You are on page 1of 11

CLINIC

CLINIC
S/N DESCRIPTION OF CLINIC QTY UNIT RATE AMOUNT(N)
1. PRELIMINARIES (1.5%)

2 SUBSTRUCTURE
Foundation Works
Excavating and filling
A Excavate foundation trench commencing at stripped level
exeeding 2.00m maximum depth width exeeding 0.30m 100.5 m2 29,038 2,920,100.00

B Excavate column pit 200 below strip depth 0.9 m2 3000 2,750.00

C Selected excavated material backfilling well watered and 56.4 m2 450 25,400.00
consolidated arround foundation

Filling
D Imported laterite filling well watered and consolidated in 82.5 m2 50,861 4,200,500.00
300mm thick layers in making up level under floor slab.

Surface treatment
E Level and compact bottom of excavation 81.4 m2 210 17,100.00

F Prepare and apply Dieldrex 20 or other equal and approved anti-


termite solution to sides and bottom of excavation 14.6 m2 90,527 1,330,500.00

In situ concrete works


Plain in situ concrete (1:3:6-40mm aggregate) developing
G minimum 25/Nm2 working strenghth at 28 days well filled and m2 48,831 1,330,500.00
computed in 37.4
Foundation dtrip 100mm thick
33.1 m2 33,000 1,094,500.00
H
Column Base 250mm thick
130.2 m2 56,371 7,341,000.00
I
Floor bed not exeeding 80mm thick

Formework for insitu concrete:


Plain vertical formwork to:
77.9 m2 11,550 900,000.00
J
Edges of bed 150mm high

Reinforcement for insitu concrete:


High yield deformed bar reinforcement to B.S 4462 including typing
wire, distance blocks and ordinary spaces: 1,100,000.00
Kg 20,016
K In Columns: 54.9
12mm diameter in straight and bent bars 12,500.00
96.1 Kg 130
L
8mm diameter in links and stirrups

84.8 Kg 1303 110,500.00


M In Footings:
12mm diamter in staright and bent bars

Blockworks:
Hollow sandscrete blockwork in cement. Motar (1:6) laid in strecher
bond filled solid with concrete [1:4:8-12mm aggregate] as work
progresess in: 251.1 m2 7,610,000.00
N

225mm thick walls in foundation

31,241,000.00
Carried to collection
SUPER STRUCTURES

3 BRICK/BLOCK WORK/ MASONRY


BRICK/BLOCK WALLING

Sandcrete blocks, hollow, 450 x 225,keyed both edges in cement-


sand mortar (1:4); flush smooth pointing as work proceeds

225 mm walls m3 1250 4,500,000.00


3600

Vibrated reinforced in-situ concrete grade 2 0 N/mm2 at 28 day


with 20mm aggregate, minimum cement content 300kg/m3;

Lintels and columns m3 7500 1,690,000.00


225.3
FORMWORK FOR IN- SITU CONCRETE

Sawn treated and fairfaced smooth finish 2,060,000.00


59 m3 35,000
Sides and soffit of Lintel.

High yield steel bar reinforcement to B. S 4 4 6 1 as before described

10mm -12mm diameter in lintels 3,560,000.00


131.8 t 27,000

4 STAIRCASE & HANDRAILS

Balustrades to Staircases
Supply and installation of stainless steel handrailing to staircases
in accordiance with Architect’s details/specification; fixed to
129.8 ln 42,000 5,450,000.00
concrete or blockwork
5 FLOOR FINISHINGS
Mortar, cement and sand (1:4); steel trowelled

50mm thick work to floors; one coat; screeded level and to falls
only not exceeding 15 degrees from horizontal to receive tiles

Tread; width 300mm

1 9mm work to plain risers on concrete base height 150 mm

Ditto, 100mm wide skirting 11,075,000.00

Stone/Concrete/Quarry/Ceramic tiling/Mosaic

750 x 750 x 10mm thick quality glazed vitrified tiles laid with
cement slurry or adhesives to approved pattern on screeded bed
(measured separately)

Ditto, 100mm wide skirting

Ditto tread; 3 0 0 mm wide staircases

Ditto risers; height 150 mm staircases

6 WALL FINISHINGS

Plastering Work
Providing & applying minimum of 12mm thick cement plaster on
existing wall after surface preparation, including; scaffolding , cauring,
rubbing the surface, raking out the joint etc., complete as directed and Sum 4,500,000.00
specified for walls, parapet, platform supports etc., at all floor levels.

POP SCREED
3mm thick POP screeding on rendered walls

staircase; (landing and sloping soffit)


Sum 3,020,000.00
7 WINDOW INSTALLATIONS
Aluminium sliding window glazed with 5mm clear sheet glass and fixed
to concrete or blockwork surround complete with accessories and
burglary roof:

Size: 1800 x 1500mm 8,700,000.00


1500 x 1200mm
1200 x 900mm
900 x 600mm
600 x 600mm
Dry wall Partitioning

8 DOORS & INSTALLATION


TIMBER DOORS

38mm thick Polished high quality solid core HDF doors complete
with subframe, frames, architraves, locks, hinges and other fixing
accessories.

Ditto, size 1200mmx 2100mm

Ditto, size 900mmx 2100mm

Ditto, size 750mmx 2100mm

Entrance and Exit Doors


14,400,500.00
Supply and fix high quality galvanised security doors, including sub -
frame, key, hinges, and other accessories.
Double leaves size 1200 x 2100mm high
Double leaves size 1500 x 2100mm high
Aluminium doors
Supply and fix quality white powder coated aluminium composite door
complete profile, with 10mm thick plain glass,including subframes and
all necessary ironmongery,fixing screws;fixed in accordance with
manufacturer instruction

Sensor signal sliding aluminium door size 1800 x 2400mm high

1200mmx 2100mm

900mmx 2100mm

750mmx 2100mm
9 SUSPENDED CEILING FINISHING
Allow for a provisional sum for a minimum of 12mm thick suspended
sum 11,006,600
POP ceilings fixed to slab and rafters with all connectig profiles, grids
and accssories with scaffolds.

10 PAINTING AND DECORATING

Prepare and apply three coats emulsion paints on:


Internal and external wall sum 9,600.00.00

Walls 100 – 200mm wide

11 EXTERNAL WORKS & LANDSCAPING

The landscaping includes provision for flower beds, walk


ways, passages and car parks and other horticultural works, sum 5,250,000.00
levelling, filling, excavating, surface dressing, refuse
dumping and physical acthetics of the surroundings.

Allow a provisional sum for landscaping purpose.


12 A ROOF AND COVERING
Structural Steel work

Steel Truss Roofing


Framing, fabrication and permanent erection of weldable steel
to B.S.4360. Hot rolled sections welded fabrication and bolted
site connection at roof level average 6.00m above ground floor
level, with and including painting off site with red oxide primer
on surfaces.

17.2 ton 1,450,000.00 25,001,000.00


Universal Column, 254 x 254 x 89kg/m S275 s
2.5 1,450,000.00 3,750,000.00
Universal Beam, 254 x 102 x 25kg/m S275 ton
s
304 Nr 72,000.00 2,190,000.00
500 x 500 x 25mm thick base plate

800 220,000.00
275 Nr
20 mm Holding down bolts in 22 mm hole at 50 mm c/ c to
hold beam horizontal member to vertical member

Top Chord Rafter


2/100 x 100 x 8mm – 11.87kg/m equal angle 6.3 ton 550,000.00 3,500,000.00
s
Bottom Chord Rafter
ton 550,000.00 4,821,000.00
2/100 x 100 x 10mm – 14.24kg/m equal angle 8.1
s

Strut Members
2/75 x 75 x 6mm – 7.35kg/m equal angle 7.2 550,000.00 3,999,000.00
ton
s
Z-Purlin
Z-Purlin, 150 x 56 x 2mm – 3.57kg/m, bolted to angle cleat 0.6 t 750,000.00 2,787,000.00
(measured seperately)

Sag Rod
0.7 t
16mm diameter reinforcement bar with bolt and nut welded to 2,714,280.00 1,901,000.00
it at both ends

Haunch 20.8 Nr 44,454.50 926,500.00


8mm Gusset Plates

Bolts and Nuts


16mm Holding down bolts in 18mm hole at 50mm c/c 300 600.00 180,000.00
Nr

16mm bolts and nut fixed to sag rods 350.8


Nr 600.00 210,500.00

Connection Plate 205.2 2,000.00 410,500.00


125 x 75 x 6mm Angle cleats Nr

16mm bolts and nut fixed to sag rods 775.8 Nr 600.00 465,500.00

Total Carried To Collection 50,362,000.00


Roof Covering
In situ concrete works to roof beams and slab.
12B
Aluminium roof covering fixed to steel roof trusses.
The Contractor is however referred to Architect’s and
Structural Engineer’s drawings for details and scope of the
works.

Aluminium Sheet Covering

Any equal and approved 0.70mm guage corrugated longspan


aluminium roofing sheet lapped and fixed in accordance with
manufacturer
instruction including coating surface in contact with
other materials with bituminous paint on:
7,500.00 21,500,000.00
Covering, exceeding 500 mm wide; pitch not exceeding 15 0 2866.6 m2

2 7,500.00 3,400,000.00
Eave soffits, exceeding 50 0 mm wide; 453.7 m

3,900.00 1, 110,500.00
Eave Fascial, not exceeding 5 0 0 mm wide; 284.7 m

7,800.00 2,422,000.00
Ridge Cap, Batch Board, Gutter; 6 0 0 mm wide 31.5 m

1,950.00 900,000.00
Eaves angle, Bottom angle, wall trimming; 1 5 0 mm wide 461.5 m

Total Carried to Collection


29,332,000.00
13 ELECTRICAL WORKS AND INSTALLATIONS

P .C. SUMS/ PROVISIONAL SUMS/ DAYWORKS


PROVISIONAL WORK

Include the following provisional sums:-

Distribution board;
1,025,000.00
Allow a provisional sum of N800,000.00 for the supply of
A
distribution boards

Conduit Pipings and sockets;

B Allow a provisional sum of …. for electrical pipes and 2,258,000.00


sockets.

Allow the provisional sum of ….. for DSTV/TV and 640,000.00


Telecommunication pipes ONLY

Lighting;
2,101,000.00
C
Allow a provisional sum of N5,750,000.00 for the supply and
fixing of lighting cables with fittings

Power;
1,980,000.00
D Allow a provisional sum of N4,950,000.00 for the supply and
fixing of power cables, servie wire and accessories

E Other electrical accessories; 3,499,500.00


Allow a provisional sum of…… for thunder arrest, change over, cut out,
security light, composite trunks etc

11,503,500.00
Carried to Collection

14
MECHANICAL WORKS AND INSTALLATIONS
A
Waste pipes/ sanitary fittings;

Allow the provisional sum of N9,400,000.00 for sanitary wares sum 3,315.000.00

Allow the provisional sum of N4,500,000.00 for soil and waste


sum 2,640,000.00
pipes and fittings

B Water pipes/fittings;

sum 2,138,000.00
Allow the provisional sum of N4,000,000.00 for water pipes and
fittings

C Sewage System;
1,863,500.00
Allow a provisional sum of N6,300,000 for Biosewage or septic sun
tank and soakaway.

D Airconditioning Pipes;
Allow the provisional sum of N2,600,000.00 for AC piping/sleeve sum 500,000.00

Total Carried to Collection 10,455,500.00


COLLECTIONS SUMMARY

ITEM DESCRIPTIONS QTY UNIT RATE AMOUNT

COLLECTIONS SUMMARY

1 PRELIMINARY (1.5%) 3,265,492.50

SUBSTRUCTURES 31,241,000.00
2

3 SUPER STRUCTURES 84,805.500.00

4 R O OF & COVERINGS 79,694,000.00

5 ELECTRICAL WORKS & INSTALLATIONS 11,503, 500.00

6 MECHANICAL WORKS & INSTALLATIONS 10,455,500.00

SUB-TOTAL 220,964,992.50

ADD: CONTINGENCIES (3%) 6,628,949.78

TOTAL 227,593,942.28

TOTAL CARRIED TO GENERAL SUMMARY 227,593.942.28

You might also like