Bill of Quantity

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


A. SUB STRUCTURE
1 EXCAVATION & EARTH WORK
1.1 Clear of site to remove top soil to a depth of
20cm thick starting from natural ground level M2 824.36 10.00 8,243.55
1.2 Bulk excavation to a depth not exceeding 70cm. M3 165.90 50.00 8,295.00
1.3 Excavation for isolated footing in ordinary soil to
a depth not exceeding 200cm starting from
reduced level M3 1,088.80 50.00 54,440.00
1.4 Trench foundation excavation in ordinary soil
3
Ditto M 27.84 50.00 1,391.75
1.5 Backfill around foundation with good dry fill
material from site and well ram in layers not
3
exceeding 20cm thick M 866.97 50.00 43,348.30
1.6 Fill under hardcore with selected borrowed
material from site and well ram in layers 3
M 17.83 150.00 2,674.50
1.7 Cart away surplus excavation material to an
appropriate tip M3 1,239.92 50.00 61,996.20
1.8 25cm thick basaltic or equivalent stone hard core
well rolled consolidated and blinded with
crushed stones M2 178.34 115.00 20,509.22
Total Carried to summary Birr ……………………………………………………………... 200,898.52

2 CONCRETE WORK
2.1 5cm thick lean concrete class C-5, under footing
2
and masonry foundation wall M 333.33 90.00 29,999.25
2.2 10cm thick reinforced concrete ground floor slab
in C-15 with minimum cement content of 280
2
kg/m3 well spread and leveled M 56.77 330.00 18,732.48
2.3 Reinforced concrete class C-30, with minimum
cement content of 360kg/m3 filled into form
work and vibrated around rod reinforcement.
Steel and form work measured separately.
a. In footings 3
M 212.23 2,300.00 488,138.20
b. In foundation column 3
M 9.60 2,300.00 22,080.00
c. In grade beam M3 54.58 2,300.00 125,534.00
2.4 Provide cut and fix in position sawn zigba wood
form work
a. To footing 2
M 398.58 240.00 95,659.20
b. To footing column 2
M 96.00 240.00 23,040.00
c. To grade beam 2
M 280.40 240.00 67,296.12
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
2.5 Reinforcement steel bars according to structural
drawings. Price includes cutting, bending,
placing in position & trying wires.
Diameter 8mm deformed bars kg 814.67 29.00 23,625.36
Diameter 10mm deformed bars kg 251.23 29.00 7,285.67
Diameter 12mm deformed bars kg 263.74 29.00 7,648.34
Diameter 16mm deformed bars kg 1,810.60 29.00 52,507.32
Diameter 20mm deformed bars kg 308.20 29.00 8,937.80
Diameter 24mm deformed bars kg 1,722.96 29.00 49,965.84
Diameter 28mm deformed bars kg 152.00 29.00 4,408.00
Total Carried to summary Birr ……………………………………………………………... 970,483.75
3 MASONRY WORK
3.1 50cm thick hard trachytic or equivalent stone
masonry foundation wall bedded in cement
3
mortar mix 1:3 M 27.84 760.00 21,154.60
Total Carried to summary Birr ……………………………………………………………... 21,154.60

Total (A)………………………………………………………
1,192,536.87 =
B. SUPER STRUCTURE
1 CONCRETE WORK
1.1 Reinforced concrete class C-30, with minimum
cement content of 360kg/m3 filled into form
work and vibrated around rod reinforcement.
a. In elevation column M3 88.18 2,300.00 202,823.17
b. In lintel, floor, and top tie beams 3
M 0.00 2,300.00 -
c. In stair case M3 0.00 2,300.00 -
1.2 Provide cut and fix in position sawn zigba wood
form work
a. To elevation column 2
M 1,442.46 240.00 346,189.62
b. To lintel, suspended, and top tie beams 2
M 2,260.20 240.00 542,447.40
c. To stair case 2
M 1,587.05 240.00 380,891.66
1.3 Reinforcement steel bars according to structural
drawings. Price includes cutting, bending,
placing in position & tying wires
Diameter 10mm deformed bars kg 1,722.01 29.00 49,938.26
Diameter 12mm deformed bars kg 1,853.90 29.00 53,763.02
Diameter 16mm deformed bars kg 2,124.95 29.00 61,623.48
Diameter 20mm deformed bars kg 4,135.78 29.00 119,937.62
Diameter 24mm deformed bars kg 34,526.28 29.00 1,001,262.12
Diameter 28mm deformed bars kg 156.36 29.00 4,534.44
Total Carried to Summary Birr …………………………….……………………….. 2,763,410.80

2 MASONRY & BLOCK WORK


2.1 Hollow concrete block wall bedded in cement
mortar both sides left for plaster
a. 20cm thick 2
M 3,399.39 185.00 628,886.71
b. 15cm thick 2
M 625.20 170.00 106,284.00
Total Carried to Summary Birr ………………………………..…………………….. 735,170.71
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
3 METAL WORK
Glazed Aluminum windows and doors including
cylindrical lock and pointed with one coat printer
two coats of synthetic enamel paint. Price
includes glazing.
3.1 2
Window M 876.51 2,450.00 2,147,442.64
3.2 2
Door M 391.53 2,450.00 959,248.50
Total Carried to Summary Birr …………………………………….. 3,106,691.14
4 FINISHING
Apply two coats of plaster in cement mortar
4.1 To external HCB wall, masonary wall, concrete
2
beam and column surface M 2,304.60 185.00 426,351.00
4.2 To internal wall surface, ditto M
2
1,547.95 185.00 286,370.82
4.3 To concrete ceiling and belly of staircase 2
M 506.35 185.00 93,675.23
4.4 Apply final coats of fine cement plaster to
external plastered wall surface M2 2,304.60 225.00 518,535.00
4.5 Apply final coat of gypsum to internal plastered
2
wall surface. M 2,054.30 45.00 92,443.64
4.6 1.5cm thick non slippery ceramic floor tile
bedded on and including 3.5cm thick cement
2
Sand screed and jointed in cement mortar 1:3 M 1,586.40 900.00 1,427,760.00
4.7 Perque floor tile, ditto 2
M 568.87 1,700.00 967,079.00
4.8 10/2cm ceramic tile skirting stuck to wall on and
including cement mortar backing Ml 5,060.00 90.00 455,400.00
4.11 Perque tile skirting, ditto Ml 5,060.00 170.00 860,200.00
4.12 Ceramic wall tile applied to plastered wall on and
including cement sand mortar bedding and white M
2
1,500.00 900.00 1,350,000.00
cement grout
Total Carried to Summary Birr ………………….…………………………….. 6,477,814.69
5 PAINTING
Prepare and apply three coats of plastic
emulssion paint
5.1 To internal plastered wall surface M2 47.95 90.00 4,315.54
5.2 To plastered ceiling surface M2 506.35 90.00 45,571.73
5.3 Prepare and apply quartz paint to external wall 2
M 2,304.60 285.00 656,811.00
Total Carried to Summary Birr …………………..………………………….. 706,698.27

Total (B)………………………………………………………
13,789,785.61 =
A+B………………. 14,982,322.47