You are on page 1of 73

It No Description Unit

Origional Qty. Unit Rate

SPECIFICATION AND BILL OF QUANTITIES

HEALTH CENTER

IPD BLOCK

A. SUB STRUCTURE

1 Excavation and Earth Works ...........................Birr


2 Concrete Works ............................................. Birr
3 Masonry Works ............................................. Birr

Total A .......... Birr

B. SUPER STRUCTURE

1 Concrete Works ............................................ Birr


2 Blockwork……………….………………… Birr
3 Roofing ……………………………………… Birr
4 Carpentry and Joinery……………………… Birr
5 Metal work ………………………………… Birr
7 Finishing ………………………………… Birr
8 Glazing ………………………………………… Birr
9 Painting……………………………………… Birr
10 Sanitary Installation……………………… Birr
11 Electrical Installation……………….. ……… Birr

Total B ………………. Birr

Total A +B for one unit……………….. Birr

Item no Description Unit Qt unit rate

A. SUB STRUCTURE

1. EXCAVATION AND EARTH WORK


1.1

Clear off the site to remove top soil to an


average depth of 200mm. M2 366.83 7.00
1.2

Bulk excavation in ordinary soil to reduce level


to a depth not exceeding 1500mm. M3 454.77 50.00
1.3
Ditto but exceeding 1500mm but not exceeding
3000mm. M3 30.32 100.00
1.4 Bulk excavation in weathered basaltic rock to
reduce level for to a depth exceeding 3000mm
but not exceeding 4500mm. M3
1.5 Trench excavationin ordinary soil to a depth not
exceeding 1500mm from reduced ground level. M3 77.99 100.00
1.6 Trench excavationin ordinary soil to a depth
exceeding 1500mm from reduced ground level. M3 88.38 100.00
1.7 Pit excavation in ordinary soil to a depth not
exceeding 1500mm from reduced ground level. M3 60.75 200.00
1.8 Pit excavation in ordinary soil to a depth
exceeding1500mm but not exceeding 3000mm
from reduced ground level. M3 68.85 200.00
1.9
Fill under slab with borrowed selected material
from quarry waste. The filling shall be
performed in layers of 200mm with
watering and compacting each layer properly. M3 363.82 20.00
2.0
Return fill around foundation with selected
excavated material from quarry waste and well
ram in layers not exceeding 200mm thickness. M3
2.1
fill around masonry foundation wall externaly
with selected excavated material from quarry
waste and well ram in layers not exceeding
200mm thickness.
2.2
Load and cart away surplus excavated material
and deposit at an appropriate tip. M3 854.43 10.00
1.11

250mm thick basaltic or equivalent stone hard


core well rolled consolidated and blinded with
crushed stone. M2 194.43 340.00
TOTAL CARRIED TO SUMMARY………………………............ Birr
2. CONCRETE WORK
2.1
50mm thick lean concrete in C-5 with
minimum cement content of 150kg/m3 of
concrete under:
a) under floor slab M2 194.43 1.00
b) under footing pad M2 18.00 500.00
c) under ground floor beam M2 66.74 500.00
2.2 10x100mm styropor foam expansion joint filler
between Grade beam and floor slab. Ml 193.98 100.00
2.3

Reinforced concrete class C-25 (with a 28-day


150mm cube crushing strength of 25MP)awith
minimum cement content of 360kg/m3 cast
into form work and vibrated around rod
reinforcement bar.
a) In footing pad M3 4.50 5000.00
b) In foundation column M3 1.67 5000.00
c) In ground floor beam. M 3
23.36 5000.00
e) In steps M3 0.46 5000.00
f) In 120mm thick ground floor slab M 2
194.43 5000.00
f) In 100mm thick ramp M 2
0.36 5000.00
2.4 Provide, cut and fix in position sawn structural
timber or steel form work whichever is
appropriate;

a) To footing pad M2 14.40 200.00


b) To foundation column M2 33.42 200.00
c) To grade beam M 2
146.82 200.00
d)Stair M2 1.15 200.00
e)Ramp M 2
0.74 200.00
2.5 Steel reinforcement bar according to structural
drawing. Price includes cutting, bending,
placing in position and tying wires,concrete
spacers and chairs;
a) 8mm diameter deformed bar Kg 490.87 150.00
b) 10mm diameter deformed bar Kg 269.44 150.00
c) 12mm diameter deformed bar Kg 429.07 150.00
d) 14mm diameter deformed bar Kg 1,470.40 150.00
3. MASONRY WORK
3.1 500mm thick trachytic or equvalent stone
masonry wall below ground level bedded in
cement mortar (1:3) in full joints. M3 165.88 3,200.00
3.2
500mm thick trachytic or equivalent well
dressed stone masonry above ground level
bedded in cement mortar (1:3) in full joints.
Price shall include pointing. M3
3.3
Masonry for steps and Ramps.Price include
pointing and other necessary activities.
M3
4.Expansion joint
4.01 8 mm thick chipwood depth 10 cm between
grade beam and floor slab painted two coats
of Asphalt paint m
TOTAL CARRIED TO SUMMARY………………………............ Birr
B-SUPER STRUCTURE

1. CONCRETE WORK
1.1 Reinforced concrete class C-25(with a 28-day
150mm cube crushing strength of 25MP) with
minimum cement content of 360kg/m3
ordinary portland cement cast into form work
and vibrated around reinforcement bars;
a) In Column M3 13.59 5,000.00
c) In roof Beams M3 7.94 5,000.00
d) In gutter M3 2.87 5,000.00
e) Lintelscut and fix in position sawn structural
Provide, M3 1.08 5,000.00
1.2 timber or steel form work whichever is
appropriate;
a) To Elevation Column M2 54.84 200.00
c) To Roof Beams M 2
83.70 200.00
d) To gutter M2 49.70 200.00
e) Lintels M2 11.57 200.00
1.3 Steel reinforcement bar according to structural
drawing. Price includes cutting, bending,
placing in position and tying wires and concrete
spacers;
a) 6mm diameter deformed bar 0.00 Kg 150.00
b) 8mm diameter deformed bar Kg 1275.10 150.00
c)10mm diameter deformed bar Kg 108.74 150.00
d) 12mm diameter deformed bar Kg 1256.63 150.00
TOTAL CARRIED TO SUMMARY………………………............ Birr
2. BLOCK WORK
2.1 200mm thick class-B HCB wall bedded in
cement mortar mix (1:3) and both sides left for
plastering. HCB quality shall be tested and
approved by the Enginner. M2 158.78 650.00
2.2 Ditto but 150mm thick. M 2
322.77 650.00
2.3 Ditto but 100mm thick for papate wall
M2
TOTAL CARRIED TO SUMMARY………………………............ Birr
3. ROOFING
3.01 Roof cover in G28 C.I.S nailed to Zigba m2
purlins,Price shall include ridge cover and roof
measured in horizontal projection.. 237.37 1,200.00
3.02 Supply and fix 100mm diameter PVC down ml
pipe as per the drawing, price shall include
metal strap1cm width with 28 guage supports
c/c 1000mm, wire strainer and all other
necessary accessories
57.60 600.00
3.03 Sheet metal coping with developmental length ml
of 2.914
39.43 600.00
3.04 Supply and fix wire mesh ventilation under m2
veranda nailed to zigba wood battens size 40 x
50 mm. Price shall include zigba wood battens
with c/c spacing of 600mm both ways, corner
and middle list and all other necessary
accessories.

TOTAL CARRIED TO SUMMARY………………………............ Birr

4. CARPENTRY AND JOINERY


4.01 Supply, assemble and mount Φ 120mm
eucalyptus wooden truss as per the detail
drawing. Price shall include anti termite
treatment ,tie bar of Φ6mm and other necessary
accessories. ml 455.87 40.00
4.02 Supply, assemble and mount Φ 80mm
eucalyptus wooden truss as per the detail
drawing. Price shall include anti termite
treatment ,tie bar of Φ6mm and other necessary
accessories. ml 332.93 40.00
4.03 Supply and fix 50x70 mm Zigba wood purlin as
per the detail drawing . Price shall include anti
termite treatment and all other necessary
accessories. ml 429.75 40.00
4.04 Supply and fix fascia board 250x25mm. Price
includes one coat primer and two coats of oil
paint and other necessary activity needed to
complete the work. ml
4.05 Supply and fix 8 mm thick chip wood ceilings as
per the engineers approval. Price shall include
40 x 50 mm Zigba wood battens with c/c
spacing of 600 mm both ways, middle and
corner list, and all other necessary accessories.
m2 104.46 700.00
4.06 Supplyand fix 20mm thick styrofoam insulating
panels over the chipwood ceiling as indicated
on the drawing m2 104.46 -
4.07 Supply and fix 7 mm thick PVC ceilings as per
the engineers approval. Price shall include
battens with c/c spacing of 600 mm both ways,
middle and corner list, and all other necessary
accessories. 105.30 M2 600.00
TOTAL CARRIED TO SUMMARY………………………............ Birr
5. METAL WORKS
5.1 Metal window and doors made of 38x1.5mm
LTZ profiles shown on the drawings.Price
include approved quality locks and all iron
mongry works, two coats of anti rust, three
coats of synthetic paint, 1mm thick sheet metal
and door stopper. All according to detail
drawing and the approval of the Engineer.
WINDOWS
a) Type W1 = size: 1720x815MM Pcs 10.00 10,000.00
b) Type W2 = size: 1720x1230mm
Pcs 7.00 10,000.00
c) Type W3 = size: 845x1720mm
Pcs 4.00 10,000.00
d) Type W4 = size: 1260x1075mm
Pcs 2.00 10,000.00
e) Type TW1 = size: 815x645mm Pcs 3.00 10,000.00
f) Type TW2 = size:1645x665mm Pcs 1.00 10,000.00
DOORS

a) Type D1 = size: 2150x845mm


Pcs 4.00 12,000.00
b) Type D2 = size: 2795 x 845mm
Pcs 6.00 12,000.00
c) Type D3 = size: 2795 x 845(800x685)mm Pcs 12,000.00
d) Type D5= size: 2795 x 1260mm Pcs 5.00 12,000.00
e) Type D7 = size: 2795 x 1645mm Pcs 1.00 12,000.00
f) Type DW4 = size: 1675X796(830 x175)mm Pcs 1.00 12,000.00
g) Type D8 = size: 700 x 2150mm Pcs
5.13 Ventilation window manufactured from
38x1.2mm LTZ profile frame and chicken
wire mesh. Price shall include one coat of
anti rust and two coats of syntetic enamel
paint Size 845x400mm No
TOTAL CARRIED TO SUMMARY………………………............ Birr

7. FINISHING
7.01 Apply three coats of plastering in cement sand
mortar (1:3). Price shall include pre-cleaning
and preparation of the surface.

a) To internal wall surface m2 106.81 300.00


b) To exposed beams and columns.(internal
/external)
m2 57.40 300.00
7.02 Ditto but two coats to receive ceramic wall tile

m2 94.56 300.00
7.03 8mm thick approved quality of 300*200 94.56 450.00
mmTabor ceramic wall tiles to different rooms
7.04 Apply one coat (3rd Coat) Gypsum plastering
as per the finishing Schadual. Price includes
on cement sand mortar (1:3) plastering . Price
cement mortar backing and joints grouted in
shall include pre-cleaning and preparation of
the surface.
7.05 a) To internal wall surface
m2 372.93 250.00
7.06 b) To internal beams and columns
7.07 Apply one coat (third coat) plastering in cement
sand mortar (1:3) above ceramic walls . Price
shall include pre-cleaning and preparation of
the surface.
7.08 Applyone two coats of plastering and one coat
of tyroline rendering in cement sand mortar
(1:3) to External parapet wall m2 125.34 300.00
7.09 Apply pointing for external HCB wall with
cement sand mortar (1:3)
m2 158.78 300.00
7.10 50 mm thick smooth finished cement sand
screed(1:3) floor finish .All as per engineers
instruction. m2 194.43 200.00
7.11 Supply and cast terrazzo tiles
(200*200mm*20mm) flooring .Price shall
include 48mm thick cement mortar & joints
grouted work with white cement and material
to provide slope if needed , polishing to make
the surface smooth all as per the detail drawing m2 140.72 500.00
7.12 100x20mm terrazo tile skirting stuck to wall
with cement mortar (1:3)mix. And chamfered at
the edge
ml 164.86 500.00
7.13 Supply and fix 200x200x6mm thick Tabor
ceramic floor tiles with cement mortar backing
with 2mm joints to be grouted with white
cement. m2 4.70 500.00
7.14 supply and fix the window sill is granite with
3cm thickness ,chamfered at the edge,with
dripping groove and sloped outside and
bedded on cement mortar) to HCB wall
ml 25.10 500.00
7.14 Supply & fix approved PVC tiles flooring stuck
to cement screed of sizes 300x300x2mm
asbesotos free hard improted (made in England
or Italy) with approved adhesive.very light
green
m2 63.92 500.00
7.14 100x2mm imported plastic tile skirting stuck to
wall with approved type adhesive glue. brown ml
color) 57.68 500.00
7.14 1000mm wide and 80mm thick C-20 pre-cast
concrete pavement around the building bedded
on 100mm thick sand/red ash base and joint
pointed in cement and sand mortar mix 1:3.
Price includes the sand/red ash base & pointing
all as per the detail dawings.

m2 97.51 500.00

TOTAL CARRIED TO SUMMARY………………………............ Birr


8. GLAZING
8.01
Supply and fix 4 mm thick frosted glass to windows
and doors according to the drawing .Price shall
include putty and all the necessary fixing accessories.
m² 60.00 1,500.00
8.01

Supply and fix 4 mm clearglass to Internal windows


according to the drawing .Price shall include putty
and all the necessary fixing accessories.


TOTAL CARRIED TO SUMMARY………………………............ Birr
9. PAINTING
9.01 Apply three coats of synthetic emulsion paint to
internal plastered wall surface.as per Engineers
and client selaction and Approval
m² 106.81 90.00
9.02 Ditto but to external pointed wall surface m² 158.78 90.00
9.03 Ditto but to chip wood ceiling.
m² 104.46 90.00

TOTAL CARRIED TO SUMMARY………………………............ Birr

10. SANITARY INSTALLATION

INTERNAL
10.01 Supply and install Galvanized Steel Pipes
for cold water distribution to all sanitary
fixtures according to the drawing complete
with the necessary pieces such as tees,
bends,unions, etc. The unit price shall
include all necessary assistance to the
installation works such as supports for
horizontal & vertical pipes, chiseling of
walls, slabs, beams, floors, etc. and closing
them with concrete or cement mortar to
normal
Diametercondition.
15 mm The installation shall be m.l 47.00 700.00
tested at a pressure of 10 kg/scm at the
expense of the contractor.
Diameter 20 mm m.l 7.00 700.00
Supply & fix Gate Valves of approved
10.02
quality complete with unions, hand wheels
etc. 700.00
Diameter 15 mm No. 23.00 700.00

Diameter 20 mm No. 1.00 700.00


SANITARY FIXTURES & FITTINGS 700.00
10.03 Supply & fix Tabor ceramic hand wash
basins made from white vitreous china
complete with concealed fixing bracket,
plugs, chains smell traps, flexible pipe cold
water taps, adapters, etc. 700.00
Supply & fix Tabor ceramic W.C. made
Size
from405*500 mm china complete with all No.
white vitreous 3.00 700.00
10.04 acessories including white plastic seat and
cover, with white vitreous china Low flush
cistern and lid, fixing devices, flexible pipes
,adaptors etc. No 1.00 700.00
10.05
Supply & fix enamaled cast iron shower try
completed withcrome plated arm valve and
adjustable shower head No 1.00 700.00
10.06
Supply and fix laundry basin made of
granila complete with smell trap water tap
and other accessories 700.00

Size 500 x 1000 mm


No 3.00 700.00
10.07
Supply and fix floor drains made of
enameled cast iron with smell trap complete
with all the accessories. 700.00

Diameter
Supply &50fixmmdouble bowl stain less steel No. 7.00 700.00
10.08 Laboratory sink complete with all
accessories including a drained removable
strainer, chrome plated hot and cold water
mixing taps. No. 2.00 700.00
10.09 Supply and fix electric water heater
complete with all water proofing mounting
& fastening material heat insulation safety
& return valves & accessories 700.00

50 liters
No 2.00 700.00
10.10
Supply & fix crystal glass mirrors
500x400mm complete with chrome plated
brass clips & screws
No. 1.00 700.00
10.11
Supply & fix Tabor ceramic toilet paper
holder complete with fixing screws and all
accessories
No. 1.00 700.00
Supply & install soil waste and vent pipe in
10.12 horizontal branches and vertical stacks
Supply
made of andrigid
fix 10mm
plasticreinforcement
pipes (PVC) bar of
as
towel rail, embed in wall with
approved standard including all ncessary cement
mortar,
fitting, length
such 60cm
as bends Y.T clean outs, No. 3.00 700.00
10.13 increasing and reducing pieces with tight
joints as shown on the drawong. All
Supply
horizontal& branches
fix Taborshall
ceramic soapinholders
be laid a slope
complete with fixing accessories
of 2%. The unit price shall include all No. 3.00 700.00
10.14 necessary masonry assistance such as
chiseling of walls.slabs, beams floor etc.
and closing them with concrete or cement
mortar. 700.00

Diameter 50 mm m.l. 35.00 700.00

Diameter 100 mm m.l. 8.00 700.00


10.15
Supply & install vent caps of rigid PVC to
be connected to the roof terminal of vent
pipe. 700.00

Diameter 50 mm No. 1.00 700.00

Diameter 100 mm No. 1.00 700.00


10.16
Supply & fix approved quality of
fireextinguisher to be mounted on thewall
size 9kg.
700.00
No. 1.00 700.00

TOTAL CARRIED TO SUMMARY………………………..........


700.00

11. ELECTRICAL INSTALLATION

All distribution boards, breakers, switches, 700.00


accessories etc, should be genuine legrand,
ABB, siemens or approved equivalents
complying with IEC standards distribution
boards, should be made of sheet metal (PVC
Boards) and have separate neutral and
ground bus bars/phase bars. All units in the
distribution boards should be labeled to give 700.00
11.01 the reference
Flush mountedand dutydistribution
main of the unit.IPD in

sheet steel enclosure with lockable door.


Bus bar rating of 50A/3ph, Earthling lead
and with all its accessories and enough
ample space for future expansion consisting
of:- 700.00
1pc m.c.b of 25A/1ph
700.00
5pcs m.c.b of 16A/1ph
700.00
4pcs m.c.b of 10A/1ph
No 1.00 700.00
11.02 Flush mounted main distribution CMDB in
sheet steel enclosure with lockable door.
Bus bar rating of 50A/3ph, Earthling lead
and with all its accessories and enough 700.00
ample space for future expansion consisting
of:-
1pc m.c.b of 63A/3ph
700.00

4pcs m.c.b of 25A/1ph


700.00

2pcs m.c.b of 16A/1ph


No 1.00 700.00

LIGHT POINT
700.00
Surface mounted light point fed through
11.02
PVC insulated copper conductor of 3x2.5
sg.mm inside PVC conduit of 13mm No
diameter including junction boxes with
29.00 700.00
covers, insulating screw caps etc.

LIGHTING FITTINGS
700.00
11.03
Philips TCS 098/236 2xTLD36W ML No
5.00 700.00
11.04
Philips TMX 204 1 x 36W IC No
13.00 700.00
11.05
RZB 20116.00X.Q No
7.00 700.00
11.06
RZB 23270.002 No
3.00 700.00
11.07
RZB 56120.00X + RZB 05-5615 + 60W
No
Lamp
1.00 700.00

SOCKET OUTLETS
700.00
Socket outlet of 16A/1ph, LEGRANDE
11.08
74131 + frame 10921, fed through PVC
sheathed flexible wire of 1x2.5 Sq.mm No
inside DLT Trunking LEGRAND 10412
25.00 700.00
80x50mm. All for surface mounting.

TELEPHONE POINT
700.00
11.09
Telepone point fed through PVC sheathed
copper wire 2x0.80 inside pvc condit of No
mimimum diameter 19mm
1.00 700.00
11.10
Telephone box 300x200x80mm No
1.00 700.00

EARTHING SYSTEM
700.00
11.11 Copper grouding rod of 1.5mt long and
120mm diameter tape furse or approved
Pcs
driven down to ground in a grounding
manhole as shown in detai drawing 1.00 700.00
11.12
Base copper wire of 10 Sq.mm ML
5.00 700.00
Construct manhole with brick wall 250mm
11.13
thick on mass concrete bed of 100mm thick
with inside walls to be platered in too cats No
of mortar with reinforced concrete slab of
1.00 700.00
60mm thick

SUPPLY POWER
700.00
11.14
Supply power from VIP-T-TO Bath Heater
through 3x2.5sq.mm PVC sheathed power Mt
cable
25.00 700.00
11.15
Supply power from CMDB TO VIP-SH
Mt
3x4sq.mm PVC sheathed power cable
20.00 700.00
11.16
Supply power from CMDB TO OPD
Mt
3x6sq.mm PVC sheathed power cable
15.00 700.00

Supply power from CMDB TO IPD


11.17 Mt
3x6sq.mm PVC sheathed power cable
5.00 700.00
11.18
Supply power from CMDB TO VIP-LA
Mt
3x4sq.mm PVC sheathed power cable
20.00 700.00
11.19
Supply power from CMDB TO WAR
Mt
3x4sq.mm PVC sheathed power cable
20.00 700.00
11.20
Supply power from CMDB TO PTO
Mt
3x4sq.mm PVC sheathed power cable
20.00 700.00

TOTAL CARRIED TO SUMMARY..............


3,196,137.80
Amount

Amount

2,567.80

22,738.68
3,031.82

0.00

7,798.50

8,838.30

12,150.00

13,770.00

7,276.38

0.00

0.00

8,544.26

66,107.02
0.00
0.00

0.00
194.43
9,000.00
33,367.50

19,398.00

0.00
22,500.00
8,355.00
116,786.25
2,308.50
972,162.00
1,802.28

0.00

2,880.00
6,684.00
29,363.40
229.50
147.75

0.00
73,631.16
40,415.57
64,361.17
220,560.07
0.00

530,803.20

0.00

0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
67,968.00
39,690.00
14,336.25
5,376.00

0.00
10,967.04
16,739.64
9,939.80
2,313.60

0.00
0.00
191,264.51
16,311.01
188,493.98
0.00
0.00

103,206.07
209,803.74
0.00
0.00
0.00

284,844.00

34,560.00

23,658.00

0.00
0.00
0.00
0.00

0.00
18,234.80

13,317.12

17,190.00

0.00

73,121.25

0.00

63,180.83
0.00
0.00

0.00
0.00
100,000.00

70,000.00

40,000.00

20,000.00
30,000.00
10,000.00
0.00

48,000.00
72,000.00
0.00
60,000.00
12,000.00
12,000.00
0.00

0.00
0.00
0.00
0.00

0.00
32,044.05

17,218.80

28,368.11
42,552.17

0.00

93,232.52
0.00

0.00

37,602.98

47,633.57

38,886.48

70,358.91

82,430.00
2,348.18

12,550.00

31,959.35

28,837.50

48,756.00
0.00
0.00
0.00

90,001.20

0.00
0.00
0.00

9,613.22
14,290.07

9,401.30

0.00

0.00

0.00
0.00
32,900.00

4,900.00

0.00
16,100.00

700.00
0.00

0.00

2,100.00

700.00

700.00

0.00

2,100.00

0.00

4,900.00

1,400.00
0.00

1,400.00

700.00

700.00

2,100.00

2,100.00

0.00

24,500.00

5,600.00

0.00

700.00

700.00

0.00
700.00

0.00

0.00

0.00

0.00

0.00

0.00

700.00

0.00

0.00

0.00

700.00

0.00
20,300.00

0.00

3,500.00

9,100.00

4,900.00

2,100.00

700.00

0.00

17,500.00

0.00

700.00

700.00

0.00
700.00

3,500.00

700.00

0.00

17,500.00

14,000.00

10,500.00

3,500.00

14,000.00

14,000.00

14,000.00

5,183,372.60
8,379,510.40
1,256,926.56
9,636,436.96
TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
A.SUB STRUCTURE
1. Excavtion and earth work
1.1 clear off site to remove top soil
L=29.97+pavement
w=8.26+pavement
L=29.97+(1.2x2)+0.025*2
w=8.26+(1.2x2)+0.025*2
L=32.87m
1 32.87 W=11.16m
11.16 depth 0.20m
366.83 Total

1.2 Pit excavation in ordinary soil to a depth not


exceeding 1500mm from reduced ground level.
18 1.5
1.5
1.5
60.75
1.2 Pit excavation in ordinary soil to a depth
exceeding 1500mm from reduced ground level.
18 1.5
1.5
1.7
68.85

1.3 Trench excavationin ordinary soil to a depth


not exceeding 1500mm from reduced ground level.
on axsis X01-X03
6 6.06
0.5
1.5
27.27
on axsis Y01-Y06

3 22.54
0.5
1.5
50.72
77.99

1.3 Trench excavationin ordinary soil to a depth


exceeding 1500mm from reduced ground level.
on axsis X01-X03
6 6.06
0.5
1.7
30.91
on axsis Y01-Y06
3 22.54
0.5
1.7
57.48
88.38
1.4 Bulk Excavation in ordinary soft to a depth not
excedding 1.5m
L=27.54+pavement +working space

Prepared by: ......................................... Approved by: ......................................... 25 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
W=7.06+pavement +working space
L=27.54+(1.2x2)+(0.25x2)
W=7.06+(1.2x2)+(0.25x2)
L=30.44m
W=9.96m
1 30.44 d=1.5m
9.96
1.5
454.77 Total volume
1.4 Ditto but excedding 1.5m a depth 0.78m
1 30.44 L=30.44m
9.96 W=9.96m
0.1
30.32 Total volume
1.5 Selected Borrowed fill material
1 30.44 depth 0.4m
9.96 L=30.44m
1.2 W=9.96m
363.82 Total volume
1.6 cartway surplus excvate material to
appropriate disance
sum of item 1.1+1.2+1.3+1.4
1 854.43
854.43

1.7 250mm thick basaltic or equivalent hardcore


1 27.54 L=27.54m
7.06 W=7.06m
194.43
2. Concrete Works
50 mm C-5 lean concrete, minimum cement
content 150 kg/m3 Under,
3 28.47 a) under grade beam
0.5 on axis X/01-X/05
42.71
6 8.01
0.5 ditto but on axis y/01-y/08
24.03
66.74 Total
b) under footing pad
18 1
1
18.00

2.2 10cm thick reinforcement concrete floor slab


194.43 m2
2.3 Reinforcement concrete C-25
6 8.01 a) In under ground grade beam
0.4 on axis X/01-X/03
0.25
4.81
3 28.47 ditto but on axis y/01-y/06
0.4
0.25
8.54
6 8.01 b) In grade beam

Prepared by: ......................................... Approved by: ......................................... 26 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
0.5 on axis X/01-X/03
0.15
3.60
3 28.47 ditto but on axis y/01-y/06
0.5
0.15
6.41
23.36 Total Volume
18 1.0 b) In footing pad
1.0
0.25
4.50 Total
12 2.5 c) In foundation column
0.2
0.2
1.20
6 2.5 area =3.14*0.1*0.1=0.0314
0.0314
0.47
1.67 Total Volume

C) Stair
2.5 0.30
0.15
1.2 0.13

1 0.11
1.073
1.2 0.14

1 0.11
1.402
1.2 0.19
0.46

D) Ramp
1 0.12
2.612
1.2 0.36
0.36

2.4 Form works


12 8.01 a) To under ground grade beam
0.4 on axis X/01-X/03
38.45
6 28.47
0.4 on axis y/01-y/06
68.33
b) To ground grade beam
12 8.01 on axis X/01 and X/03
0.15
14.42
6 28.47
0.15 on axis y/01 and y/06
25.62
146.82 Total
72 1 b) To footing pad

Prepared by: ......................................... Approved by: ......................................... 27 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
0.2
14.40 Total
COLUMN
48 2.5
0.2
24.00
Area =2*3.14*0.1
6 2.5
0.628
9.42
33.42
C) STAIR
2 2.475
0.15 0.74

5 0.3
0.15 0.22

4 0.3
0.15 0.18
1.15
d) Ramp
2 2.612
0.115 0.60

1 1.2
0.115 0.14
0.74
2.04 Mild steel reinforcement

a) Dia. 6mm plain bar


- 0.00 See annexed rebar schedule sheet
0.00 kg

b) Dia. 8mm deformed bar


490.87 490.87 See annexed rebar schedule sheet
490.87 kg

c) Dia. 10mm deformed bar


269.44 269.44 See annexed rebar schedule sheet
269.44 kg

d) Dia. 12mm deformed bar


429.07 429.07 See annexed rebar schedule sheet
429.07 kg

d) Dia. 14mm deformed bar


1,470.40 1,470.40 See annexed rebar schedule sheet
1,470.40 kg

10x100mm styropor foam expansion joint filler between Grade


beam and floor slab.
10 8.01 80.1 a)b/n grade beam and floor slap
on axis X/01-X/03

4 28.47 113.88 ditto but on axis y/01-y/06

193.98 ml
3. MASONRY WORKS

Prepared by: ......................................... Approved by: ......................................... 28 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

3.01 50cm thick masonry foundation


138.23 Depth of masonry=1.2 m
1.2 165.88

Prepared by: ......................................... Approved by: ......................................... 29 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
165.88 m 3

B - SUPER STRUCTURE

1. CONCRETE WORKS
Ht. of column=3.2m
Size of column=0.20m x 0.20m
No. of columns=12
12 3.2
0.2 1.01 C-20 RC:
0.2 1.54 a) In elevation columns
m3
Area =2*3.14*0.1=0.628
6 3.2
0.628
12.06
13.59
CL length of roof beam (half block)=
(29.979-(6*0.2))*3+(8.26-(0.2*3))*6
132.30 b) In roof beams
0.2
0.3 7.94
7.94 m3

b) In lintels
26.88 Tot. L=7*(.815+2*0.2)+3*(0.815+2*0.2)+
0.2 7*(1.23+2*0.2)+2*(1.26+.2*2)=26.88m
0.2 1.08

b) Ingutter
1 38.23
0.5
0.15
2.87 m3
1.02 Formwork:

a) To elevation columns & lintels

12 3.200 (Permtr=4*0.2=0.80m)
0.8 30.72 To columns

12 3.200 (permiter=2*3.14*0.1)
0.628 24.12
54.84
19.28
0.6 11.57 To lintels
11.57 m2
b) To roof beams

6 29.979
0.3 53.96

12 8.26
0.3 29.74
83.70
C) in gutter
2 38.23
0.65
49.699
1.03 Mild steel reinforcement

Prepared by: ......................................... Approved by: ......................................... 30 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

a) Dia. 6mm plain bar


0.00 0.00 See annexed rebar schedule sheet
0.00 kg

b) Dia. 8mm plain bar


1,275.10 1,275.10 See annexed rebar schedule sheet
1,275.10 kg

c) Dia. 10mm deformed bar


108.74 108.74 See annexed rebar schedule sheet
108.74 kg

d) Dia. 12mm deformed bar


1,256.63 1,256.63 See annexed rebar schedule sheet
1,256.63 kg

2. BLOCK WORK

2.01 200mm thick class C HCB

Total Length=2*(29.979+6.21)-(16*0.2)
69.178 =69.178m
3.2 221.37 Gross area

-2 2.23
3.2 -14.27 Deduct corridor opening

-1 1.645
2.795 -4.60 Deduct D7door opening

-1 2.11
2.795 -5.90 Deduct string curtain opening

-2 0.845
2.795 -4.72 Deduct D2L door opening

-3 0.815
0.665 -1.63 Deduct TW1 window opening

-1 1.645
0.665 -1.09 Deduct TW2 window opening

-7 0.845
1.72 -10.17 Deduct W1L window opening

-7 1.26
1.72 -15.17 Deduct W2 window opening

-3 0.845
1.72 -4.36 Deduct W1R window opening

-2 0.845
0.4 -0.68 Deduct VW1 window opening

158.78 m2

2.02 150mm thick class C HCB


L (X direction)=2.24+3.47+3.91+
2.405+2.42+2.075+1.144=17.664m

Prepared by: ......................................... Approved by: ......................................... 31 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
L (Y direction.)=8*(6.21-2*0.2)+4.03=50.53m
Total L.=68.19m
68.19 Height=3.2
3.3 225.03 Gross area

Prepared by: ......................................... Approved by: ......................................... 32 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
-3 1.26
2.795 -10.57 Deduct D5L door opening

-2 0.845
2.1 -3.55 Deduct D1L door opening

-2 1.26
2.795 -7.04 Deduct D5R door opening

-2 0.845
2.15 -3.63 Deduct D1R door opening

-2 0.845
2.795 -4.72 Deduct D2R door opening

-2 0.845
2.795 -4.72 Deduct D2L door opening

-2 1.26
1.075 -2.71 Deduct W4 window opening

-1 0.845
2.795 -2.36 Deduct DW4R (door side) opening

-1 0.83
1.7505 -1.45 Deduct DW4R (win. side) opening

2 8.86 Paraphet wall


1.756 31.12

2 30.579
1.756 107.39
322.77 m3

3. ROOFING
3.01 G28 CIS roof cover

A1=(29.791+18.689)/2*3.856*2=186.93
A2=1/2*(8.26*6.095)*2=50.344
237.37 237.37
237.37 m2

3.04 Sheet metal coping with developmental length of 2.914


39.43 39.43 L=2*(29.97+.6+8.26+.6)=39.43m
39.43 ml
3.05 PVC down pipe

12 3.6 43.2 Front

4 3.6 14.4 Rear


57.60 ml

4. CARPENTRY & JOINERY


Truss(T1 and T2)
455.87 Dia 120cm eucal,(bot.+toP.)=455.87
455.87

332.928 Dia 80cm eucal,(v.+diag.)=332.928


332.928

Prepared by: ......................................... Approved by: ......................................... 33 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
4.02 50x70 mm zigba wood purlin
429.75 429.75
429.75 ml
4.04 plastic ceiling
2.24
2.04 4.57 Toilet

2.24
3.62 8.11 Preparation

3.91
4.03 15.76 Delivery

2.405
1.875 4.51 Sluice room

2.42
3.385 8.19 Washing

1.165
2.34 2.73 Sluice

29.97
2.05
61.44 Covered walk way

105.30
4.04 8mm thick chip wood ceiling
3.47
4.08 14.16 Labor

7.53
1.63 12.27 Corridor, X-direction

2.435
3.785 9.22 Sterilization

2.42
2.275 5.51 Ironing

3.355
5.81 19.49 Male ward

2.075
3.28 6.81 Nurse station

1.675
2.58 4.32 Entry hall

4.96
5.81 28.82 Female & pediatric ward

1.165
3.32 3.87 Janitors' room

104.46 m2

4.05 20mm thick styrafoam insulating


panels over the chip wood ceiling

Prepared by: ......................................... Approved by: ......................................... 34 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
104.46 m (same as Item 4.04)
2

5. METAL WORK
WINDOWS

7 1 7 5.01 W1L size: 815X1720mm


7.00 No.

3 1 3 5.02 W1R size: 815x1720mm


3.00 No.

7 1 7 5.03 W2 size: 1230X1720mm


7.00 No.

2 1 2 5.03 W4 size: 1260X1720mm


2.00 No.
DOORS

2 1 2 5.04 D1L size: 845x2150 mm


2.00 No.

2 1 2 5.05 D1R size: 845x2150 mm


2.00 No.

4 1 4 5.06 D2L size: 845x2795 mm


4.00 No.

2 1 2 5.07 D2R size: 845x2795mm


2.00 No.

1 1 1 5.07 DW4R size: 1260x2795mm


1.00 No.

3 1 3 5.08 D5L: 1260x2795mm (BOQ Des.Q Diff.)


3.00 No.

5.09 D5R: 1260x2795mm (BOQ Des. Diff.)


2 1 2 (Door closing by fixed springs)
2.00 No.

1 1 1 5.10 D7 size: 1675x2795mm (D7 in dwg)


1.00 No.

TOP WINDOWS (Glass Louver)

3 1 3 5.11 TW1 size: 845X645mm


3.00 No.

1 1 1 5.12 TW2 size: 1675X645mm


1.00 No.

2 1 2 5.13 Vent. window: Size 845x400mm


2.00 No.

7. FINISHING

7.01 1st and 2nd cement plaster 3rd gypsum plastering to internal
wall
Height=3.2+0.3=3.5m

2 7.55

Prepared by: ......................................... Approved by: ......................................... 35 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
3.5 52.85 Labor

-2 0.815
2.15 -3.50 Deduct D1L opening (815x2150 mm)

5.115 Perimeter=0.815+2*2.15=5.145m
0.15 0.77 Add D1L int. per. opening (845x2150 mm)

-1 1.23
1.72 -2.12 Deduct W2 opening (1230x1720mm)

5.96 Perimeter=2*(1.23+1.72)=5.96m
0.2 1.19 Add W2 int. per. opening (1260x1720mm)

-1 1.26
2.795 -3.52 Deduct D5L opening (1260x2795 mm)

6.85 Perimeter=1.26+2*2.795=6.85m
0.15 1.03 Add D5L int. per. opening (1260x2795 mm)

2 9.06
3.5 63.42 Corridor, front

-2 1.26
2.795 -7.04 Deduct D5L opening (1260x2795 mm)

-1 1.26
2.795 -3.52 Deduct D5R opening (1260x2795 mm)

3 6.85 Perimeter=1.26+2*2.795=6.85m
0.15 3.08 Add D5R int. per. opening (1260x2795 mm)

-1 0.815
2.15 -1.75 Deduct D1R opening (815x2150 mm)

5.115 Perimeter=0.815+2*2.15=5.115m
0.15 0.77 Add D1R int. per. opening (845x2150 mm)

-1 1.645
2.795 -4.60 Deduct D7 (D7-BOQ) op. (1645x2795 mm)

7.235 Perimeter=1.645+2*2.795=7.265m
0.2 1.45 Add D6/D7 int. per. Op. (1675x2795mm)

-1 0.815
0.665 -0.54 Deduct TW1 opening (815X665mm)

2.96 Perimeter=2*(0.815+0.665)=2.98m
0.2 0.59 Add TW1 int. per. (845X645mm)

-1 1.645
0.665 -1.09 Deduct TW2 opening (1645X665mm)

4.62 Perimeter=2*(1.645+0.665)=4.62m
0.2 0.92 Add TW2 int. per. (1675X645mm)

2 6.22
3.5 43.54 Sterilization

-1 0.845
2.15 -1.82 Deduct D1R opening (845x2150 mm)

Prepared by: ......................................... Approved by: ......................................... 36 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

-1 0.845
2.795 -2.36 Deduct D2R opening (845x2795 mm)

6.435 Perimeter=0.845+2*2.795=6.435m
0.15 0.97 Add D2R int. per. opening (845x2795 mm)

-1 0.815
1.72 -1.40 Deduct W1L opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.13m
0.2 1.01 Add W1L int. per. opening (845X1720mm)

2 4.695
3.5 32.87 Ironing

-1 0.845
2.795 -2.36 Deduct D2L opening (845x2795 mm)

6.435 Perimeter=0.845+2*2.795=6.435m
0.15 0.97 Add D2L int. per. opening (845x2795 mm)

-1 1.23
1.72 -2.12 Deduct W2 opening (1230x1720mm)

5.9 Perimeter=2*(1.23+1.72)=5.96m
0.2 1.18 Add W2 int. per. opening (1260x1720mm)

2 9.165
3.5 64.16 Male ward

-1 0.815
1.72 -1.40 Deduct W1R opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1R int. per. opening (845X1720mm)

-1 0.815
1.72 -1.40 Deduct W1L opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1L int. per. opening (815X1720mm)

-1 1.26
1.075 -1.35 Deduct W4 opening (1260x1075mm)

4.67 Perimeter=2*(1.26+1.075)=4.67m
0.15 0.70 Add W4 int. per. opening (1260x1075mm)

-1 1.26
2.795 -3.52 Deduct D5L opening (1260x2795 mm)

6.85 Perimeter=1.26+2*2.795=6.85m
0.15 1.03 Add D5L int. per. opening (1260x2795 mm)

-1 1.23
1.72 -2.12 Deduct W2 opening (1230x1720mm)

5.9 Perimeter=2*(1.23+1.72)=5.9m
0.2 1.18 Add W2 int. per. opening (1260x1720mm)

Prepared by: ......................................... Approved by: ......................................... 37 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
2 5.355
3.5 37.49 Nurse station

-2 1.26
1.075 -2.71 Deduct W4 opening (1260x1075mm)

4.67 Perimeter=2*(1.26+1.075)=4.67m
0.15 0.70 Add W4 int. per. opening (1260x1075mm)

-1 0.815
1.72 -1.40 Deduct W1L opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1L int. per. opening (845X1720mm)

-1 0.845
2.795 -2.36 Deduct DW4R (door side) door opening

3.64 Perimeter=0.845+2.795=3.64m
0.15 0.55 Add DW4R int. per. Op. (845X2795mm)

-1 0.83
1.7505 -1.45 Deduct DW4R (win. side) door opening

3.4105 Perimeter=2*0.83+1.7505=3.4105m
0.15 0.51 Add DW4R int. per. Op. (830X1750.5mm)

2 4.255
3.5 29.79 Entry hall

-1 1.26
2.795 -3.52 Deduct D5L opening (1260x2795 mm)

-1 0.845
2.795 -2.36 Deduct DW4R (door side) door opening

-1 0.83
1.7505 -1.45 Deduct DW4R (win. side) door opening

-1 1.26
2.795 -3.52 Deduct D5R opening (1260x2795 mm)

6.85 Perimeter=1.26+2*2.795=6.85m
0.15 1.03 Add D5R int. per. opening (1260x2795 mm)

-1 2.075
3.5 -7.26 Deduct string curtain opening

2 10.77
3.5 75.39 Female & pediatric ward

-1 1.26
2.795 -3.52 Deduct D5R opening (1260x2795 mm)

6.85 Perimeter=1.26+2*2.795=6.85m
0.15 1.03 Add D5R int. per. opening (1260x2795 mm)

-1 1.26
1.075 -1.35 Deduct W4 opening (1260x1075mm)

-1 0.815

Prepared by: ......................................... Approved by: ......................................... 38 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
1.72 -1.40 Deduct W1R opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1R int. per. opening (845X1720mm)

-1 0.815
1.72 -1.40 Deduct W1L opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1L int. per. opening (845X1720mm)

-1 1.23
1.72 -2.12 Deduct W2 opening (1230x1720mm)

5.9 Perimeter=2*(1.23+1.72)=5.9m
0.2 1.18 Add W2 int. per. opening (1260x1720mm)

2 4.485
3.5 31.39 Janitors' room

-1 0.815
1.72 -1.40 Deduct W1R opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1R int. per. opening (815X1720mm)

-1 0.845
2.795 -2.36 Deduct D2L opening (845x2795 mm)

6.435 Perimeter=0.845+2*2.795=6.435m
0.2 1.29 Add D2L int. per. opening (845x2795 mm)

372.93 m2

3rd coat of plastering to internal wall surface


2 4.28
1.7 14.55 Toilet (excl. 1.8m high ceramic wall)

-1 0.815
0.665 -0.54 Deduct TW1 opening (845X645mm)

2.98 Perimeter=2*(0.845+0.645)=2.98m
0.2 0.60 Add TW1 int. per. (845X645mm)

-1 0.845 (Ht. for above the ceramic wall tile)


0.35 -0.30 Deduct D1L opening (845x2150 mm)

5.115 Perimeter=0.815+2*2.15=5.145m
0.15 0.77 Add D1L int. per. opening (845x2150 mm)

2 5.86 (excl. 1.8m high ceramic wall)


1.7 19.92 Preparation

-1 0.815 (excl. 1.8m high ceramic wall)


0.995 -0.81 Deduct W1L opening (845X1720mm)

5.07 Permtr=2*(0.815+(1.72)=5.07m
0.2 1.01 Add W1L int. per. opening (845X1720mm)

-1 1.26
1.145 -1.44 Deduct D5L opening (1260x2795 mm)

Prepared by: ......................................... Approved by: ......................................... 39 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

6.85 Perimeter=1.26+2*2.795=6.85m
0.15 1.03 Add D5L int. per. opening (1260x2795 mm)

-1 0.815
0.665 -0.54 Deduct TW1 opening (845X645mm)

2.96 Perimeter=2*(0.815+0.665)=2.96m
0.2 0.59 Add TW1 int. per. (845X645mm)

2 7.99 (excl. 1.8m high ceramic wall)


1.7 27.17 Delivery

-1 0.815 (excl. 1.8m high ceramic wall)


0.35 -0.29 Deduct D1L opening (815x2150 mm)

-2 1.23 (excl. 1.8m high ceramic wall)


0.995 -2.45 Deduct W2 opening (1230x1720mm)

2 4.51 Permtr=2*(1.26+(1.075+1.72-1.8))=4.51m
0.2 1.80 Add W2 int. per. (1260X1720mm)

-1 0.815 (excl. 1.8m high ceramic wall)


0.35 -0.29 Deduct D1R opening (815x2150 mm)

5.115 Perimeter=0.815+2*2.15=5.115m
0.15 0.77 Add D1R int. per. opening (845x2150 mm)

-1 1.26 (excl. 1.5m high ceramic wall)


0.995 -1.25 Deduct D5R opening (1260x2795 mm)

2 4.275 (excl. 1.8m high ceramic wall)


1.7 14.54 Sluice room

-1 0.815 (excl. 1.8m high ceramic wall)


0.35 -0.29 Deduct D1R opening (815x2150 mm)

-1 0.815 (excl. 1.8m high ceramic wall)


0.995 -0.81 Deduct W1L opening (815X1720mm)

5.07 Perimeter=2*(0.815+1.72)=5.07m
0.2 1.01 Add W1L int. per. opening (815X1720mm)

-1 0.815 (excl. 1.8m high ceramic wall)


0.995 -0.81 Deduct D2R opening (815x2795 mm)

6.405 Perimeter=0.815+2*2.795=6.435m
0.15 0.96 Add D2R int. per. opening (845x2795 mm)

2 5.805 (excl. ceramic wall tile Ht.)


1.7 19.74 Washing

-1 0.845 (excl. ceramic wall tile Ht.)


0.995 -0.84 Deduct D2L opening (845x2795 mm)

6.435 Perimeter=0.845+2*2.795=6.435m
0.15 0.97 Add D2L int. per. opening (845x2795 mm)

-1 1.23 (excl. ceramic wall tile Ht.)


0.995 -1.22 Deduct W2 opening (1230x1720mm)

Prepared by: ......................................... Approved by: ......................................... 40 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
4.45 Perimeter=2*(1.23+(1.075+1.72-1.8))=4.45m
0.2 0.89 Add W2 int. per. opening (1260x1720mm)

2 3.505 (excl. ceramic wall tile Ht.)


1.7 11.92 Sluice

-1 0.845 (excl. ceramic wall tile Ht.)


0.995 -0.84 Deduct D2L opening (845x2795 mm)

6.435 Perimeter=0.845+2*2.795=6.435m
0.2 1.29 Add D2L int. per. opening (845x2795 mm)

-1 0.845 (excl. ceramic wall tile Ht.)


0.995 -0.84 Deduct W1L opening (845X1720mm)

4.28 Perimeter=2*(0.845+(1.075+1.72-1.5)=4.28m
0.2 0.86 Add W1L int. per. opening (845X1720mm)

106.81

To exposed beam
76.46
0.6 45.876 m2

To exposed column
18 0.2
3.2 11.52 m2
57.396
7.02 Ditto but two coats to receive
2 4.28 ceramic wall tile (to 1.5m height)
1.8 15.41 In toilet

-1 0.845
1.8 -1.52 Deduct D1L opening (845x2150 mm)

2 5.86
1.8 21.10 Preparation

-1 0.815
0.725 -0.59 Deduct W1L opening (815X1720mm)

-1 1.26
1.8 -2.27 Deduct D5L opening (1260x2795 mm)

2 7.99
1.8 28.76 Delivery

-1 0.845
1.8 -1.52 Deduct D1L opening (845x2150 mm)

-2 1.26
0.725 -1.83 Deduct W2 opening (1260x1720mm)

-1 0.845
1.8 -1.52 Deduct D1R opening (845x2150 mm)

-1 1.26
1.8 -2.27 Deduct D5R opening (1260x2795 mm)

2 4.31
1.8 15.52 Sluice room

Prepared by: ......................................... Approved by: ......................................... 41 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

-1 0.845
1.8 -1.52 Deduct D1R opening (845x2150 mm)

-1 0.845
0.725 -0.61 Deduct W1L opening (845X1720mm)

-1 0.845
1.8 -1.52 Deduct D2R opening (845x2795 mm)

2 5.805
1.8 20.90 In washing

-1 0.845
1.8 -1.52 Deduct D2L opening (845x2795 mm)

-1 1.26
0.725 -0.91 Deduct W2 opening (1260x1720mm)

2 3.505
1.8 12.62 Sluice

-1 0.845
1.8 -1.52 Deduct D2L opening (845x2795 mm)

-1 0.845
0.725 -0.61 Deduct W1L opening (845X1720mm)
94.56 m2

7.03 tyroline rendering toparaphet wall

2 37.29
1.756 130.96

16 -0.2 deduct columns


1.756 -5.62

125.34 m2

7.04 Pointing to external HCB

158.8 158.8 To 200mm thich Class C HCB (Item 2.01)


158.78 m2

7.05 Floor finish

50mm thick floor finish


194.43
194.43 m2

2.24 Ceramic tile


2.04 4.57 Toilet(ceramictile)

1 0.845
0.15 0.13 Add under D1L (845x2150x150 mm)
4.70
Pvc tile
2.24
3.62 8.11 Preparation(p)

1 1.26

Prepared by: ......................................... Approved by: ......................................... 42 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
0.15 0.19 Add under D5L (1260x2795x150 mm)

3.355
5.81 19.49 Male ward(p)

1 1.26
0.15 0.19 Add under D5L (1260x2795x150 mm)

2.075
3.28 6.81 Nurse station(p)

1 0.845
0.15 0.13 Add under DW4R (845x2795x150 mm)

4.96
5.81 28.82 Female & pediatric ward(p)

1 1.26
0.15 0.19 Add under D5R (1260x2795x150 mm)

63.92
Terrazo tile
3.47
4.08 14.16 Labor(t)

7.53
1.63 12.27 Corridor, front to rear(T)

3.91
4.08 15.95 Delivery(T)

2.4
1.875 4.50 Sluice room(T)

2.435
3.785 9.22 Sterilization(T)

2.42
3.385 8.19 Washing(T)

2.42
2.275 5.51 Ironing(T)

1.675
2.58 4.32 Entry hall(T)

1.165
3.32 3.87 Janitors' room(T)

1.165
2.34 2.73 Sluice(T)

29.04
1.98 57.50 Covered walkway(T)

1 1.26
0.15 0.19 Add under D5L (1260x2795x150 mm)

1 0.845
0.15 0.13 Add under D1L (845x2150x150 mm)

Prepared by: ......................................... Approved by: ......................................... 43 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
2 0.845
0.15 0.25 Add under D1R (845x2150x150 mm)

1 1.26
0.15 0.19 Add under D5R (1260x2795x150 mm)

1 1.675
0.2 0.34 Add under D7 (1675x2795x200 mm)

2 0.845
0.15 0.25 Add under D2R (845x2795x150 mm)

2 0.845
0.15 0.25 Add under D2L (845x2795x150 mm)

2 0.845
0.2 0.34 Add under D2L (845x2795x200 mm)

3 1.26
0.15 0.57 Add under D5L (1260x2795x150 mm)

140.72 m2
Skirting

Pvc tile

2 5.86 11.72 Preparation(p)

-1 1.26
-1.26 Add under D5L (1260x2795x150 mm)

2 9.165 18.33 Male ward(p)

-1 1.26
-1.26 Add under D5L (1260x2795x150 mm)

2 5.355 10.71 Nurse station(p)

-1 0.845
-0.85 Add under DW4R (845x2795x150 mm)

2 10.77 21.54 Female & pediatric ward(p)

-1 1.26
-1.26 Add under D5R (1260x2795x150 mm)

57.68 ml
Terrazo tile

2 7.55 15.10 Labor(t)

2 9.16 18.32 Corridor, front to rear(T)

2 7.99 15.98 Delivery(T)

Prepared by: ......................................... Approved by: ......................................... 44 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
2 4.275 8.55 Sluice room(T)

2 6.22 12.44 Sterilization(T)

2 5.805 11.61 Washing(T)

2 4.695 9.39 Ironing(T)

2 4.255 8.51 Entry hall(T)

2 4.485 8.97 Janitors' room(T)

2 3.505 7.01 Sluice(T)

2 31.02 62.04 Covered walkway(T)

1 1.26
1.26 Add under D5L (1260x2795x150 mm)

-1 0.845
-0.85 Add under D1L (845x2150x150 mm)

-2 0.845
-1.69 Add under D1R (845x2150x150 mm)

-1 1.26
-1.26 Add under D5R (1260x2795x150 mm)

-1 1.675
-1.68 Add under D7 (1675x2795x200 mm)

-2 0.845
-1.69 Add under D2R (845x2795x150 mm)

-2 0.845
-1.69 Add under D2L (845x2795x150 mm)

-2 0.845
-1.69 Add under D2L (845x2795x200 mm)

-3 1.26
-3.78 Add under D5L (1260x2795x150 mm)

164.86 Ml

7.06 1.2mm thick formed window sill

Winds. (incl. VW, W4, & DW4R) Tot. sill L


=3*0.815+1*1.675+2*0.45+7*0.815+
3*0.815+7*1.23+2*1.26+1*0.83=25.1m
25.1 25.1
25.10 ml

7.07 150x150x6mm thick ceramic wall tile

Prepared by: ......................................... Approved by: ......................................... 45 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches

94.56 94.560375 Same as Item 7.02 (to 1.5m height)


94.56 m2

7.08 1000mm wide & 80mm thick C-20


precast concrete pavement around bldg
(Width of walkway is 1.2m in dwg,
but 1m in BOQ. Dwg's is taken. It'd be
78.6m if 1m is taken)
81.26 CL L of walkway=2*((8.19+2*0.5*1.2)+
1.2 97.51 (29.04+2*0.5*1.2))=79.26m
97.51 m2

8. GLAZING

8.01 4mm thick clear glass


7 0.815
1.72 9.81 To W1L (815x1720mm)

3 0.815
1.72 4.21 To W1R (815x1720mm)

7 1.23
1.72 14.81 To W2 (1230x1720mm)

2 1.26
1.72 4.33 To W4 (1260x1720mm)

4 0.845
1.58 5.34 To D1 (L & R 845x1580mm)

6 0.845
1.58 8.01 To D2 (L & R 845x1580mm)

5 1.26
1.58 9.95 To D5 (L & R 1260x1580mm)

1 1.645
0.56 0.92 To D7 (1645x560mm)

1 0.845
1.56 1.32 To DW4R (door part 845x1560mm)

1 0.83
1.56 1.29 To DW4R (window part 830x1560mm)
60.00 m2

9. Painting

9.01 3 coats of synthetic emulsion paint


to internal wall surface

106.81 106.81 Same as Item 7.01


106.81 m2

9.02 Ditto but to external pointed wall

158.78 158.78
158.78 m2

Prepared by: ......................................... Approved by: ......................................... 46 of 73


TAKE-OFF SHEET

Project: HC Project
Item: IPD block, new design, expansive soil
Date: September 01, 2009
Qty L/W/D Product Description & Sketches
9.03 Ditto but to chip wood ceiling

104.46 104.46
104.46 m2

Prepared by: ......................................... Approved by: ......................................... 47 of 73


IPD block

SUB - STRUCTURE
No of
Drg.No Location Ref No Shape Dia Length No of bar member Dia 6

Footing pad 14 1.20 16 18


undere ground beam
on axis X/01-X/02 10 9.89 3 3
10 8.82 3 3
10 12.00 3 3
8 0.40 144 3
ditto but on axis y/01-y/08 10 8.90 3 6
8 0.40 41 6

Foundation column 12 4.47 6 18


Stirrup 8 0.70 14 12
Stirrup circular 8 0.48 14 6
Grade beam 14 9.89 3 3
on axis X/01-X/03 14 8.82 3 3
14 12.00 3 3
14 12.00 3 3
14 6.57 3 3
14 11.73 3 3
8 1.20 144 3
ditto but on axis y/01-y/08 14 8.90 3 6
14 8.90 3 6
8 1.20 41 6

Stair 12 3.41 9 1
12 2.48 9 1
12 0.57 9 2
12 0.55 9 2
8 1.20 26 1
Ramp 12 2.61 9 1
12 2.33 9 1
8 1.20 14 2
-
Weight per M 0.222
Total weight (kg) 0.00
Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia20 Dia24 236

345.6

89.046
79.407
108
172.8
160.236
98.4

483.192
117.6
40.32
89.046
79.407
108
108
59.13
105.552
518.4
160.236
160.236
295.2

30.726
22.311
10.188
9.9
31.2
23.508
20.97
33.6
1,242.72 436.69 483.19 1,215.21 - - -
0.395 0.617 0.888 1.21 1.578 2.468 3.55
490.87 269.44 429.07 1470.40 0.00 0.00 0.00
IPD block

SUPER - STRUCTURE
No of
Drg.No Location Ref No Shape Dia Length No of bar member Dia 6 Dia 8
Elevation column
12 3.51 6 18
8 0.70 16 12 134.4
stirab Circular 8 0.48 16 6 46.08
Slab
bar1 8 5.67 46 2 521.548
bar2 8 5.69 33 5 938.025
8 5.69 46 1 261.51
bar3 8 1.72 11 5 94.325
bar4 8 6.31 46 1 290.03
bar5 8 5.06 46 1 232.668
Sub merged beam
10 2.24 4 1
10 5.81 4 7
10 1.15 4 1
8 0.64 49 1 31.507

LINTEL
12 1.22 2 10
12 1.62 2 10
12 1.63 2 7
12 2.03 2 7
12 1.66 2 2
12 2.06 2 2

Top tie beam


RB1 12 10.32 3 3
12 9.25 3 3
12 12.00 3 3
12 12.00 3 3
12 6.99 3 3
12 12.00 3 3
8 1.00 144 3 432
RB2 12 9.72 3 6
12 9.72 3 6
8 1.00 41 6 246

- 3,228.09
Weight per M 0.222 0.395
Total weight (kg) 0.00 1275.10
Dia 10 Dia 12 Dia 14 Dia 16 Dia20 Dia24 236

379.512

8.96
162.68
4.6

24.3
32.3
22.82
28.42
6.64
8.24

92.844
83.232
108
108
62.928
108

174.942
174.942

176.24 1,415.12 - - - -
0.617 0.888 1.208 1.578 2.468 3.55
108.74 1256.63 0.00 0.00 0.00 0.00
Origional
It No Description Unit Qty. Unit Rate Amount

SPECIFICATION AND BILL OF QUANTITIES

HEALTH CENTER

OPD BLOCK

A. SUB STRUCTURE

1 Excavation and Earth Works ..........................Birr


2 Concrete Works ............................................ Birr
3 Masonry Works ............................................ Birr

Total A .......... Birr

B. SUPER STRUCTURE

1 Concrete Works ........................................... Birr


2 Blockwork……………….………………… Birr
3 Roofing ……………………………………… Birr
4 Carpentry and Joinery…………………… Birr
5 Metal work ……………………………… Birr
7 Finishing ………………………………… Birr
8 Glazing ……………………………………… Birr
9 Painting…………………………………… Birr
10 Sanitary Installation…………………… Birr
11 Electrical Installation……………….. …… Birr

Total B ………………. Birr

Total A +B for one unit……………….. Birr

Item no Description Unit Qt unit rate Amount


A. SUB STRUCTURE
1. EXCAVATION AND EARTH WORK
1.1

Clear off the site to remove top soil to an


average depth of 200mm. M2 138.94 7.00 972.61
1.2

Bulk excavation in ordinary soil to reduce


level to a depth not exceeding 1500mm. M3 312.22 50.00 15,610.88
1.3

Ditto but exceeding 1500mm but not


exceeding 3000mm. M3 20.81 100.00 2,081.45
1.4
Bulk excavation in weathered basaltic rock to
reduce level for to a depth exceeding 3000mm
but not exceeding 4500mm. M3 0.00 0.00
1.5 Pit excavation in ordinary soil to a depth not
exceeding 1500mm from reduced ground
level. M3 50.63 100.00 5,062.50
1.6 Pit excavation in ordinary soil to a depth
exceeding1500mm but not exceeding 3000mm
from reduced ground level. M3 57.38 100.00 5,737.50
1.7 Trench excavationin ordinary soil to a depth
not exceeding 1500mm from reduced ground
level. M3 41.58 200.00 8,316.75
1.8 Trench excavationin ordinary soil to a depth
exceeding 1500mm from reduced ground
level. M3 47.13 200.00 9,425.65
1.9

Fill under slab with borrowed selected


material from quarry waste. The filling shall
be performed in layers of 200mm with
watering and compacting each layer properly. M3 249.77 20.00 4,995.48
2.0 Return fill around foundation with selected
excavated material from quarry waste and
well ram in layers not exceeding 200mm
thickness. M3 0.00
2.1 fill around masonry foundation wall externaly
with selected excavated material from quarry
waste and well ram in layers not exceeding
200mm thickness. 0.00
2.2

Load and cart away surplus excavated


material and deposit at an appropriate tip. M3 557.53 10.00 5,575.33
2.3
250mm thick basaltic or equivalent stone hard
core well rolled consolidated and blinded with
crushed stone. 144.08 M2 340.00 48,987.20
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
50mm thick2. lean
CONCRETE
concreteWORK
in C-5 with 0.00
2.1 minimum cement content of 150kg/m3 of 0.00
concrete under:
a) under floor slab M2 144.08 1.00 144.08
b) under footing pad M 2
15.00 500.00 7,500.00
c) under ground floor beam M2 44.42 500.00 22,211.25
2.2 10x100mm styropor foam expansion joint filler
between Grade beam and floor slab. Ml 128.84 100.00 12,884.00
Reinforced concrete class C-25 (with a 28-day
2.3 150mm cube crushing strength of 25MP)awith
minimum cement content of 360kg/m3 cast
into form work and vibrated around rod
reinforcement bar. - 0.00
a) In footing pad M 3
3.75 5,000.00 18,750.00
b) In foundation column M 3
1.39 5,000.00 6,962.50
c) In ground floor beam. M3 23.41 5,000.00 117,039.00
e) In steps M3 0.46 5,000.00 2,308.50
f) In 120mm thick ground floor slab M2 144.08 5,000.00 720,400.00
Provide, cut and fix in position sawn
f) In 100mmtimber
structural thick ramp
or steel form work M2 0.36 5,000.00 1,802.28
2.4 whichever is appropriate; - 0.00
a) To footing pad M2 12.00 200.00 2,400.00
b) To foundation column M 2
27.85 200.00 5,570.00
c) To grade beam M2 99.03 200.00 19,806.60
Steel reinforcement bar according to structural
d)Stair M2 1.15 200.00 229.50
drawing. Price includes cutting, bending,
e)Ramp
placing in position and tying wires,concrete M2 3.03 200.00 606.75
2.5 spacers and chairs; - 0.00
a) 8mm diameter deformed bar Kg 363.87 150.00 54,581.10
b) 10mm diameter deformed bar Kg 189.29 150.00 28,392.77
c) 12mm diameter deformed bar Kg 430.11 150.00 64,515.82
d) 14mm diameter deformed bar Kg 1,040.46 150.00 156,069.49
500mm thick 3. MASONRY
trachytic orWORK
equvalent stone - 0.00
3.1 500mm
masonry wall trachytic
thick or equivalent
below ground well
level bedded M3 108.04 3,200.00 345,715.20
3.2 dressed
in cement stone
mortarmasonry
(1:3) above
in full ground
joints. level
Masonry M 3
0.00
bedded infor steps mortar
cement and Ramps.Price
(1:3) in full
3.3 include pointing and other necessary M3 0.00
joints. Price shall include pointing.
activities. 4.Expansion
8 mm thick chipwood joint
depth 10 cm 0.00
4.01 between grade beam and floor slab painted m 0.00
two coats of Asphalt paint
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
B-SUPER STRUCTURE 0.00
0.00
1. CONCRETE WORK 0.00
1.1 Reinforced concrete class C-25(with a 28-day
150mm cube crushing strength of 25MP) with
minimum cement content of 360kg/m3
ordinary portland cement cast into form work
and vibrated around reinforcement bars; 0.00
a) In Column M3 11.33 5000.00 56,640.00
c) In roof Beams M3 5.40 5000.00 27,013.50
d) In gutter M3 1.92 5000.00 9,603.75
Provide, cut and fix in position sawn
e) Lintels timber or steel form work
structural M3 0.63 5000.00 3,171.00
1.2 whichever is appropriate; 0.00 0.00
a) To Elevation Column M2 35.65 200.00 7,129.60
c) To Roof Beams M2 54.02 200.00 10,803.60
d) To gutter M2 33.29 200.00 6,658.60
Steel reinforcement bar according to structural
drawing. Price includes cutting, bending,
e) Lintelsin position and tying wires and
placing 200.00 M2 10.69 2,137.60
1.3 concrete spacers; 0.00 0.00
a) 6mm diameter deformed bar Kg 0.00 150.00 0.00
b) 8mm diameter deformed bar Kg 717.09 150.00 107,563.75
c)10mm diameter deformed bar Kg 30.73 150.00 4,608.99
d) 12mm diameter deformed bar Kg 857.64 150.00 128,646.69
e) 14mm diameter deformed bar Kg 0.00 0.00 0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
2. BLOCK WORK 0.00
2.1 200mm thick class-B HCB wall bedded in M2 123.22 650.00 80,091.80
2.2 cement mortar
Ditto but mix (1:3)
150mm thickand both sides
including left for
paraphet M 2
121.50 650.00 78,977.12
plastering.
wall HCB quality shall be tested and
2.3 Ditto but 100mm
approved thick for papate wall
by the Enginner. M2 0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
3. ROOFING 0.00
3.01 Roof cover in G28 C.I.S nailed to Zigba m2 105.93 1,200.00 127,110.00
3.02 purlins,Price
Supply and fixshall include
100mm ridge PVC
diameter coverdown
and ml
roof measured in horizontal projection..
pipe as per the drawing, price shall include
metal strap1cm width with 28 guage supports
c/c 1000mm, wire strainer and all other
necessary accessories 21.60 600.00 12,960.00
3.03 Sheet metal coping with developmental length ml
of 2.914 52.83 600.00 31,698.00
3.04 Supply and fix wire mesh ventilation under m 2

veranda nailed to zigba wood battens size 40


x 50 mm. Price shall include zigba wood
battens with c/c spacing of 600mm both
ways, corner and middle list and all other 0.00
necessary accessories.
0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
0.00
4. CARPENTRY AND JOINERY 0.00
4.01 Supply, assemble and mount Φ 120mm ml 455.87 40.00 18,234.80
4.02 eucalyptus wooden truss
Supply, assemble and mount Φ 80mm as per the detail
ml 161.74 40.00 6,469.56
drawing. Price
eucalyptus wooden shalltruss
include
as perantithetermite
detail
4.03 Supply and
treatment Price fix 50x70
,tie bar mm Zigba wood purlin ml 386.73 40.00 15,469.20
drawing.
as per the detail shallof include
drawing
Φ6mm anti
. Price
and termite
other
shall include
4.04 Supply
treatmentand fix
,tie fascia board
bar ofand Φ6mm 250x25mm. Price
andnecessary
other ml - 0.00
anti termite
includes treatment
onefixcoat primer all two
and othercoats of oil
4.05 Supply and
accessories. 8 mm thick chip wood ceilings m 2
0.00
paint
as perandtheother necessary
engineers activity Price
approval. needed to
shall
4.06 Supplyand
complete fix 20mm thick styrofoam m2 - 0.00
include 40the
insulating x 50work.
panels mmoverZigba
the wood battens
chipwood with
ceiling as
4.07 Supply
c/c and fix
spacing 7 mm thick
bothPVC ceilings as and
per m 2
112.57 600.00 67,542.27
indicated onof
the engineers the600 mm
drawing
approval.
ways, middle
Price shall include
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
battens with c/c spacing of 600 mm both
5. METAL
ways, middle WORKS and corner list, and all other 0.00
5.1 Metal window and doors made of 38x1.5mm 0.00
LTZ profiles shown on the drawings.Price
WINDOWS 0.00
include approved quality locks and all iron
a) Type W1
mongry = size:
works, two1720x815MM
coats of anti rust, three Pcs 4.00 10,000.00 40,000.00
b) Type W2 = size: 1720x1230mm Pcs 3.00 10,000.00 30,000.00
c) Type W3 = size: 845x1720mm Pcs 1.00 10,000.00 10,000.00
d) Type W4 = size: 1260x1075mm Pcs 10,000.00 0.00
e) Type TW1 = size: 815x645mm Pcs 10,000.00 0.00
f) Type TW2 = size:1645x665mm Pcs 10,000.00 0.00
DOORS 0.00
a) Type D1 = size: 2150x845mm 15,000.00Pcs 0.00
b) Type D2 = size: 2795 x 845mm Pcs 15,000.00 0.00
c) Type D3 = size: 2795 x 845(800x685)mm Pcs 4.00 15,000.00 60,000.00
d) Type D5= size: 2795 x 1260mm Pcs 15,000.00 0.00
e) Type D7 = size: 2795 x 1645mm Pcs 15,000.00 0.00
f) Type DW4 = size: 1675X796(830 x175)mm Pcs 15,000.00 0.00
Ventilation window manufactured from
g) Type D8 =LTZ
38x1.2mm size: 700 x 2150mm
profile frame and chicken Pcs 15,000.00 0.00
5.13 wire mesh. Price shall include one coat of No 15,000.00 0.00
anti rust and two coats of syntetic enamel
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
paint Size 845x400mm 0.00
7. FINISHING 0.00
7.01 Apply three coats of plastering in cement 0.00
sand mortar wall
a) To internal (1:3).surface
Price shall include pre-
m2 110.80 300.00 33,238.82
cleaning and preparation of the surface.
b) To exposed beams and columns. m 2
39.69 300.00 11,907.60
7.02 (internal
Ditto but /external)
two coats to receive ceramic wall tile m2 116.54 300.00 34,962.57
7.03 8mm thick approved quality of 300*200 m2 116.54 300.00 34,962.57
7.04 mmTabor
Apply one ceramic wall Coat)
coat (3rd tiles toGypsum
different
300.00 0.00
rooms as
plastering per the finishing
onwallcement sand mortar Price
Schadual. (1:3)
7.05 a) To internal
includes cement surface backing
mortar and joints m2 55.94 300.00 16,781.66
plastering . Price shall include pre-cleaning
7.06 b)
andTo internal beams
preparation of theand columns
surface. 300.00 0.00
7.07 Apply one coat (third coat) plastering in 300.00 0.00
7.08 cement
Applyone sand mortar
coats of (1:3) and
plastering above
one ceramic
coat of
walls . Price shall include pre-cleaning
tyroline rendering in cement sand mortar and m2 75.96 300.00 22,788.99
preparation
(1:3) of
to External the surface.
7.09 Apply pointing parapet wall HCB wall with
for external m 2
47.25 300.00 14,176.46
7.10 cement sand mortar (1:3)
50 mm thick smooth finished cement sand m2 144.08 300.00 43,224.00
7.11 screed(1:3)
Supply floor
and finish cast.All as per engineers
terrazzo tiles m2 57.88 600.00 34,729.05
instruction.
(200*200mm*20mm) flooring .Price shall
7.12 100x20mm terrazo tile skirting stuck to wall ml 23.21 600.00 13,923.00
include
with cement48mm thick(1:3)mix.
cement And mortar & joints
7.13 Supply
grouted and mortar
work fix
with 200x200x6mm
white cement and
chamfered
thick Tabor
material m2 116.54 600.00 69,925.14
at the edge
ceramic floor tiles with cement mortar backing
7.14 supply and fix the window sill is granite with ml 7.77 600.00 4,659.00
with 2mm joints
3cm thickness to be grouted
,chamfered at the with white
7.14 Supply
cement. & groove
fix approved PVC tilesedge,with
flooring 60.50 600.00 36,302.40
dripping
stuck to cement and
screed sloped
of sizes outside
300x300x2mm and
7.14 100x2mm
bedded on imported
cement plastictotile
mortar) HCB skirting
wall stuck 48.78 600.00 29,268.60
asbesotos
to wall with freeapproved
hard improted (madeglue.in
7.14 1000mm
England wideor 80mmtype
andItaly) thick
with
adhesive
C-20approved
pre-cast
brown
concretecolor)
pavement around the building
bedded on 100mm thick sand/red ash base
and joint pointed in cement and sand mortar
mix 1:3. Price includes the sand/red ash base
& pointing all as per the detail dawings. m2 66.74 600.00 40,046.40
0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
Supply and fix 4 mm thick frosted glass to
8. GLAZING 0.00
8.01 windows
Supply andand doors
fix 4according to the drawing
mm clearglass .Price
to Internal
shall include putty and all drawing
the necessary m² 18.36 1,500.00 27,532.95
8.01 windows according to the .Price fixing
shall
accessories.
include putty and all the necessary fixing m² 0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr
accessories. 0.00
9. PAINTING 0.00
9.01 Apply three coats of synthetic emulsion paint m² 110.80 90.00 9,971.64
9.02 to
Dittointernal plastered
but to external wallwall
pointed surface.as
surface per m² 47.25 90.00 4,252.94
Engineers and client selaction and Approval
9.03 Ditto but to chip wood ceiling. m² 0.00
TOTAL CARRIED TO SUMMARY………………………............ Birr 0.00
10. SANITARY INSTALLATION 0.00
INTERNAL 0.00
10.01 Supply and install Galvanized Steel Pipes for
cold water distribution to all sanitary fixtures
according to the drawing complete with the
necessary pieces such as tees, bends,unions,
etc. The unit price sgall include all necessary
assistance to the installation works such as
supports for horizontal & vertical pipes,
chiseling of walls, slabs, beams, floors, etc. and
closing them with concrete or cement mortar
to normal condition. The installation shall be
tested at a pressure of 10 kg/scm at the
expense of the contractor.

0.00
Diameter 15 mm m.l 10.00 700.00 7,000.00
10.02 Supply & fix Gate Valves of approved quality
complete with unions, hand wheels etc.
700.00 0.00
Diameter 15 mm No. 7.00 700.00 4,900.00
700.00 0.00
SANITARY INSTALLATION & FITTINGS 700.00 0.00
700.00 0.00
10.03 Supply & fix Tabor ceramic hand wash basins
made from white vitreous china complete
with concealed fixing bracket, plugs, chains
smell traps, flexible pipe cold water taps,
adapters, etc.
700.00 0.00
Size 405*500 mm No. 2.00 700.00 1,400.00
10.04 Supply & fix double bowl stain less steel sink
complete with all accessories including a
drained removable strainer, chrome plated hot
and cold water mixing taps.
No 1.00 700.00 700.00
10.05 Supply & fix single bowl Laboratory sink
complete with all accessories including a
drained removable strainer, chrome plated hot
and cold water mixing taps. No 1.00 700.00 700.00
10.06 Supply and fix floor drains made of enameled
cast iron with smell trap complete with all the
accessories. 700.00 0.00
Diameter 50 mm No. 2.00 700.00 1,400.00
10.07 Supply and fix 10mm reinforcement bar as
towel rail, embed in wall with cement mortar,
length 60cm No. 2.00 700.00 1,400.00
10.08 Supply & fix Tabor ceramic soap holders
complete with fixing accessories No. 2.00 700.00 1,400.00
10.09 Supply & install soil waste and vent pipe in
horizontal branches and vertical stacks made
of rigid plastic pipes (PVC) of approved
standard including all ncessary fitting, such as
bends Y.T clean outs, increasing and reducing
pieces with tight joints as shown on the
drawong. All horizontal branches shall be laid
in a slope of 2%. The unit price shall include
all necessary masonry assistance such as
chiseling of walls.slabs, beams floor etc. and
closing them with concrete or cement mortar.

700.00 0.00
Diameter 50 mm m.l. 12.00 700.00 8,400.00
10.11 Supply & fix approved quality of fire
extinguisher to be mounted on the wall size
9kg. 700.00 0.00
No. 1.00 700.00 700.00
TOTAL CARRIED TO
SUMMARY………………............ Birr 700.00 0.00
11. ELECTRICAL INSTALLATION 700.00 0.00
700.00 0.00
All distribution boards, breakers, switches,
accessories etc, should be genuine legrand,
ABB, siemens or approved equivalents
complying with IEC standardds distribution
boards, should be made of sheet metal (PVC
Boards) and have separate neutral and ground
bus bars/phase bars. All units in the
distriution boards should be labeled to give
the reference and duty of the unit

700.00 0.00
11.01 Flush mounted main distribution OPD in
sheet steel enclouser with lockable door.
Bus bar rating of 50A/3ph, Earthing lead
and with all its accessories and enough
ample space for future expansion
consisting of:-
700.00 0.00
1pc m.c.b of 25A/1ph 700.00 0.00
4pc m.c.b of 16A/1ph 700.00 0.00
2pcs m.c.b of 10A/1ph 700.00 0.00
2pcs m.c.b of 10A/1ph No 1.00 700.00 700.00
700.00 0.00
LIGHT POINT 700.00 0.00
700.00 0.00
11.02 Surface mounted light point fed through PVC
insulated copper conductor of 3x2.5 sg.mm
inside PVC conduit of 13mm diameter
including junction boxes with covers,
insulating screw caps etc.
No 24.00 700.00 16,800.00
700.00 0.00
LIGHTING FITTINGS 700.00 0.00
700.00 0.00
11.03 Philips TCS 098/236 2xTLD 36W ML No 4.00 700.00 2,800.00
11.04 Philips TMX 204 1x6W IC No 20.00 700.00 14,000.00
11.05 Socket outlet of 16A/1ph, LEGRANDE 700.00 0.00
74131 + frame 10921, fed through PVC
sheathed flexible wire of 1x2.5 Sq.mm inside
DLT Trunking LEGRAND 10412 80x50mm.
All for surface mounting. No 18.00 700.00 12,600.00
700.00 0.00
TELEPHONE POINT 700.00 0.00
700.00 0.00
11.06 Telepone point fed through PVC sheathed
copper wire 2x0.80 inside pvc condit of
mimimum diameter 19mm No 1.00 700.00 700.00
11.07 Telephone box 300x200x80mm No 1.00 700.00 700.00
TOTAL CARRIED TO
SUMMARY………………………............ Birr 3,196,137.80
Qty L/W/D Product Description & Sketches
A-SUB STRUCTURE
1.EXCAVATION & EARTHWORK
1.01Site clearing and removing of top 200mm
thick soil Including walk way
21.71
6.40
138.94 m2

1.2 Pit excavation in ordinary soil to a depth not


exceeding 1500mm from reduced ground level.
15 1.5
1.5
1.5
50.63

1.2 Pit excavation in ordinary soil to a depth


exceeding 1500mm from reduced ground level.
15 1.5
1.5
1.7
57.38

1.3 Trench excavationin ordinary soil to a depth


not exceeding 1500mm from reduced ground
level.
on axsis X01-X03
5 3.4
0.5
1.5
12.75
on axsis Y01-Y06
3 12.815
0.5
1.5
28.83
41.58

1.3 Trench excavationin ordinary soil to a depth


exceeding 1500mm from reduced ground level.
on axsis X01-X03

5 3.4
0.5

1.7

14.45

on axsis Y01-Y06

3 12.815
0.5
1.7
32.68
47.13
1.4 Bulk Excavation in ordinary soft to a depth
not excedding 1.5m
L=19.01+pavement +working space
W=6.6+pavement +working space
L=19.01+(1.2x2)+(0.25x2)
W=6.6+(1.2x2)+(0.25x2)
L=21.91m
W=9.5m
1 21.91 d=1.5m
9.5
1.5
312.22 Total volume
1.4 Ditto but excedding 1.5m
1 21.91 L=21.91m
9.5 W=9.5m
0.1
20.81 Total volume
1.5 Selected Borrowed fill material
1 21.91 depth 0.4m
9.5 L=21.91m

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
1.2 W=9.5m
249.77 Total volume
1.6 cartway surplus excvate material to
appropriate disance
sum of item 1.1+1.2+1.3+1.4
1 557.533
557.53
1.7 250mm thick basaltic or equivalent
hardcore
1 18.01 L=18.01m
8 W=6m
144.08
2. Concrete Works
50 mm C-5 lean concrete, minimum cement
content 150 kg/m3 Under,
3 18.615 a) under grade beam
0.5 on axis X/01-X/05
27.92
5 6.6
0.5 ditto but on axis y/01-y/08
16.50
44.42 Total
b) under footing pad
15 1
1
15.00

2.2 10cm thick reinforcement concrete floor slab


144.08 m2
2.3 Reinforcement concrete C-25
5 6.6 a) In under ground grade beam
0.4 on axis X/01-X/03
0.15
1.98
3 19.01 ditto but on axis y/01-y/06
0.4
0.15
3.42
5 6.6 b) In grade beam
0.5 on axis X/01-X/03
0.4
6.60 Total
3 19.01 ditto but on axis y/01-y/06
0.5
0.4
11.41 Total
23.41 Total Volume
15 1.0 b) In footing pad
1.0
0.25
3.75
10 2.5 c) In foundation column
0.2
0.2
1.00
5 2.5 area =3.14*0.1*0.1=0.0314
0.0314
0.39
1.39 Total Volume

C) Stair
2.5 0.30
0.15
1.2 0.13

1 0.11
1.073
1.2 0.14

1 0.11
1.402
1.2 0.19
0.46 m3
D) Ramp
1 0.12

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
2.612
1.2 0.36 m3

2.4 Form works


10 6.6 a) To under ground grade beam
0.4 on axis X/01-X/03
26.40 Total
6 19.01
0.4 on axis y/01-y/06
45.62 Total
b) To ground grade beam
10 6.6 on axis X/01 and X/03
0.15
9.90
6 19.01
0.15 on axis y/01 and y/06
17.11
99.03 Total
60 1 b) To footing pad
0.2
12.00 Total
COLUMN
40 2.5
0.2
20.00 Total
Area =2*3.14*0.1
5 2.5
0.628
7.85
27.85
C) STAIR
2 2.475
0.15 0.74

5 0.3
0.15 0.22

4 0.3
0.15 0.18
1.15 m2
d) Ramp
2 2.612
0.115 0.60

1 1.2
0.115 0.14

3.03 m2
2.04 Mild steel reinforcement
a) Dia. 6mm plain bar
- 0.00 See annexed rebar schedule sheet
0.00 kg

b) Dia. 8mm deformed bar


0 0.00 See annexed rebar schedule sheet
363.87 kg

c) Dia. 10mm deformed bar


0 0.00 See annexed rebar schedule sheet
189.29 kg

d) Dia. 12mm deformed bar


0.00 0.00 See annexed rebar schedule sheet
430.11 kg

d) Dia. 14mm deformed bar


0.00 0.00 See annexed rebar schedule sheet
1,040.46 kg

10x100mm styropor foam expansion joint filler between


Grade beam and floor slab.
8 6.6 52.8 a)b/n grade beam and floor slab
on axis X/01-X/03

4 19.01 76.04 ditto but on axis y/01-y/06

128.84 ml
3. MASONRY WORKS

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches

3.01 50cm thick masonry foundation


90.03 Depth of masonry=1.2 m
1.2 108.04
108.04 m3
B - SUPER STRUCTURE

1. CONCRETE WORKS
Ht. of column=3.2m
Size of column=0.20m x 0.20m
No. of columns=10
10 3.2
0.2 1.01 C-20 RC:
0.2 1.28 a) In elevation columns
m3
Area =2*3.14*0.1=0.628
5 3.2
0.628
10.05
11.33
CL length of roof beam (half block)=
90.05 b) In roof beams
0.2
0.3 5.40
5.40 m3
b) In lintels
15.86 Tot. L=8*(.815+2*0.2)+3*(1.645+2*0.2)
0.2
0.2 0.63
0.63 m3

b) Ingutter
1 25.61
0.5
0.15
1.92
1.02 Formwork:

a) To elevation columns & lintels

10 3.200 (Permtr=4*0.2=0.80m)
0.8 25.60 To columns

5 3.200 (permiter=2*3.14*0.1)
0.628 10.05
35.65
19.28 To lintels
0.6 11.57 Tot. L=8*(.815+2*0.2)+3*(1.645+2*0.2)
m2
-4.4
0.2 -0.88
10.69 m2
b) To roof beams

6 19.01
0.3 34.22

10 6.6
0.3 19.80
54.02
C) To gutter
2 25.61
0.65
33.293
1.03 Mild steel reinforcement

a) Dia. 6mm plain bar


0.00 0.00 See annexed rebar schedule sheet
0.00 kg

b) Dia. 8mm plain bar


717.09 717.09 See annexed rebar schedule sheet
717.09 kg

c) Dia. 10mm deformed bar


30.73 30.73 See annexed rebar schedule sheet
30.73 kg

d) Dia. 12mm deformed bar

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
857.64 857.64 See annexed rebar schedule sheet
857.64 kg

e) Dia. 14mm deformed bar


0.00 0.00 See annexed rebar schedule sheet
0.00 kg
2. BLOCK WORK
2.01 200mm thick class C HCB

Total Length=2*(19.01+4.55)-(10*0.2)
45.12 =45.12m
3.2 144.38 Gross area

-3 0.825
2.13 -5.27 Deduct D3L Door

-3 0.82
0.6655 -1.64 Deduct D3L Window

-1 0.825
2.13 -1.76 Deduct D3R Door

-1 0.82
0.6655 -0.55 Deduct D3R Window

-2 0.815
1.72 -2.80 Deduct W1L window opening

-2 0.815
1.72 -2.80 Deduct W1R window opening

-3 1.23
1.72 -6.35 Deduct W2 window opening

123.22 m2

2.02 150mm thick class C HCB


3 4.15 laboratory,Treatment,VCT and Examination
3.2 39.84 m3

2 7.2 Paraphet wall


1.523 21.93

2 19.61
1.523 59.73

121.50

3. ROOFING
3.01 G28 CIS roof cover
A1=(18.815+6.4)/2*3.251*2=81.97
A2=1/2*(6.4*3.743)*2=23.955
105.925 105.93
105.93 m2

3.04 Sheet metal coping with developmental length of


2.914
52.83 52.83 L=2*(18.815+.6+6.4+.6)=52.83m
52.83 ml

3.05 PVC down pipe

3 3.6 10.8 Front

3 3.6 10.8 Rear


21.60 ml

4. CARPENTRY & JOINERY

Truss(T1 and T2)


261.26 Dia 120cm eucal,(bot.+toP.)=261.26
261.26

161.739 Dia 80cm eucal,(v.+diag.)=332.928


161.739

4.02 50x70 mm zigba wood purlin


386.73 386.73
386.73 ml

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
4.04 plastic ceiling
4.15
5.015 20.81 LABOURATORY

4.15
4.744 19.69 Treatment

4.15
4.86 20.17 VCT

4.15
3.574 14.83 Examination

19.01
1.95
37.07 Covered walk way
112.57

5. METAL WORK
WINDOWS
2 1 2 5.01 W1L size: 815X1720mm
2.00 No.

2 1 2 5.02 W1R size: 815x1720mm


2.00 No.

3 1 3 5.03 W2 size: 1230X1720mm


3.00 No.

1 1 1 5.03 W3L size: 845X1720mm


1.00 No.
DOORS

3 1 3 5.04 D3L size: 845x2795 mm


3.00 No.

1 1 1 5.05 D3R size: 845x2795 mm


1.00 No.

7. FINISHING
7.01 1st and 2nd cement plaster 3rd gypsum plastering to
internal wall
Height=3.2+0.3=3.5m
1 19.015
3.5 66.55 Coverd walkway

-3 0.825
2.13 -5.27 Deduct D3L Door

-3 0.82
0.6655 -1.64 Deduct D3L Window

-1 0.825
2.13 -1.76 Deduct D3R Door

-1 0.82
0.6655 -0.55 Deduct D3R Window

-1 0.815
1.72 -1.40 Deduct W3L opening (815x1720 mm)

55.94 m2

3rd coat of plastering to internal wall surface


2 9.165
1.7 31.16 lABORATORY(excl. 1.8m high ceramic wall)

-1 0.825
0.33 -0.27 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

-1 0.815
0.725 -0.59 Deduct W3L opening (815x1720 mm)

-1 1.23
0.725 -0.89 Deduct W2 window opening

-1 0.815
0.725 -0.59 Deduct W1L window opening

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
2 8.894 (excl. 1.8m high ceramic wall)
1.7 30.24 Treatement

-1 0.825
0.33 -0.27 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

-1 0.815
0.725 -0.59 Deduct W1L window opening

-1 0.815
0.725 -0.59 Deduct W1R window opening

2 9.01 (excl. 1.8m high ceramic wall)


1.7 30.63 VCT

-1 0.825
0.33 -0.27 Deduct D3R Door

-1 0.82
0.33 -0.27 Deduct D3R Window

-1 0.815
0.725 -0.59 Deduct W1L window opening

-1 0.815
0.725 -0.59 Deduct W1R window opening

2 7.724 (excl. 1.8m high ceramic wall)


1.7 26.26 EXAMINATION

-1 0.825
0.33 -0.27 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

-1 1.23
0.725 -0.89 Deduct W2 window opening

110.80
To exposed beam
51.22
0.6 30.732 m2

To exposed column
14 0.2
3.2 8.96 m2
39.69

7.02 Ditto but two coats to receive


ceramic wall tile (to 1.8m height)

2 9.165
1.8 32.99 lABORATORY(excl. 1.8m high ceramic wall)

-1 0.825
1.8 -1.48 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

-1 0.815
0.725 -0.59 Deduct W3L opening (815x1720 mm)

-1 1.23
0.725 -0.89 Deduct W2 window opening

-1 0.815
0.725 -0.59 Deduct W1L window opening

2 8.894 (excl. 1.8m high ceramic wall)


1.8 32.02 Treatement

-1 0.825
0.33 -0.27 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
-1 0.815
0.725 -0.59 Deduct W1L window opening

-1 0.815
0.725 -0.59 Deduct W1R window opening

2 9.01 (excl. 1.8m high ceramic wall)


1.8 32.44 VCT

-1 0.825
0.33 -0.27 Deduct D3R Door

-1 0.82
0.33 -0.27 Deduct D3R Window

-1 0.815
0.725 -0.59 Deduct W1L window opening

-1 0.815
0.725 -0.59 Deduct W1R window opening

2 7.724 (excl. 1.8m high ceramic wall)


1.8 27.81 EXAMINATION

-1 0.825
0.33 -0.27 Deduct D3L Door

-1 0.82
0.33 -0.27 Deduct D3L Window

-1 1.23
0.725 -0.89 Deduct W2 window opening

116.54
7.03 tyroline rendering toparaphet wall

2 26.415
1.523 80.46

14 -0.2 deduct columns


1.606 -4.50

75.96 m2

7.04 Pointing to external HCB

47.3 47.3 To 200mm thich Class C HCB (Item 2.01)

47.25 m2

7.05 Floor finish


Pvc tile
4.74
4.15 19.67 Treatment

1 0.825
0.2 0.17 Add under D3L

4.86
4.15 20.17 VCT

1 0.825
0.2 0.17 Add under D3R

4.86
4.15 20.17 Examination

1 0.825
0.2 0.17 Add under D3L
60.50
Terrazo tile
5.015
4.15 20.81 Labortory

19.01
1.95 37.07 Coverd walkway

57.88 m2
Skirting
Pvc tile
2 8.894 17.79 Treatment

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches

-1 0.825
-0.825 Add under D3L

2 9.01 18.02 VCT

-1 0.825
-0.83 Add under D3R

2 7.724 15.45 Examination

-1 0.825
-0.83 Add under D3L

48.78 ml
Terrazo tile

2 9.16 18.32 Laboratory

-1 0.825
-0.825 Add under D3L

1 9.01 9.01 coverd walkway

-4 0.825
-3.3 Add under D3L

23.21 Ml

7.06 1.2mm thick formed window sill


Winds. (W1L,W1R,W2 &w3)
=2*0.815+2*0.815+3*1.23+1*0.815

7.765 7.765
7.77 ml

7.07 150x150x6mm thick ceramic wall tile

116.54 116.5419 Same as Item 7.02 (to 1.5m height)


116.54 m2

7.08 1000mm wide & 80mm thick C-20


precast concrete pavement around bldg
(Width of walkway is 1.2m in dwg,
2 27.81
1.2 66.74
66.74 m2

8. GLAZING

8.01 4mm thick clear glass


2 0.815
1.72 2.80 To W1L (815x1720mm)

2 0.815
1.72 2.80 To W1R (815x1720mm)

3 1.23
1.72 6.35 To W2 (1230x1720mm)

1 0.815
1.72 1.40 To W3(815x1720mm)

2 1.01
0.825 1.67 To D3L & D3R (door part 845x1560mm)

4 1.01 To D3L (window part 830x1560mm)


0.825 3.33

18.36 m2
9. Painting

9.01 3 coats of synthetic emulsion paint


to internal wall surface

110.80 110.80 Same as Item 7.01

Prepared by........................... Certified by............................. Approved by...........................


Qty L/W/D Product Description & Sketches
110.80 m2

9.02 Ditto but to external pointed wall

47.25 47.25 Same as Item 7.04


47.25 m2

Prepared by........................... Certified by............................. Approved by...........................


IPD block

SUB - STRUCTURE

Drg.No Location Ref No Shape Dia Length No of bar

Footing pad 14 1.20 16


undere ground beam
on axis X/01-X/03 10 10.47 3
10 9.20 3
8 0.40 95
ditto but on axis y/01-y/05 10 7.21 3
8 0.40 32

Foundation column 12 4.08 6


Stirrup 8 0.70 14
Stirrup circular 8 0.48 14
Grade beam 14 8.16 3
on axis X/01-X/03 14 11.68 3
14 10.47 3
14 9.20 3
8 1.20 95
ditto but on axis y/01-y/08 14 7.21 3
14 7.21 3
8 1.20 32
Stair 12 3.41 9
12 2.48 9
12 0.57 9
12 0.55 9
8 1.20 26
Ramp 12 2.61 9
12 2.33 9
8 1.20 14

Weight per M
Total weight (kg)
No of
member Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia20 Dia24 236

15 288

3 94.23
3 82.791
3 114
6 129.762
6 76.8

15 366.75
10 98
5 33.6
3 73.458
3 105.138
3 94.23
3 82.791
3 342
5 108.135
5 108.135
5 192
1 30.726
1 22.311
2 10.188
2 9.9
1 31.2
1 23.508
1 20.97
2 33.6
- 921.20 306.78 484.35 859.89 - - -
Weight per M 0.222 0.395 0.617 0.888 1.21 1.578 2.468 3.55
Total weight (kg) 0.00 363.87 189.29 430.11 1040.46 0.00 0.00 0.00
IPD block

SUPER - STRUCTURE
No of
Drg.No Location Ref No Shape Dia Length No of bar member Dia 6 Dia 8
Elevation column
12 3.51 6 15
8 0.70 16 10 112
stirab Circular 8 0.48 16 5 38.4
Slab
bar1 8 1.68 101 1 169.175
bar2 8 4.84 34 1 164.56
bar3 8 4.03 101 1 406.525
bar4 8 4.67 34 2 317.22
bar5 8 3.39 34 1 115.396

Sub merged beam


10 4.15 4 3
8 0.64 22 1 14.146

LINTEL
12 1.62 2 8
12 1.21 2 8
12 2.45 2 4
12 2.05 2 4
Top tie beam
RB1 12 8.01 3 3
12 12.00 3 3
12 10.61 3 3
12 9.13 3 3
8 1.00 91 3 273
RB2 12 7.02 3 5
12 7.02 3 5
8 1.00 41 5 205
- 1,815.42
Weight per M 0.222 0.395
Total weight (kg) 0.00 717.09
Dia 10 Dia 12 Dia 14 Dia 16 Dia20 Dia24 236

316.26

49.8

25.84
19.44
19.56
16.36

72.09
108
95.49
82.206

105.285
105.285

49.80 965.82 - - - -
0.617 0.888 1.208 1.578 2.468 3.55
30.73 857.64 0.00 0.00 0.00 0.00

You might also like