S/N DESCRIPTION OF CLINIC QTY UNIT RATE AMOUNT(N)
1. PRELIMINARIES (1.5%)
2 SUBSTRUCTURE
Foundation Works
Excavating and filling
A Excavate foundation trench commencing at stripped level
exeeding 2.00m maximum depth width exeeding 0.30m 100.5 m2 29,038 2,920,100.00
B Excavate column pit 200 below strip depth 0.9 m2 3000 2,750.00
C Selected excavated material backfilling well watered and 56.4 m2 450 25,400.00
consolidated arround foundation
Filling
D Imported laterite filling well watered and consolidated in 82.5 m2 50,861 4,200,500.00
300mm thick layers in making up level under floor slab.
Surface treatment
E Level and compact bottom of excavation 81.4 m2 210 17,100.00
Blockworks:
Hollow sandscrete blockwork in cement. Motar (1:6) laid in strecher
bond filled solid with concrete [1:4:8-12mm aggregate] as work
progresess in: 251.1 m2 7,610,000.00
N
31,241,000.00
Carried to collection
SUPER STRUCTURES
Balustrades to Staircases
Supply and installation of stainless steel handrailing to staircases
in accordiance with Architect’s details/specification; fixed to
129.8 ln 42,000 5,450,000.00
concrete or blockwork
5 FLOOR FINISHINGS
Mortar, cement and sand (1:4); steel trowelled
50mm thick work to floors; one coat; screeded level and to falls
only not exceeding 15 degrees from horizontal to receive tiles
Stone/Concrete/Quarry/Ceramic tiling/Mosaic
750 x 750 x 10mm thick quality glazed vitrified tiles laid with
cement slurry or adhesives to approved pattern on screeded bed
(measured separately)
6 WALL FINISHINGS
Plastering Work
Providing & applying minimum of 12mm thick cement plaster on
existing wall after surface preparation, including; scaffolding , cauring,
rubbing the surface, raking out the joint etc., complete as directed and Sum 4,500,000.00
specified for walls, parapet, platform supports etc., at all floor levels.
POP SCREED
3mm thick POP screeding on rendered walls
38mm thick Polished high quality solid core HDF doors complete
with subframe, frames, architraves, locks, hinges and other fixing
accessories.
1200mmx 2100mm
900mmx 2100mm
750mmx 2100mm
9 SUSPENDED CEILING FINISHING
Allow for a provisional sum for a minimum of 12mm thick suspended
sum 11,006,600
POP ceilings fixed to slab and rafters with all connectig profiles, grids
and accssories with scaffolds.
800 220,000.00
275 Nr
20 mm Holding down bolts in 22 mm hole at 50 mm c/ c to
hold beam horizontal member to vertical member
Strut Members
2/75 x 75 x 6mm – 7.35kg/m equal angle 7.2 550,000.00 3,999,000.00
ton
s
Z-Purlin
Z-Purlin, 150 x 56 x 2mm – 3.57kg/m, bolted to angle cleat 0.6 t 750,000.00 2,787,000.00
(measured seperately)
Sag Rod
0.7 t
16mm diameter reinforcement bar with bolt and nut welded to 2,714,280.00 1,901,000.00
it at both ends
16mm bolts and nut fixed to sag rods 775.8 Nr 600.00 465,500.00
2 7,500.00 3,400,000.00
Eave soffits, exceeding 50 0 mm wide; 453.7 m
3,900.00 1, 110,500.00
Eave Fascial, not exceeding 5 0 0 mm wide; 284.7 m
7,800.00 2,422,000.00
Ridge Cap, Batch Board, Gutter; 6 0 0 mm wide 31.5 m
1,950.00 900,000.00
Eaves angle, Bottom angle, wall trimming; 1 5 0 mm wide 461.5 m
Distribution board;
1,025,000.00
Allow a provisional sum of N800,000.00 for the supply of
A
distribution boards
Lighting;
2,101,000.00
C
Allow a provisional sum of N5,750,000.00 for the supply and
fixing of lighting cables with fittings
Power;
1,980,000.00
D Allow a provisional sum of N4,950,000.00 for the supply and
fixing of power cables, servie wire and accessories
11,503,500.00
Carried to Collection
14
MECHANICAL WORKS AND INSTALLATIONS
A
Waste pipes/ sanitary fittings;
Allow the provisional sum of N9,400,000.00 for sanitary wares sum 3,315.000.00
B Water pipes/fittings;
sum 2,138,000.00
Allow the provisional sum of N4,000,000.00 for water pipes and
fittings
C Sewage System;
1,863,500.00
Allow a provisional sum of N6,300,000 for Biosewage or septic sun
tank and soakaway.
D Airconditioning Pipes;
Allow the provisional sum of N2,600,000.00 for AC piping/sleeve sum 500,000.00
COLLECTIONS SUMMARY
SUBSTRUCTURES 31,241,000.00
2
SUB-TOTAL 220,964,992.50
TOTAL 227,593,942.28