Professional Documents
Culture Documents
LOCATED AT RUBAVU
BILL OF QUANTITY
IV REINFORCED CONCRETE
1 Footing base 1500*1500*300mm Cm 14.9 300,000 4,470,000
2 Sub-column, column (300*300*2700) Cm 5.15 300,000 1,545,000
4 200*450mm beams Cm 10.92 250,000 2,730,000
5 Slab of 150mm thick Cm 28.14 300,000 8,442,000
S/TOTAL 12,717,000
V ELEVATION
The wall should be constructed in cement
block with cement sand joint
200mm thick cement block wall bedded and
jointed in cement and sand (1:4) mortar with
V.1 every alternate course Cm 102.59 40,000 4,103,600
1 S/TOTAL 4,103,600
External and Internal wall finishes
15mm thick two coats cement sand wall (1:6)
V.1.2 plaster both side finished smooth with steel Sm 516 3,000 1,546,890
Painting by applying three coats on the render
1 plastered wall Sm 517 2,500 1,291,625
2 S/TOTAL 2,838,515
3 DOORS
3 S/TOTAL 620,000
FLOOR FINISHES
X PLUMBING INSTALLATION
Installation and pipes laying from the main item 1 100,000 100,000
1 Installation of sitting water closet with all pcs 2 100,000 200,000
2 Installation of hand washing basin with all pcs 1 80,000 80,000
4 Installation of shower with all accessories pcs 2 150,000 300,000
5 Fixing of mirror pcs 2 15,000 30,000
6 Fixing of soap holder pcs 2 8,000 16,000
7 Fixing of toilet paper holder pcs 2 8,000 16,000
8 Fixing of towel holder pcs 2 10,000 20,000
9 Drainage of rain water pipe item 4 300,000 1,200,000
10 Inspection chamber of 50*50*50cm cm 4 50,000 200,000
11 Floor traps item 12 30,000 360,000
12 Under ground rain water tank Cm 4 200,000 800,000
13 Septic tank ff 4,000,000
14 Soak pit of 25m lm 25 4,000 100,000
15 S/TOTAL 7,422,000
ELEVATION
Four Colunms Supporting Roof covering
(450*450) section wdith by Side and Covered
with Aluminium sheet
1 Footing base (2000*2000*500)mm Cm 4 300,000 1,200,000
2 Sub-Column (450*450*5000)mm Cm 4 300,000 1,200,000
II S/TOTAL 1,200,000
III ROOF STRUCTURE
1 Metallict trusses 60*40*5mm lm 300 12,000 3,600,000
2 Metallic tube for purlins 40*40*5mm lm 300 12,000 3,600,000
3 Sheets metal 26 B.G with bolts Sm 1408.4 2,000 2,816,000
4 Metallic gutter lm 68.8 4,500 309,600
Down PVC pipe with all accessoires for rain
5 water lm 82 4,500 369,000
6 Elbow pcs 500 4,500 2,250,000
S/TOTAL 12,944,600
X MECHANICAL MACHINES
1 Fuel Pumps pcs 4 4,000,000 16,000,000
2 Citernes pcs 2 500,000 1,000,000
3 Generator pcs 1 800,000 800,000
S/TOTAL 17,800,000
EXTERNAL WORKS
Surface by compacting hard the earthworks
and sprayering and compact bitumen parking
1 and walking and Driving ways ff 20,000,000
Trench exacation and fixing metal on top of
2 the trench Sm 138.62 3,500 485,170
3 Garden ff 250,000
4 Streets Lights in the parking yard pcs 2 150,000 300,000
S/TOTAL 21,035,170
FENCE
4 Excavation of trenches and Footings Cm 79.6 2,000 159,200
5 Stone foundation Cm 53.09 50,000 2,654,500
6 Footings and columns Cm 11.73 300,000 3,519,000
7 Wall elevation with stone walling Cm 84.97 40,000 3,398,800
8 Gates item 2 350,000 700,000
XII Light pcs 10 10,000 100,000
S/TOTAL 10,531,500
S/TOTAL 27,216,670
Ni word : One hundred twenty Million Eighty Nine thousand five hundred and twenty eight.