1.SUPESTRUCTURE
WALLING
Masonry walls bedded and jointed in cement and
A sand (1:4) mortar in:
200mm thick walls reinforced with 32x2mm hoop iron SM 182 1,500 273,000.00
every alternate course
B
150mm thick walls reinforced with 32x2mm hoop iron SM 205 1,400 287,000.00
every alternate course
C
Provide 100mm pipe vents in beam above all doors NO 8 500 4,000.00
with wire gauze and 25mmx400mm approximately in
all windows upper middle compartment as permanent
ventilation
TOTAL FOR WALLING TO SUMMARY 564,000.00
TYPICAL FLOORS R.C SLAB
Vibrated reinforced concrete class 25/20mm in;
D Columns CM 8 13,000 104,000.00
E
Beam; 1,3&5 (600*200) CM 8 13,000 104,000.00
2&4 (600*250) CM 6 13,000 78,000.00
6 (450*200) CM 2 13,000 26,000.00
F
Slab 175mm Thick CM 40 12,000 480 ,000.00
G Reinforcement
Columns
H
Y16, Y12 KG 416 150 62,400.00
Painting
Prepare and apply three coats first quality plastic
P emulsion paint to: -
Internal Walls SM 270 130 35,100.00
FLOOR FINISHES
R 40mm thick 1:4 Cement Sand render to floor SM 180 400 72,000.00
S
5mm thick cement screed to floor SM 180 70 12,600.00
T
Ditto, but 100mm high skirting LM 120 140 16,800.00
TOTAL FOR FLOOR FINISHES TO SUMMARY 101,400.00
WINDOWS
Supply and fix steel casement windows consisting of
Standard Angline section frames and square rods
primed with one coat red oxide complete with steel
metal;
U
Windows size 1500x1500mm high(W1) NO 4 7,500 30,000.00
V
Ditto size 800x800mm high(W2) NO 1 3,000 3,000.00
SUMMARY
1 WALLING 564,000.00
2
SLAB REINFORCEMENT 1,389,800.00
3
WALL FINISHES 219,400.00
4
FLOOR FINISHES 101,400.00
5
EXTERNAL OPENINGS
SUB-TOTAL 2,274,600.00
Add 5% Contingency 113,800.00
TOTAL 2,388,400.00