S/ DESCRIPTION OF WORK QUANTITY UNIT RATE AMOUNT

N
1. Allow for the removal of all existing - Sum - 100,000
damage roofing sheet, all hard wood
carcassing members with and including
demolition of block or concrete columns
and stanchions, scraping off of sand screed
floor finish and coats of paint to received
terrazzo
2. Plain insitu concrete apron (shoulder) 3.5 M2 30,000 105,000
round the block 600mm wide and 150mm
thick
3. Ditto but concrete ramp with 50mm - Sum - 90,000
diameter galvanised iron circular steel pipe
welded together to form patterns bedded
in concrete slab, sleeping not exceeding 60
degree, finish with tarazzo paving 1800mm
wide for disable
4. 225mm thick load bearing wall in super 48 M2 4,500 216,000
structure 1.3m heigh
5. Ditto but 150mm thick as paralet wall 1.3m 25 M2 4,500 112,500
heihht
6. Allow protecting all work under - Sum - 16,861

Concrete and block work carry to - - - 640,361


summary
ROOFING
1. 0.55mm thick long span aluminium roofing
sheet and accessories with coloured
finished lapped
2. Roofing not exceeding 90c degree from 165 M2 4,500 742,500
horizon
3. Eave angle 19 M2 2,500 47,500
4. Ditto but cladding 19 M2 3,500 66,500
WOOD WORK
Supply and fix the following well treatment
sawn hard wood timber
1. 50x150 raffer 1200 centre –centre 152 M 800 121,600
2. Ditto but struts and king post 146 M 800 116,800
3. Ditto but tie beam 135 M 800 108,000
4. 50x100mm timber purling 187 M 600 112,200
5. 50x50 timer noggin 1441 M 300 432,300
6. 6x3 inch USB as well plate across the block 19 M 12,000 228,000
span
7. Supply and fix magnetic ceramic steel white 2 No 80,000 160,000
board
8. Celetoc notice board 1.20m 2 No 15,000 30,000
9. Allow for protecting work under w/work - Sum - 15,000

Wood work and roofing carry to summary - - - 1,323,900


FLOOR WALL AND CEILING FINISH INSTU
FINISHE
1. Cast instu terrazzo paving on screened bed 160 M2 4,500 720,000
and approved colour laid 1200x1200 in bay
with and including ebonite dividing strip in
classroom and veranda
2. 13mm thick plastering to wall surface on 526 M2 1,200 631,200
internal and external wall
3. Allow for minor/major wall cracks - Item - 55,000
4. Tyrolene wall finishing using cement motor 230 M2 800 184,000
1:2 finish fair
CEILING
5. Flexible hard board ceiling fix to timber 160 M2 1,800 288,00
hard wood noggin with and including
38x13mm soft wood batten in classrooms
and veranda
Finish carry to summary - - - 1,878,200
PAINTING
1. Prepared and apply one under coat and 190 M2 750 142,500
one finishing coat of light blue emulsion
paint internally
2. Prepared and apply one under coats and 160 M2 750 120,000
two finish, coats of while emulsion on
celling surface
3. Prepared and apply two coats of emulsion 295 M2 750 221,250
paint on external walls
4. Apply two coat of approve colour gloss part 53 M2 900 47,700
to doors and windows
5. Ditto but light blue gloss paint internally to 133 M2 900 119,700
lintel level
6. Ditto but lower part of the skirting at height - Item - 10,000
0.30m
7. Levelling/inscription - Item - 10,000
Painting carry to summary - - - 690,850
FURNITURE
1. Construction and distribution of 2 scatters 42 Ng 37,209 1,562,778
pupils furniture
2. Construction and distribution of set 2 Set 41,861 83,722
teachers furniture
Furniture carry to summary 1,646,500
REHABILITATION OF 2 BLOCKS OF 8 VIP
TOILETS
1. Remove existing damage roofing sheet and - Sum - 23,733
wood
2. 50x100 timber purlins 15 M 600 9,000
3. 50x50 timber noggins 40 M 300 12,000
4. 0.55mm thick long span aluminium roofing 38 M2 4,500 171,000
sheets
5. Supply and fix purpose made steel door size 3 No 30,000 90,000
with pad lock
6. 13mm floor screed finish fair and smooth 24 M2 1,500 90,000
7. 13mm thick plastering to wall surface 80 M2 1,200 96,000
internally
8. Tyroleven cement finish extremely 83m2 1,200 800 66,400
9. Hardboard ceiling fix to nogging will cover 24 M2 1,800 43,200
better
10. Plain in situ concrete in concrete slab at 3 M2 40,000 120,000
back
11. Prepare and apply two coats of whitr 24 M2 850 20,400
emulsion paint to ceiling
12. Prepare and apply light blue emulsion 83 M2 850 70,550
internally
13. Ditto but externally 93 M2 850 79,050
14. Prepare and apply gloss pain on metal and 9 M2 1,200 10,800
facia board
15. Ditto but lower part of block work not 19 M 1,200 22,800
exceeding 0.60m
16. Painting of standard inscription - - - 16,989
17. 100mm diameter PVC pipes with elbow 2 No 10,000 20,000
Toilets carry to summary - - - 820,189
GENERAL SUMMARY
1. Concrete and block work - - - 640,361
2. Wood work and roofing - - - 1,323,900
3. Floor finish and ceiling - - - 1,878,200
4. Painting - - - 690,850
5. Furniture - - - 1,646,500
6. Toilet - - - 820,1892

GRAND TOTAL ================== 7,000,000


S/ DESCRIPTION OF WORK QUANTITY UNIT RATE AMOUNT
N
1. Allow for the removal of all existing - - Sum 110,000
damage roofing sheet all hard wood
carcassing members with and
including demolition of block or
concrete removal of scarfing off of
sand screed floor and coat of pain to
receive terrazzo
2. Plain in situ concrete apron 4 M3 35,000 140,000
(shoulder) round the block 600mm
wide and 150mm thick
3. Ditto but concrete ramp with 50mm - Sum - 95,000
diameter galuanise iron circular steel
pipe welded together to form
BLOCK WORK

4. 225mm thick load bearing wall in 25 M2 4,500 234,000


super structure 1:3m height
5. Ditto but 150mm thick as parapet 29 M2 4,500 130,500
wall 1:3m height
6. Allow for protecting all work under - Sum - 10,000
block work.
Demolition and block work carry - - - 719,500
ROOFING

0.55mm thick long span aluminium roofing


sheet and accessories with coloured
finished lapped
1. Roofing not exceeding 90 degree from 288 M2 4,500 1,296,000
horizontal
2. Leave angle 62 M2 2,500 155,000

3. Ditto but cladding 23 M2 4,955 113,965

4. Precast concrete gutter as water flow 7 Ng 4,000 28,000


passage
5. Allow for protecting all work under roofing - Sum - 25,496

Roofing carry to summary - - - 1,618,461


WOOD WORK

Supply and for the following well treated


sawm hard wood times
1. 50x150mm times raffers 162 M2 800 129,600

2. Ditto but struit and king post 173 M 800 138,400

3. Ditto but tie beam 160 M 800 128,000

4. 50x100mm timber purlins 220 M 600 132,000

5. 50x50mm timber noggia 1650 M 300 495,000

6. 6x3 universal steel beam wall plate for roof 22 M 120,00 264,000
member support across the block span
7. Poly vision e3 magnete ceramic steel white 2 No 80,000 160,000
board
8. Celetox notice board 1:20m 2 No 15,000 30,000

9. Allow for protecting all work under work - - - 5,000

Wood work carry to summary - - - 1,482,000


FLOOR WALL AND CEILLING FINISHES
INSITU FINISHES
1. Cast in situ terrazzo paving on screeded 186 M2 4,500 837,000
bad of approved colour laid 1200x1200 in
bay with and including ebonite dividing
strip in classroom and verandah
2. 13mm thick plastering to wall surface 652 M2 1,200 782,400
internal and external
3. Allow for minor/major wall cracks - Item - 39,939

4. Tyrolene wall finishing finish fair 244 M2 800 195,200

5. Flexible hard board ceiling fix to timber 186 M2 1,800 334,800


noggin with and including batter
Floor wall and ceiling work carry to - - - 2,189,339
summary
PAINTING

1. Prepare and apply one leader coat and one 234 M2 750 175,500
finishing coat of light blue emulsion
internally
2. Prepare and apply two finishing coat of 186 M2 750 139,500
white emulsion pain on ceiling surface
3. Prepare and apply emulsion paint on 368 M2 750 276,000
external wall
4. Prepare knot prime stop and apply two 56 M2 900 50,400
coats of gloss paint to doors and windows
5. Ditto but light blue gloss paint on internally 164 M2 900 147,600
lintel level
6. Ditto but lonee part of skirting 37 M2 900 33,300

7. Level inscription - Item - 10,000

Painting work carry to summary - - - 832,300


FURNITURE

1. Construction and distribution of 2 seater 84 No 37,209 3,125,556


pupil furniture
2. Construction and distribution of set teacher 6 No 41,861 251,166
furniture
Furniture carry to summary - - - 3,376,722
S/ DESCRIPTION OF WORK QUANTITY UNIT RATE AMOUNT
N
7. Allow for the removal of all existing - - Sum 110,000
damage roofing sheet all hard wood
carcassing members with and
including demolition of block or
concrete removal of scarfing off of
sand screed floor and coat of pain to
receive terrazzo
8. Plain in situ concrete apron 4 M3 35,000 140,000
(shoulder) round the block 600mm
wide and 150mm thick
9. Ditto but concrete ramp with 50mm - Sum - 95,000
diameter galuanise iron circular steel
pipe welded together to form
BLOCK WORK

10. 225mm thick load bearing wall in 25 M2 4,500 234,000


super structure 1:3m height
11. Ditto but 150mm thick as parapet 29 M2 4,500 130,500
wall 1:3m height
12. Allow for protecting all work under - Sum - 10,000
block work.
Demolition and block work carry - - - 719,500
GENERAL SUMMARY

1. Demolition and block work - - - 719,500

2. Roofing - - - 1,618,461

3. Wood work - - - 1,489,000

4. Floor wall and ceiling finish - - - 2,189,339

GRAND TOTAL ================== 7,000,000