ITEM SUB STRUCTURE(FOUNDATION) UNIT QTY RATE AMOUNT

DESCRIPTION

1 Site clearance sm 600 100 6000

2 Setting out 10,000

3 Excavation of foundation trenches to a M3 370 300 111,000


depth not exceeding 1.5m
4 Excavation for pits for basis M2 60 200 12,000

5 Blinding concrete class 15/20 mix 1:3:6 M2 15 8500 127,500


50mm thick
6 Steel re-enforcements to
Columns KG 1184 200 236,800
Bases KG 836 200 167,200
Strip foot KG 948 200 189,600

7 Foundation concrete class 25/20 M2 49 13,500 661,500

8 Natural stone re-in forced with hoop iron sm 600 2,100 1,260,000
(optional) at every alternate course.
200mm thick
9 Formwork to columns sm 58 800 46,400

10 Concrete class 25/20 to columns M2 4 13,500 54,000

11 Back filling to sides of foundation walls M2 200 150 30,000


with appropriate materials
12 Hard core filling in layers not exceeding M2 410 300 123,000
300mm
13 Murram blinding 5mm thick sm 410 200 82,000

14 Anti-termite treatment as termidor or sm 410 150 65,000


equal quality
15 Dpm 500g polythene to all treated surfaces sm 410 300 44,000

16 BRC A142 Mesh reinforcement including M2 410 300 123,000


laps
17 Allow for a sum of Ksh. 350,000 for 350,000
electrtrical and plumbing pipe

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


18 Form work to sides of slab 5m 60 80 48,000
19 Concrete class 25/20 M2 41 13,500 553,500
1000mm thick mix 1:15:3 to ground floor
slabs
4,324,000
Total