete cement block using concrete class M15

Sub-Total 4,116.00
III. DOORS
8 Supply and fix double leaf metel gate to the wall Item 1 650 650
with dimension 3000mmx2400mm
9 Supply and fix double leaf metel doors to the Item 1 200 200
wall. Size of the door are 1200x2100mm
Sub-Total 850.00
IV. FINISHING
10 Apply 20mm thick mortar on foundation, walls M2 453.6 5 2,268.00
and beams both inside and out side. Walls should
be cured at least one weak after 24 hours of
plastering
11 Supply and apply two coats of white wash on all M2 453.6 2 907.20
plastered surfaces
12 Supply and apply two coats of emulsion paint on M2 453.6 3 1,360.80
white washed area
Sub-Total 4,536.00
Grand Total 13,491.20

Prepared by: Abdiwahid Yusuf Muse